You are on page 1of 204

QATAR ARMED FORCES

QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 25.03.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping and mechanical
Site Work : Block work is in progress in area A. wall piping.
Housekeeping .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries :one ton steel received and blocks of 4" Plants,Equipments and/off site :
-1320-No. Received Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-17, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No.


Date : 26.03.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping and mechanical
Site Work : Block work is in progress in area A. wall piping.
Housekeeping is maintained.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 8" Blocks of-1404no.received Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-17, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 27.03.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping and mechanical
Site Work : Block work is in progress in area A. wall piping.
Housekeeping is maintained.
Lintel Formwork in area A is started.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 8" Blocks of-1404no.received Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-18, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 29.03.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping and mechanical
Site Work : Block work is in progress in area A. wall piping.
Housekeeping is maintained.
Lintel Formwork in area A is in progress.
Lintel reinforcement in area A is started
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-18, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No.


Date : 30.03.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping and mechanical
Site Work : Block work is in progress in area A. wall piping.
Housekeeping is maintained.
Lintel Formwork in area A is in progress.
Lintel reinforcementin area A is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 8" Blocks of-4212no.received Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-17, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No.


Date : 31.03.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Inspection for Lintel Formwork & reinforcement in area A is completed.
Block work setting out in area C is started.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 8" Blocks of-1044 no.received Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-14, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 01.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Block work setting out in area C is completed.
Concrete Work :
Concreting with 3Cu.M. of 30N-OPC for Lintel in area A is completed.

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 02.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Block 4"- Plants,Equipments and/off site :


2000Nos, White wood -180 no.and Marine plywood-51no. Generator-1,Roller Compactor-1,Plate
Received. Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 03.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 05.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 06.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:
Electrical GI box wall
Site Work : Block work completed at area A. piping and mechanical
Housekeeping is maintained. wall piping.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Block 8"- Plants,Equipments and/off site :


1404Nos. Received. Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No.


Date : 07.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:
Electrical GI box wall
Site Work : piping and mechanical
STOP WORKING DUE TO SECURITY REASON wall piping.

Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-5 , Carpenter-9,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 08.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Formwork for 1st floor beams at area B is started.
Housekeeping is maintained.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : jacks-200 Plants,Equipments and/off site :


Nos. Received. Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-5, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 09.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work :
Housekeeping is maintained.
Formwork for 1st floor beams at area B is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-9, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 10.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work :
Housekeeping is maintained.
Formwork for 1st floor beams at area B is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Block 4"- Plants,Equipments and/off site :


2000Nos, White wood -180 no.and Marine plywood-51no. Generator-1,Roller Compactor-1,Plate
Received. Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-1,Drill
Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-9, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 12.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Blocks shifting.
Cement shifting.
Plywood and white wood arrangement.
Housekeeping is maintained.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 13.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Blocks shifting.
Cement shifting.
Plywood and white wood arrangement.
Housekeeping is maintained.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 14.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Housekeeping is maintained.
Shovel for external levelling around the building.
Formwork for 1st floor beams at area B is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-11,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 15.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Housekeeping is maintained.
Shovel for external levelling around the building.
Formwork for 1st floor beams at area B is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-13,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 16.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Housekeeping is maintained.
Shovel for external levelling around the building.
Formwork for 1st floor beams at area B is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-13,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 17.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Housekeeping is maintained.
Shovel for external levelling around the building.
Formwork for 1st floor beams at area B is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Marine Plants,Equipments and/off site :


plywood-51no. Received.,Common nails boxes - Generator-1,Roller Compactor-1,Plate
20no.Received. Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect : Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-13,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 19.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Housekeeping is maintained.
Formwork for 1st floor beams at area B is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-12,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 20.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and


mechanical sleeve.
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is started .
Formwork for 1st floor beams at area B is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-13,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 21.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Reinforcement for 1st floor beams at area B is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect : Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-15 , Carpenter-2,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 22.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Reinforcement for 1st floor beams at area B is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-14 , Carpenter-2,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 23.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Reinforcement for 1st floor beams at area B is in progress .
Formwork for 1st floor beams at area A is started.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Marine Plants,Equipments and/off site :


plywood-51no. Received. Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect : Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-16 , Carpenter-2,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 24.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Reinforcement for 1st floor beams at area B is in progress .
Formwork for 1st floor beams at area A is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-17 , Carpenter-2,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 26.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work :
Reinforcement for 1st floor beams at area B is in progress .
Block work in area C is in progress.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-11 , Carpenter-2,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 27.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Lintel formwork in area C is started .
Reinforcement for 1st floor beams at area B is in proress .
Formwork for 1st floor beams at area A is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-17 , Carpenter-3,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 28.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Lintel formwork in area C is in progress .
Lintel reinforcement in area C is started .
Reinforcement for 1st floor beams at area B is in progress .
Formwork for 1st floor beams at area A is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-13, Steel Fixer-17 , Carpenter-3,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 29.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Lintel formwork in area C is completed .
Lintel reinforcement in area C is completed .
Reinforcement for 1st floor beams at area B is completed .
Formwork for 1st floor beams at area B is in progress .
Formwork for 1st floor beams at area A is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-8 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 30.04.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Formwork for 1st floor beams at area B is in progress.
Formwork for 1st floor beams at area A is in progress .
Concrete Work :
Concreting with 2Cu.M. of 30N-OPC for Lintel in area C is completed.

Arr. Dep. QECE & other visitors comments

Material Deliveries : jacks-200 Plants,Equipments and/off site :


Nos. Received. Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-2 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 01.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes trenches , manholes ,
car parking shed and septic tank is in progress and for sub- station is
started.
Block work in area C is in progress.
Formwork for 1st floor beams at area B is in progress.
Formwork for 1st floor beams at area A is in progress .
Concrete Work :
Concreting with 2Cu.M. of 30N-OPC for Sil in area A&C is completed.

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-2 , Carpenter-13,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 03.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes and manholes , car
parking shed , sub-station and completing septic tank is hold because we
couldn't make gate pass for poclain driver because it is holiday today for
gate pass office .
Block work in area C is in progress.
Formwork for 1st floor beams at area B is in progress.

Formwork for 1st floor beams at area A is hold because we couldn't make
gate pass for carpenters because it is holiday today for gate pass office .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-2 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 04.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed , sub-station and septic tank is in progress .
Block work in area C is in progress.
Formwork for 1st floor beams at area B is in progress.
Formwork for 1st floor beams at area A is in progress .
Reinforcement for 1st floor beams at area A is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-16 , Carpenter-13,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 05.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and septic tank is in progress and sub-station is hold because of
Kahramaah Company .
Block work in area C is in progress.
Formwork for 1st floor beams at area B is completed.
Formwork for 1st floor beams at area A is in progress .
Reinforcement for 1st floor beams at area A is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-16 , Carpenter-13,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 06.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and septic tank is in progress and sub-station is hold because of
Kahramaah Company .
Block work in area C is in progress.
Formwork for 1st floor beams at area A is in progress .
Reinforcement for 1st floor beams at area A is in progress .
Concrete Work :
Concreting with 57 Cu.M. of 30N-OPC for first floor beams in area B is
completed.
Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-16 , Carpenter-3,
Labour-10,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 07.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and septic tank is in progress and sub-station is hold because of
Kahramaah Company .
Block work in area C is in progress.
Formwork for 1st floor beams at area A is completed .
Reinforcement for 1st floor beams at area A is completed .
Formwork deshuttering ( sides only ) for 1st floor beams at area B is
completed .
Curing for 1st floor beams at area B with water .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-16 , Carpenter-13,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 08.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed is completed and septic tank is in progress and sub-station is hold
because of Kahramaah Company .
Block work in area C is completed.
Curing for 1st floor beams at area B with water .
Concrete Work : Concreting with 29 Cu.M. of 30N-OPC for first floor beams in area A is
completed.

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-12, Steel Fixer-2 , Carpenter-2,
Labour-10,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 10.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for septic tank and sub-station is hold because we
couldn't make gate pass for poclain driver because it is holiday today for
gate pass office and sub-station is hold also because of Kahramaah
Company .

Formwork deshuttering ( sides only ) for 1st floor beams at area A is


completed .
Curing for 1st floor beams at area B & area A with water .
Material arrangement and housekeeping at site.
Working is stopped from 10 : 00 am to 3 : 00 pm because of the windy -
sand storm weather .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower:- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-5, Labour-
5,Plumber-2,Electricions-3
Weather :
Windy - sand storm .

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 11.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain for septic tank is in progress and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is started .
Curing for 1st floor beams at area B & area A with water .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : H.D.G. cable trunking Plants,Equipments and/off site :


150*100*1.50*2.44MTR -64no. , G.I. threaded rod Generator-1,Roller Compactor-1,Plate
10mm*3.0MTR and G.I. uni strut 41*41*1.5mm*3.0MTR Compactor-1,Vibrator-2,Mixer Machine-
Received. 1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-11,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 12.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain for septic tank is in progress and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is in progress .
Curing for 1st floor beams at area B & area A with water .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : H.D.G. cable trunking Plants,Equipments and/off site :


150*100*1.50*2.44MTR -64no. , G.I. threaded rod Generator-1,Roller Compactor-1,Plate
10mm*3.0MTR and G.I. uni strut 41*41*1.5mm*3.0MTR Compactor-1,Vibrator-2,Mixer Machine-
Received. 1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 13.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain for septic tank is in progress and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is in progress .
Reinforcement for 1st floor beams at area C is started .
Curing for 1st floor beams at area B & area A with water .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 22 tons of washed sand . Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-10 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 14.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain for septic tank is in progress and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is in progress .
Reinforcement for 1st floor beams at area C is in progress .
Curing for 1st floor beams at area A with water .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 1 ton of 8mm and 1 ton of 12mm Plants,Equipments and/off site :
straight reinforcement steel bars . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-10 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 15.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping , mechanical
wall piping and
Electrical and
mechanical sleeve.

Site Work : Excavation by poclain for septic tank is completed and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is completed .
Reinforcement for 1st floor beams at area C is completed .
Leveling for foundation level and plain concrete formwork for septic tank
are completed .
Curing for 1st floor beams at area A with water .
Material arrangement and housekeeping at site.
Concrete Work : Concreting with 29 Cu.M. of 30N-OPC for first floor beams in area C is
completed.
Concreting with 4 Cu.M. of 30N-OPC for plain concrete of septic tank is
completed .
Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-10 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 17.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for saokways and R.G is started and for sub-station
is hold because of Kahramaah Company .
Formwork deshuttering ( bottoms and jacks ) for 1st floor beams at area B
is completed .
Formwork deshuttering ( sides only ) for 1st floor beams at area C is
completed .
Formwork for ground floor outer lintels at area B is started .
Reinforcement for ground floor outer lintels at area B is started .
Leveling for foundation level and plain concrete formwork for manholes are
started .
Curing for 1st floor beams at area C with water .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 18.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for saokways and R.G is in proress and for sub-
station is hold because of Kahramaah Company .
Formwork for ground floor outer lintels at area B is completed .
Reinforcement for ground floor outer lintels at area B is completed .
Leveling for foundation level and plain concrete formwork for manholes are
in progress .
Curing for 1st floor beams at area C with water .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-4, Steel Fixer-2 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 19.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for saokways and R.G is in proress and for sub-
station is hold because of Kahramaah Company .
Leveling for foundation level and plain concrete formwork for manholes are
completed .
Curing for 1st floor beams at area C with water .
Primer paintinig for plain concrete of septic tank is completed .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 2 tons of 12mm and 4 tons of 16mm Plants,Equipments and/off site :
straight reinforcement steel bars and wire mesh A-252 Generator-1,Roller Compactor-1,Plate
(8mm) -100 Nos . Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 20.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for saokways is completed and for R.G is in proress
and for sub-station is hold because of Kahramaah Company .
Roof columns reinforcement at area A is started ( stirrups) .
Curing for 1st floor beams at area C with water .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-10 , Carpenter-4,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 21.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for R.G is in proress and for sub-station is hold
because of Kahramaah Company .
Roof columns reinforcement at area A is completed ( stirrups) .
Curing for 1st floor beams at area C with water .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-4, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 22.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Mechanical inspetion for


manholes is completed .

Site Work : Excavation by poclain for R.G is in proress and for sub-station is hold because
of Kahramaah Company .
Setting out of block work for ground floor at area B is started.
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-5, Steel Fixer-2 , Carpenter-4, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 25.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for R.G is in proress and for sub-station is hold because
of Kahramaah Company .
Block work for ground floor at area B is in progress .
Shuttering for manholes reinforced footings is completed ( to be placed in its
proper positions) .
Water proofing for septic tank plain concrete with membrane sheets is completed
.
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-5 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 26.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for R.G is completed and for sub-station is hold because
of Kahramaah Company .
Block work for ground floor at area B is in progress .
Reinforcement for septic tank footing is in progress .
Formwork for septic tank reinforced footing is started .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-5 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 27.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

Block work for ground floor at area B is in progress .


Reinforcement for septic tank footing is in progress .
Formwork for septic tank reinforced footing is in progress .
Hollow core slab erection at area A is completed .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-5 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 28.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

Block work for ground floor at area B is in progress .


Reinforcement for septic tank footing is completed .
Formwork for septic tank reinforced footing is completed .
Hollow core slab erection at area B ( ground floor ) is started .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-5 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 29.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

Block work for ground floor at area B is in progress .


Hollow core slab erection at area B ( ground floor ) is completed .
Shuttering for hollow core screed at area A is started .
Reinforcement for hollow core screed at area A is started .
Material arrangement and housekeeping at site.
Concrete Work : Concreting with 15 Cu.M. of 30N-SRC for septic tank reinforced raft is
completed.
Concreting with 3 Cu.M. of 30N-SRC for manholes plain concerte is completed.
Concreting
with 2 Cu.M. of 30N-SRC for outer lintels at area B ( ground floor) is completed .

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-5 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 31.05.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

Block work for ground floor at area B is in progress .


Shuttering for hollow core screed at area A is completed .
Reinforcement for hollow core screed at area A is completed .
Columns RFT for first floor at area B is started .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-7 , Carpenter-3, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 2.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

Block work for ground floor at area B is in progress .


Columns RFT for first floor at area B is in progress .
Deshuttering for screed at area A is completed .
Curing with water for hollow core screed at area A and septic tank raft .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 4 trips of washed sand received . Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-5 , Carpenter-3, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 3.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical and mechanical


extentions for GF hollow
core slabs at area B
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

Block work for ground floor at area B is in progress .


Columns RFT for first floor at area B is in progress .
Formwork for septic tank walls is started .
Curing with water for hollow core screed at area A and septic tank raft .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 4 trips of washed sand received . Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-5 , Carpenter-3, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 4.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

Block work for ground floor at area B is in progress .


Columns RFT for first floor at area B is completed .
Block work for parapet at area A is started .
RFT for septic tank walls is started .
Curing with water for hollow core screed at area A and septic tank raft .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 1440 Nos of 8" hollow blocks are Plants,Equipments and/off site :
received . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-
1 , bobcat-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-9, Steel Fixer-5 , Carpenter-3, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 5.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

RFT for septic tank walls is in progress .


Block work for parapet at area A is in progress .
Formwork for inner lintels for ground floor at area B is started .
RFT for inner lintels for ground floor at area B is started .
Formwork for screed for ground floor hollow core slabs is started .
Curing with water for hollow core screed at area A and septic tank raft .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 1650 Nos of 4" hollow blocks are Plants,Equipments and/off site :
received . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-
1 , bobcat-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-6, Labour-
8,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 7.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

RFT for septic tank walls is in progress .


Block work for parapet at area A is in progress .
Block work for ground floor at area B is in progress .
Formwork for inner lintels for ground floor at area B is in progress .
RFT for inner lintels for ground floor at area B is in progress .
Formwork for screed for ground floor hollow core slabs is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-
1,

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-6, Labour-
8,Plumber-2,Electricions-3
Weather :
Normal

QECE Sign : Contractor Sign :


QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 8.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box wall


piping

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

RFT for septic tank walls is completed .


Block work for parapet at area A is completed .
Block work for ground floor at area B is in progress .
Formwork for inner lintels for ground floor at area B is completed .
RFT for inner lintels for ground floor at area B is completed .
Formwork for screed for ground floor hollow core slabs at area B is completed .

RFT for screed for ground floor hollow core slabs at area B is started .
Material arrangement and housekeeping at site.
# Working is stopped because of Windy sandy storm from 10:00 am to 12:00 .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-
1,

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-10, Steel Fixer-5 , Carpenter-6,
Labour-8,Plumber-2,Electricions-3
Weather :
Windy sandy storm from 10:00 am to
12:00
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 9.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .

Block work for ground floor at area B is in progress .


RFT for screed for ground floor hollow core slabs is completed .
Material arrangement and housekeeping at site.
Concrete Work : Concreting with 60 Cu.M. of 20N-OPC for screed for ground floor hollow core
slabs at area B is completed.
Concreting with 3 Cu.M. of 20N-OPC for inner lintels for ground floor at area B is
completed.
Arr. Dep. QECE & other visitors comments

Material Deliveries : 350 Nos of 6" hollow blocks . Plants,Equipments and/off site :
Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-
1,

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-10, Steel Fixer-5 , Carpenter-1,
Labour-10,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 10.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Coordinates marking for 1st floor columns at area B by surveyor is completed .
Formwork for 1st floor columns at area B is started .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 1 trip of plaster sand . Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , bobcat-
1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-6, Labour-
10,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 11.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for 1st floor columns at area B is in progress .
Erection of precast hollow core slabs at area C ( ground floor ) is completed .
Stirrups for parapet columns fixing at area C is completed .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , bobcat-1,
crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-6, Labour-
10,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 12.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping

Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for 1st floor columns at area B is in progress .
Formwork for ground floor hollow core slabs ready mix concrete at area C is
started .
RFT for ground floor hollow core slabs ready mix concrete at area C is started .
Material arrangement and housekeeping at site.
# Work is stopped from 9:00am to 3:00pm because of windy sand storm .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : 2 trips of plaster sand . Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , J.C.P
telescope-1, crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-6, Labour-
10,Plumber-2,Electricions-3
Weather :
Windy sand storm
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 14.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping & mechanical sleeves
for septic tank
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for 1st floor columns at area B is in progress .
Formwork for ground floor hollow core slabs ready mix concrete at area C is
completed .
RFT for ground floor hollow core slabs ready mix concrete at area C is completed .

Material arrangement and housekeeping at site.


Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-4, Steel Fixer-2 , Carpenter-7, Labour-
8,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 15.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for 1st floor columns at area B is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-4, Steel Fixer-6 , Carpenter-8, Labour-
8,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 16.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for 1st floor columns at area B is completed .
Formwork for parapet columns at area A is started .
Material arrangement and housekeeping at site.
Concrete Work : Concreting with 30 Cu.M. of 20N-OPC for screed for ground floor hollow core
slabs at area C is completed.
Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


450 MTR of 150MM VC pipe 1.5M long SS 6X50 - 110 Generator-1,Roller Compactor-1,Plate
PCS of 150MM VC GZ 60C long SS 2X45+20 - 8 KG of Compactor-1,Vibrator-2,Mixer Machine-1,Bending
lubricant . Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-4, Steel Fixer-7 , Carpenter-10,
Labour-9,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 17.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for 15 parapet columns at area A is completed .
Material arrangement and housekeeping at site.
Concrete Work : Concreting with 32 Cu.M. of 30N-OPC for 1st floor columns at area B is
completed.
Concreting with 3 Cu.M. of 30N-OPC for 15 parapet columns at area A is
completed .
Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-4, Steel Fixer-7 , Carpenter-10,
Labour-9,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 18.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Deshuttering for 1st floor columns at area B is completed .
Formwork for parapet columns at area A is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-2 , Carpenter-10,
Labour-9,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 19.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for septic tank walls is started .
Formwork for parapet columns at area A is completed .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-6 , Carpenter-7, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 21.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for septic tank walls is hold because gate passes renewal for
carpenters is still under working from camp security since 3 days .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-5, Labour-
2,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 22.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for septic tank walls is in proress .
Formwork for air conditions footings at area A and area C is started .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 23.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for septic tank walls is in proress .
Formwork for air conditions footings at area A and area C is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


1404 Nos of 20 8" hollow blocks Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 24.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for septic tank walls is in proress .
Formwork for air conditions footings at area A and area C is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 25.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for septic tank walls is in proress .
Formwork for air conditions footings at area A and area C is completed .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 26.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Electrical GI box & wall


piping .
Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for septic tank walls is completed .
Formwork for drainage slabs at area D is started .
Parapet block work at area C is started .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 28.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for drainage slabs at area D is completed .
RFT for drainage slabs at area D is completed .
Parapet block work at area C is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 29.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for drainage slabs at area D is completed .
RFT for drainage slabs at area D is completed .
Parapet block work at area C is in progress .
Material arrangement and housekeeping at site.
Concrete Work : Concreting with 27 Cu.M. of 30N-SRC for septic tank walls is completed .
Concreting with 4 Cu.M. of 20N-OPC for 20 parapet columns at area A is
completed .
Concreting with 3.5 Cu.M. of 20N-OPC for A.Cs. footings at area A is completed.
Concreting
with 1.5 Cu.M. of 20N-OPC for drainage slab at area A is completed .

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 30.06.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Formwork for sub-station footings is completed .


RFT for sub-station footings is started .
Formwork deshuttering for septic tank walls is completed .
Parapet block work at area C is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 01.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : RFT for sub-station footings is completed .


Parapet block work at area C is in progress .
Formwork deshuttering for parapet columns at area A is completed .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


250 cement bags . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-8, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 02.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Parapet block work at area C is completed .


Formwork deshuttering for parapet columns at area A is completed .
Material arrangement and housekeeping at site.

Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-5, Labour-
4,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 03.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: GI box and wall piping

Site Work : Formwork for septic tank roof slab is started .


Reinforcement for manholes footings is started .
Material arrangement and housekeeping at site.

Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-6, Labour-
3,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 05.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Formwork for septic tank roof slab is in progress .


Reinforcement for manholes footings is in progress .
Material arrangement and housekeeping at site.

Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-7, Labour-
4,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 06.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Formwork for septic tank roof slab is completed .


Reinforcement for manholes footings is in progress .
Material arrangement and housekeeping at site.

Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-5 , Carpenter-7, Labour-
3,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 07.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Reinforcement for manholes footings is completed .


Material arrangement and housekeeping at site.
Concrete Work : Concreting with 9 Cu.M. of 30N-SRC for manholes footings and A.C. footings at
area C is completed .
Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-2 , Carpenter-7, Labour-
3,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 08.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Reinforcement for manholes walls is started .


Material arrangement and housekeeping at site.
Concrete Work : Concreting with 3 Cu.M. of 30N-SRC for sub-station reinforced footings is
completed .
Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel-1 , poclain-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-2 , Carpenter-1, Labour-
3,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 09.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work: GI box and wall piping .

Site Work : Reinforcement for manholes walls is in progress .


Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


2 tons of 16mm high grade reinforcement straight bars . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel-1 , poclain-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-2 , Carpenter-1, Labour-
4,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 10.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Reinforcement for manholes walls is in progress .


Material arrangement and housekeeping at site.
Reinforcement for septic tank roof slab is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel-1 , poclain-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-3, Steel Fixer-6 , Carpenter-1, Labour-
7,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 12.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Reinforcement 10 manholes walls is completed .


Reinforcement for septic tank roof slab is in progress .
Block work for 1st floor at area D is started .
Interior plaster work for ground floor at area A is started .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel-1 , poclain-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-15, Steel Fixer-6 , Carpenter-1,
Labour-7,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 13.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Reinforcement for septic tank roof slab is completed .


Block work for 1st floor at area D is in progress .
Interior plaster work for ground floor at area A is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


1044 Nos of 8" hollow blocks . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel-1 , poclain-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-15, Steel Fixer-6 , Carpenter-1,
Labour-7,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 14.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Block work for 1st floor at area D is in progress .


Interior plaster work for ground floor at area A is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel-1 , poclain-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-14, Steel Fixer-6 , Carpenter-1,
Labour-7,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No. ( 0 )


Date : 15.07.2014

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Block work for 1st floor at area D is in progress .


Interior plaster work for ground floor at area A is in progress .
Material arrangement and housekeeping at site.
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-1,Bending
Machine-1, Grinder-1,Wood Cutting Machine-
1,Water Pump-2,Hilty-1,Drill Machine-1 , crane-1 ,
shewel-1 , poclain-1

Manpower :- Other Comments/Information :


Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-14, Steel Fixer-6 , Carpenter-1,
Labour-7,Plumber-2,Electricions-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 24.07.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Sealer in area A and area B is in progress


Housekeeping in F.F. is started .
Beam work for F.F. is on hold .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-7 , Steel Fixer-7 ,


Mason-27 , labour-10
Weather :
Sandy
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 26.07.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Sealer in area A and area B is in progress


Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


One trip of plaster sand . Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-7 , Steel Fixer-5 ,


Mason-17 , labour-8 , Painters-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 27.07.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Sealer in area A and area B is in progress


Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Nine manholes walls reinforcement and shuttering are completed and the
remaining are in progress .
Concrete Work : Concreting with 9 Cu.M. of 30N-SRC for nine manholes walls is completed .

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-7 , Steel Fixer-5 ,


Mason-17 , labour-8 , Painters-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 31.07.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Sealer in area A and area B is in progress


Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Deshuttering for nine manholes walls is completed .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-7 , Steel Fixer-5 ,


Mason-17 , labour-8 , Painters-3
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 02.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after sealer in area A and area B is started .
Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-11 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 03.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after sealer in area A and area B is in progress .
Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-11 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 04.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after sealer in area A and area B is in progress .
Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-11 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 05.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after sealer in area A and area B is in progress .
Housekeeping at site .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Formwork for parapet columns at area C is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-11 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 06.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after sealer in area A and area B is in progress .
Housekeeping at site .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are completed .
Formwork for parapet columns at area C is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


5trips of plaster sand . Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-11 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 07.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after sealer in area A and area B is completed .
Housekeeping at site .
Internal plaster work in area C is in progress .
Formwork for parapet columns at area C is completed .
Concrete Work : Concreting with 9 Cu.M. of 30N-SRC for manholes walls and 9 Cu.M. of 30N-OPC
for parapet columns at area C is completed .
Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-11 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 09.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Filler 1st coat for internal painting at area A and area B is started .
Housekeeping at site .
Internal plaster work in area C is completed .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-11 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 10.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Filler 1st coat for internal painting at area A and area B is in progress .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 11.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Filler 1st coat for internal painting at area A and area B is completed .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 ,
Generator-1 , Plywood cutter machine-2 , Water
pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 12.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after Filler 1st coat for internal painting at area A and area B is
started .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 13.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after Filler 1st coat for internal painting at area A and area B is in
proress .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 14.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after Filler 1st coat for internal painting at area A and area B is in
proress .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 16.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after Filler 1st coat for internal painting at area A and area B is
completed .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 17.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Filler 2nd coat for internal painting at area A and area B is started .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 18.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Filler 2nd coat for internal painting at area A and area B is in progress .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 19.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Filler 2nd coat for internal painting at area A and area B is completed .
Housekeeping at site .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 20.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after Filler 2nd coat for internal painting at area A and area B is
started .

Housekeeping at site .
Sealer for internal painting at area C is completed .
Backfilling with fine sand and leveling up to sewage pipes bottom levels back side the
building is started

False ceiling installation at areas A and B is started .


Internal plaster for parapet at areas A and C is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 21.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after Filler 2nd coat for internal painting at area A and area B in
progress .

Housekeeping at site .
Surface cleaning after sealer for internal painting at area C is completed .
Filler 1st coat for internal painting at area C is started .
Backfilling with fine sand and leveling up to sewage pipes bottom levels back side the
building is completed .

False ceiling installation at areas A and B is in progress .


Internal plaster for parapet at areas A and C is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-17 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 23.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Surface cleaning after Filler 2nd coat for internal painting at area A and area B is
completed .

Housekeeping at site .
Filler 1st coat for internal painting at area C is completed .
Sewage pipes installation back side the building is started .
False ceiling installation at areas A and B is in progress .
Formwork for roof beams at area D is started .
Reinforcement for roof beams at area D is started .
Internal plaster for parapet at areas A and C is completed .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 24.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Surface cleaning after filler 1st coat for internal painting at area C is completed .
Sewage pipes installation back side the building is in progress .
False ceiling installation at areas A and B is in progress .
Formwork for roof beams at area D is in progress .
Reinforcement for roof beams at area D is in progress .
Fixing sub frames for doors is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 25.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


2nd coat for internal painting at area C is started .
Sewage pipes installation back side the building is completed .
False ceiling installation at areas A , B and C is in progress .
Formwork for roof beams at area D is in progress .
Reinforcement for roof beams at area D is in progress .
Fixing sub frames for doors is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 26.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


2nd coat for internal painting at area C is in progress .
Backfilling above Sewage pipes back side the building is started .
False ceiling installation at ground floor is started .
Formwork for roof beams at area D is in progress .
Reinforcement for roof beams at area D is in progress .
Fixing sub frames for doors is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 27.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


2nd coat for internal painting at area C is completed .
Backfilling above Sewage pipes back side the building is completed .
False ceiling installation at ground floor is in progress .
Formwork for roof beams at area D is in progress .
Reinforcement for roof beams at area D is in progress .
Fixing sub frames for doors is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 28.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Surface cleaning after 2nd coat for internal painting at area C is started .
External plaster preparations and accessories fixing at area C is started .
False ceiling installation at ground floor is in progress .
Formwork for roof beams at area D is in progress .
Reinforcement for roof beams at area D is in progress .
Fixing sub frames for doors is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 30.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Surface cleaning after 2nd coat for internal painting at area C is completed .
External plaster preparations and accessories fixing at area C is in progress .
False ceiling installation at ground floor is in progress .
Formwork for roof beams at area D is completed .
Reinforcement for roof beams at area D is completed .
Fixing sub frames for doors is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9 , Painters-4
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 31.08.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster at area C is started .
False ceiling installation at ground floor is in progress .
Fixing sub frames for doors is completed .
Ceramic tiles works for public bathroom walls is started .
Concrete Work : Concreting with 60 m3 30N/mm2 - OPC- for roof beams at area D is completed .

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9 ,
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 01.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster at area C is in progress .
False ceiling installation at ground floor is in progress .
Deshuttering for roof beams sides .
Ceramic tiles works for public bathroom walls is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 02.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster at area C is in progress .
False ceiling installation at ground floor is in progress .
Ceramic tiles works for public bathroom walls is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-8 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 03.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster at area C is in progress .
False ceiling installation at ground floor is in progress .
External plaster preparations and accessories fixing at area C is in started .
Ceramic tiles works for public bathroom walls is completed .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 04.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster at area C is in progress .
False ceiling installation at ground floor is in progress .
External plaster at area C is in started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
RMED FORCES
ORPS OF ENGINEERS
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 06.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-14 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 07.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-4 , Steel Fixer-6 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 08.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 09.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-6 , Steel Fixer-4 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 10.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-14 , labour-10
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 11.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 13.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 14.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 15.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-6 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 16.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 17.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-10
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 18.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 20.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 21.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Internal plaster at first floor is started .
External painting is started .
Hollow core slabs placing at area D is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9 , Painters-5
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 22.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Internal plaster at first floor is in progress .
External painting is in progress .
Hollow core slabs placing at area D is completed .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9 , Painters-5
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 23.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Internal plaster at first floor is in progress .
External painting is in progress .
Hollow core slabs screed formwork at area D is started .
Hollow core slabs screed reinforcement at area D is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9 , Painters-5
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 24.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Internal plaster at first floor is in progress .
External painting is in progress .
Hollow core slabs screed formwork at area D is completed .
Hollow core slabs screed reinforcement at area D is completed .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-9 , Painters-5
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 25.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Internal plaster at first floor is in progress .
External painting is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-4 , Painters-5
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 27.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Internal plaster at first floor is in progress .
External painting is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-4 , Painters-5
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 28.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Internal plaster at first floor is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-4 , Painters-5
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 29.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External plaster is completed .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Internal plaster at first floor is completed .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-15 , labour-4 , Painters-5
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 30.09.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Formwork for parapet columns at area D is started .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 01.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Formwork for parapet columns at area D is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 02.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Formwork for parapet columns at area D is completed .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 12.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is started .
Internal painting at area D is started .
False ceiling installation at 1st floor is started .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 13.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 14.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 15.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 16.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 18.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 19.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
water proofing for roof is started .
water proofing for septic tank is started .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-4 , labour-4
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 20.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
water proofing for roof is in progress .
water proofing for septic tank is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-9 , labour-7
Weather :
Normal
QECE Sign : Contractor Sign :
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 21.10.2014

PROJECT NAME : Community Park No. 153

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
water proofing for roof is in progress .
water proofing for septic tank is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-9 , labour-7
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 22.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
water proofing for roof is in progress .
water proofing for septic tank is in progress .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-9 , labour-7
Weather :
Normal
QECE Sign : Contractor Sign :
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-308-01 Page No. ( 0 )


Date : 23.10.2014

PROJECT NAME : Procurement Directorate Building at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


External painting is in progress .
Internal painting at area D is in progress .
False ceiling installation at 1st floor is in progress .
False ceiling installation at ground floor is in progress .
Porclain tiles works in ground floor are in progress .
water proofing for roof is in progress .
water proofing for septic tank is completed .
Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Compactor-2 , Vibrator-3 , Compressor-1 , Generator-
1 , Plywood cutter machine-2 , Water pump-2

Manpower :- Other Comments/Information :


Indirect : Safety Officer-1 , Surveyor-1 , Site Engineer-
1 , Site Manager , Project Manager

Direct: Foreman-1 , Carpenter-5 , Steel Fixer-5 ,


Mason-9 , labour-7
Weather :
Normal
QECE Sign : Contractor Sign :
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 29th July 2015 - 12nd Ramadan 1436

PROJECT NAME : Al Deffi Park

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Excavation Manually around poles footings is in progress .
Coating new poles footings is in progress .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Jumping Compactor-1, Gas cutter
machine-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1, Bobcat didn't work for last 2 days because it
Safety Officer-1,Site Engineer-1,Civil needs to be repaired and admin was informed
Foreman-1 about that .

Direct: Mason-1, Welders-3,Bobcat operator-1, ( all


working as labors )
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 05th July 2015 - 18th Ramadan 1436

PROJECT NAME : Al Deffi Park

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Coating new poles footings is in progress .
Installation of new poles footings is started .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Jumping Compactor-1, Gas cutter
machine-1 , JCB-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1,
Safety Officer-1,Site Engineer-1,Civil
Foreman-1

Direct:
Mason-1, Welders-3, ( all working as labors )
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 08th July 2015 - 21st Ramadan 1436

PROJECT NAME : Al Deffi Park

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Disconnecting cables for old


footings and connecting cables
for new footings are in
progress .

Site Work : Housekeeping at site .


Coating new poles footings is in progress .
Installation of new poles footings is in progress .
Backfilling around new footings of lighting poles is started .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Jumping Compactor-1, Gas cutter
machine-1 , JCB-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1,
Safety Officer-1,Site Engineer-1,Civil
Foreman-1, Electrical foreman-1
Direct: Mason-1, Welders-3, Labors-4 ( all working
as labors ) , Electritians-2
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 09th July 2015 - 22nd Ramadan 1436

PROJECT NAME : Al Deffi Park

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Disconnecting cables for old


footings and connecting cables
for new footings are in
progress .

Site Work : Housekeeping at site .


Coating new poles footings is in progress .
Installation of new poles footings is in progress .
Installation of old poles is in progress .
Backfilling around new footings of lighting poles is started .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Jumping Compactor-1, Gas cutter
machine-1 , JCB-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1,
Safety Officer-1,Site Engineer-1,Civil
Foreman-1, Electrical foreman-1
Direct: Mason-1, Welders-3, Labors-4 ( all working
as labors ) , Electritians-2
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 01st August 2015 - 16th Shawwal 1436

PROJECT NAME : Al Deffi Park

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Disconnecting cables for old


footings and connecting cables for
new footings are in progress .

Site Work : Housekeeping at site .


Coating new poles footings with bitumenous material is in progress ( 8 are completed ) .
Installation of new poles footings is in progress ( 5 are completed ) .
Installation of old poles is in progress ( 3 are completed ) .
Backfilling around new footings of lighting poles is in progress ( 14 are completed ) .
Coating new poles footings polyethelyne sheets is in progress ( 5 are completed ) .
Disposal of lighting poles old footings is in progress ( 4 are completed ) .
Removing lighting poles from their old footings and base plates anchor bolts holes
enlargement are in progress ( 6 are completed ) .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


20 polyethelyne sheet rolls - New 18 lighting poles Generator-1,Jumping Compactor-1, Gas cutter machine-
footing . 1 , JCB-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1,
Safety Officer-1,Site Engineer-1,Civil
Foreman-1, Electrical foreman-1
Direct:
Mason-2, Welders-3, Labors-2 , Electritian-2
Mason-2, Welders-3, Labors-2 , Electritian-2
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 02nd August 2015 - 17th Shawwal 1436

PROJECT NAME : Al Deffi Park

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Disconnecting cables for old


footings and connecting cables for
new footings are in progress .

Site Work : Housekeeping at site .


Coating new poles footings with bitumenous material is in progress ( 10 are completed ) .
Installation of new poles footings is in progress ( 6 are completed ) .
Installation of old poles is in progress ( 4 are completed ) .
Backfilling around new footings of lighting poles is in progress ( 11 are completed ) .
Coating new poles footings polyethelyne sheets is in progress ( 6 are completed ) .
Disposal of lighting poles old footings is in progress ( 3 are completed ) .
Manual excavation around old poles footings is in progress ( 4 are completed ) .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


New 15 lighting poles footing . Generator-1,Jumping Compactor-1, Gas cutter machine-
1 , JCB-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1,
Safety Officer-1,Site Engineer-1,Civil
Foreman-1, Electrical foreman-1
Direct:
Mason-2, Welders-3, Labors-2 , Electritian-2
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 03rd August 2015 - 18th Shawwal 1436

PROJECT NAME : Al Deffi Park

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Disconnecting cables for old


footings and connecting cables for
new footings are in progress .

Site Work : Housekeeping at site .


Coating new poles footings with bitumenous material is in progress ( 7 are completed ) .
Installation of new poles footings is in progress ( 7 are completed ) .
Installation of old poles is in progress ( 7 are completed ) .
Backfilling around new footings of lighting poles is in progress ( 5 are completed ) .
Coating new poles footings polyethelyne sheets is in progress ( 7 are completed ) .
Removal of lighting poles old footings is in progress ( 9 are completed ) .
Removing lighting poles from their old footings and base plates anchor bolts holes
enlargement are in progress ( 10 are completed ) .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


New 15 lighting poles footing . Generator-1,Jumping Compactor-1, Gas cutter machine-
1 , JCB-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1,
Safety Officer-1,Site Engineer-1,Civil
Foreman-1, Electrical foreman-1
Direct:
Mason-2, Welders-3, Labors-1 , Electritian-2
Mason-2, Welders-3, Labors-1 , Electritian-2
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 04th August 2015 - 19th Shawwal 1436

PROJECT NAME : Al Deffi Park

CONTRACTOR : Progress including Samples and Tests :

MEP Work: Disconnecting cables for old


footings and connecting cables for
new footings are in progress .

Site Work : Housekeeping at site .


Coating new poles footings with bitumenous material is in progress ( 7 are completed ) .
Installation of new poles footings is in progress ( 7 are completed ) .
Installation of old poles is in progress ( 7 are completed ) .
Backfilling around new footings of lighting poles is in progress ( 2 are completed ) .
Coating new poles footings polyethelyne sheets is in progress ( 7 are completed ) .
Removal of lighting poles old footings is in progress ( 4 are completed ) .
Removing lighting poles from their old footings and base plates anchor bolts holes
enlargement are in progress ( 8 are completed ) .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1,Jumping Compactor-1, Gas cutter machine-
1 , JCB-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1,
Safety Officer-1,Site Engineer-1,Civil
Foreman-1, Electrical foreman-1
Direct:
Mason-2, Welders-3, Labors-1 , Electritian-2
Mason-2, Welders-3, Labors-1 , Electritian-2
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 08th August 2015 - 23rd Shawwal 1436

PROJECT NAME : Bridge 27-T218

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Excavation around piles is in progress ( 8 Piles are completed → Approximately 14Cubic
meter )
Removing backfilling to expose retaining wall is in progress ( Approximately 6 Cubic
meter )

Marking for unsound concrete removal is in progress .


Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1, Small grinder-1 , Big grinder-1 , Air
compressor-1 , Jackhammer-1 , Air blower-1 , Wood
cutting machine-1 , Small jackhammer-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1, Chipping hammer - Shuttering materials .
Safety Officer-1,Site Engineer-1,Civil
Foreman-1
Direct:
Mason-5 , Carpenter-1 , Leadman-1
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 09th August 2015 - 24th Shawwal 1436

PROJECT NAME : Bridge 27-T218

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Excavation around piles is in progress ( 5 Piles are completed → Approximately 9Cubic
meters )
Removing backfilling to expose retaining wall is in progress ( Approximately 6 Cubic
meter )

Marking for unsound concrete removal is in progress .


Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1, Small grinder-1 , Big grinder-1 , Air
compressor-1 , Jackhammer-1 , Air blower-1 , Wood
cutting machine-1 , Small jackhammer-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1, Chipping hammer - Shuttering materials to be
Safety Officer-1,Site Engineer-1,Civil transferred from 156 - Permission for excavation
Foreman-1 inside pipe line corridor .
Direct: Mason-4 , Carpenter-1 , Labor-1 , Scaffolder-
1
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 13rd August 2015 - 28th Shawwal 1436

PROJECT NAME : Bridge 27-T218

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Removing backfilling to expose retaining wall is in progress
Marking and cutting for unsound concrete removal is in progress .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1, Small grinder-1 , Big grinder-1 , Air
compressor-1 , Jackhammer-1 , Air blower-1 , Wood
cutting machine-1 , Small jackhammer-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1, Chipping hammer is needed - Excavation around
Safety Officer-1,Site Engineer-1,Civil 16 piles is on hold because a permission is needed
Foreman-1 for excavation inside pipe line corridor-
Jackhammer operator is needed .
Direct: Mason-4 , Carpenter-1 , Labor-1 , Scaffolder-
1
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 15th August 2015 - 30th Shawwal 1436

PROJECT NAME : Bridge 27-T218

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Removing backfilling to expose bearin walls is in progress .
Marking and cutting for unsound concrete removal is in progress .
Removing unsound concrete with exposing rebars is started .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1, Small grinder-1 , Big grinder-1 , Air
compressor-1 , Jackhammer-1 , Air blower-1 , Wood
cutting machine-1 , Small jackhammer-1, Chipping
hammer-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1, Excavation around 16 piles is on hold because a
Safety Officer-1,Site Engineer-1,Civil permission is needed for excavation inside pipe
Foreman-1 line corridor- Jackhammer operator is needed .
Direct: Mason-3 , Carpenter-1 , Labor-1 , Scaffolder-
1 , Leadman-1
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 18th August 2015 - 03rd Dhu al-Qa'dah1436

PROJECT NAME : Bridge 27-T218

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Marking and cutting for unsound concrete removal is in progress .
Removing unsound concrete with exposing rebars is in progress .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1, Small grinder-1 , Big grinder-1 , Air
compressor-1 , Jackhammer-1 , Air blower-1 , Wood
cutting machine-1 , Small jackhammer-1, Chipping
hammer-1

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1, Excavation around 16 piles is on hold because a
Safety Officer-1,Site Engineer-1,Civil permission is needed for excavation inside pipe
Foreman-1 line corridor .
Direct: Mason-3 , Carpenter-1 , Jackhammer
operator-2 , Scaffolder-1 , Leadman-1
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail

SITE DIARY

PROJECT REF : 560-S28 Page No. ( 0 )


Date : 01st Sep 2015 - 17th Dhu al-Qa'dah1436

PROJECT NAME : Bridge 27-T218

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work : Housekeeping at site .


Chipping for bearing wall & slab bottom and side is in progress .
Formwork for bearing wall is in progress .
Slab bottom repair is in progress .
Concrete Work :

Arr. Dep. QC & other visitors comments

Material Deliveries : Plants,Equipments and/off site :


Generator-1, Small grinder-2 , Air compressor-1 ,
Jackhammer-1 , Air blower-1 , Wood cutting machine-1 ,
Small jackhammer-1, Chipping hammer-1 , Mixing drill-1 ,
Hilti Drill-1 , water drums-6

Manpower :- Other Comments/Information :


Indirect : Project Manager-1,Construction manager-1, Excavation around 16 piles is on hold because a
Safety Officer-1,Site Engineer-1,Civil permission is needed for excavation inside pipe
Foreman-1 line corridor .
Direct: Mason-3 , Carpenter-2 , Jackhammer
operator-2 , Scaffolder-1
QATAR ARMED FORCES
QATAR EMIRI CORPS OF ENGINEERS

SITE DIARY

PROJECT REF : F-309-01 Page No.


Date :

PROJECT NAME : Headquarters Building for Transport unit at Sailiyah Camp

CONTRACTOR : Progress including Samples and Tests :

MEP Work:

Site Work :

Concrete Work :

Arr. Dep. QECE & other visitors comments

Material Deliveries : Plants,Equipments and/off site :

Manpower:- Other Comments/Information :


Indirect :

Direct:

Weather :

QECE Sign : Contractor Sign :

You might also like