SITE DIARY
Material Deliveries :one ton steel received and blocks of 4" Plants,Equipments and/off site :
-1320-No. Received Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Inspection for Lintel Formwork & reinforcement in area A is completed.
Block work setting out in area C is started.
Concrete Work :
SITE DIARY
MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Block work setting out in area C is completed.
Concrete Work :
Concreting with 3Cu.M. of 30N-OPC for Lintel in area A is completed.
SITE DIARY
MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Concrete Work :
SITE DIARY
MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Concrete Work :
SITE DIARY
MEP Work:
Electrical GI box wall
Site Work : Block work is in progress in area A. piping and mechanical
Housekeeping is maintained. wall piping.
Concrete Work :
SITE DIARY
MEP Work:
Electrical GI box wall
Site Work : Block work completed at area A. piping and mechanical
Housekeeping is maintained. wall piping.
Concrete Work :
SITE DIARY
MEP Work:
Electrical GI box wall
Site Work : piping and mechanical
STOP WORKING DUE TO SECURITY REASON wall piping.
Concrete Work :
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Reinforcement for 1st floor beams at area B is started .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Reinforcement for 1st floor beams at area B is in progress .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Reinforcement for 1st floor beams at area B is in progress .
Formwork for 1st floor beams at area A is started.
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Reinforcement for 1st floor beams at area B is in progress .
Formwork for 1st floor beams at area A is in progress.
Concrete Work :
SITE DIARY
Site Work :
Reinforcement for 1st floor beams at area B is in progress .
Block work in area C is in progress.
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Lintel formwork in area C is started .
Reinforcement for 1st floor beams at area B is in proress .
Formwork for 1st floor beams at area A is in progress .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Lintel formwork in area C is in progress .
Lintel reinforcement in area C is started .
Reinforcement for 1st floor beams at area B is in progress .
Formwork for 1st floor beams at area A is in progress .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Lintel formwork in area C is completed .
Lintel reinforcement in area C is completed .
Reinforcement for 1st floor beams at area B is completed .
Formwork for 1st floor beams at area B is in progress .
Formwork for 1st floor beams at area A is in progress .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and completing septic tank is in progress .
Block work in area C is in progress.
Formwork for 1st floor beams at area B is in progress.
Formwork for 1st floor beams at area A is in progress .
Concrete Work :
Concreting with 2Cu.M. of 30N-OPC for Lintel in area C is completed.
SITE DIARY
Site Work : Excavation by poclain around the building for pipes trenches , manholes ,
car parking shed and septic tank is in progress and for sub- station is
started.
Block work in area C is in progress.
Formwork for 1st floor beams at area B is in progress.
Formwork for 1st floor beams at area A is in progress .
Concrete Work :
Concreting with 2Cu.M. of 30N-OPC for Sil in area A&C is completed.
SITE DIARY
Site Work : Excavation by poclain around the building for pipes and manholes , car
parking shed , sub-station and completing septic tank is hold because we
couldn't make gate pass for poclain driver because it is holiday today for
gate pass office .
Block work in area C is in progress.
Formwork for 1st floor beams at area B is in progress.
Formwork for 1st floor beams at area A is hold because we couldn't make
gate pass for carpenters because it is holiday today for gate pass office .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed , sub-station and septic tank is in progress .
Block work in area C is in progress.
Formwork for 1st floor beams at area B is in progress.
Formwork for 1st floor beams at area A is in progress .
Reinforcement for 1st floor beams at area A is started .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and septic tank is in progress and sub-station is hold because of
Kahramaah Company .
Block work in area C is in progress.
Formwork for 1st floor beams at area B is completed.
Formwork for 1st floor beams at area A is in progress .
Reinforcement for 1st floor beams at area A is in progress .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and septic tank is in progress and sub-station is hold because of
Kahramaah Company .
Block work in area C is in progress.
Formwork for 1st floor beams at area A is in progress .
Reinforcement for 1st floor beams at area A is in progress .
Concrete Work :
Concreting with 57 Cu.M. of 30N-OPC for first floor beams in area B is
completed.
Arr. Dep. QECE & other visitors comments
SITE DIARY
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed and septic tank is in progress and sub-station is hold because of
Kahramaah Company .
Block work in area C is in progress.
Formwork for 1st floor beams at area A is completed .
Reinforcement for 1st floor beams at area A is completed .
Formwork deshuttering ( sides only ) for 1st floor beams at area B is
completed .
Curing for 1st floor beams at area B with water .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Excavation by poclain around the building for pipes , manholes , car parking
shed is completed and septic tank is in progress and sub-station is hold
because of Kahramaah Company .
Block work in area C is completed.
Curing for 1st floor beams at area B with water .
Concrete Work : Concreting with 29 Cu.M. of 30N-OPC for first floor beams in area A is
completed.
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for septic tank and sub-station is hold because we
couldn't make gate pass for poclain driver because it is holiday today for
gate pass office and sub-station is hold also because of Kahramaah
Company .
SITE DIARY
Site Work : Excavation by poclain for septic tank is in progress and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is started .
Curing for 1st floor beams at area B & area A with water .
Material arrangement and housekeeping at site.
Concrete Work :
. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-11,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal
SITE DIARY
Site Work : Excavation by poclain for septic tank is in progress and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is in progress .
Curing for 1st floor beams at area B & area A with water .
Material arrangement and housekeeping at site.
Concrete Work :
. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal
SITE DIARY
Site Work : Excavation by poclain for septic tank is in progress and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is in progress .
Reinforcement for 1st floor beams at area C is started .
Curing for 1st floor beams at area B & area A with water .
Material arrangement and housekeeping at site.
Concrete Work :
. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-10 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal
SITE DIARY
Site Work : Excavation by poclain for septic tank is in progress and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is in progress .
Reinforcement for 1st floor beams at area C is in progress .
Curing for 1st floor beams at area A with water .
Material arrangement and housekeeping at site.
Concrete Work :
Material Deliveries : 1 ton of 8mm and 1 ton of 12mm Plants,Equipments and/off site :
straight reinforcement steel bars . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1
. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-10 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal
SITE DIARY
Site Work : Excavation by poclain for septic tank is completed and for sub-station is
hold because of Kahramaah Company .
Formwork for 1st floor beams at area C is completed .
Reinforcement for 1st floor beams at area C is completed .
Leveling for foundation level and plain concrete formwork for septic tank
are completed .
Curing for 1st floor beams at area A with water .
Material arrangement and housekeeping at site.
Concrete Work : Concreting with 29 Cu.M. of 30N-OPC for first floor beams in area C is
completed.
Concreting with 4 Cu.M. of 30N-OPC for plain concrete of septic tank is
completed .
Arr. Dep. QECE & other visitors comments
. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-10 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for saokways and R.G is started and for sub-station
is hold because of Kahramaah Company .
Formwork deshuttering ( bottoms and jacks ) for 1st floor beams at area B
is completed .
Formwork deshuttering ( sides only ) for 1st floor beams at area C is
completed .
Formwork for ground floor outer lintels at area B is started .
Reinforcement for ground floor outer lintels at area B is started .
Leveling for foundation level and plain concrete formwork for manholes are
started .
Curing for 1st floor beams at area C with water .
Material arrangement and housekeeping at site.
Concrete Work :
. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-10,
Labour-5,Plumber-2,Electricions-3
Weather :
Normal
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for saokways and R.G is in proress and for sub-
station is hold because of Kahramaah Company .
Formwork for ground floor outer lintels at area B is completed .
Reinforcement for ground floor outer lintels at area B is completed .
Leveling for foundation level and plain concrete formwork for manholes are
in progress .
Curing for 1st floor beams at area C with water .
Material arrangement and housekeeping at site.
Concrete Work :
. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-4, Steel Fixer-2 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for saokways and R.G is in proress and for sub-
station is hold because of Kahramaah Company .
Leveling for foundation level and plain concrete formwork for manholes are
completed .
Curing for 1st floor beams at area C with water .
Primer paintinig for plain concrete of septic tank is completed .
Material arrangement and housekeeping at site.
Concrete Work :
Material Deliveries : 2 tons of 12mm and 4 tons of 16mm Plants,Equipments and/off site :
straight reinforcement steel bars and wire mesh A-252 Generator-1,Roller Compactor-1,Plate
(8mm) -100 Nos . Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood
Cutting Machine-1,Water Pump-2,Hilty-
1,Drill Machine-1
. Other Comments/Information :
Indirect :
Project Manager-1,Site Manager-1,
Safety Officer-1,Site Engineer-1,Elec.
Engineer-1,Mech. Engineer-1,Foreman-
1,Mech. Foreman-1,Elec. Forman-2,
Surveyor-1,Ass.Surveyor-2
Direct: Mason-2, Steel Fixer-2 , Carpenter-2, Labour-
5,Plumber-2,Electricions-3
Weather :
Normal
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for saokways is completed and for R.G is in proress
and for sub-station is hold because of Kahramaah Company .
Roof columns reinforcement at area A is started ( stirrups) .
Curing for 1st floor beams at area C with water .
Material arrangement and housekeeping at site.
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for R.G is in proress and for sub-station is hold
because of Kahramaah Company .
Roof columns reinforcement at area A is completed ( stirrups) .
Curing for 1st floor beams at area C with water .
Material arrangement and housekeeping at site.
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain for R.G is in proress and for sub-station is hold because
of Kahramaah Company .
Setting out of block work for ground floor at area B is started.
Material arrangement and housekeeping at site.
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for R.G is in proress and for sub-station is hold because
of Kahramaah Company .
Block work for ground floor at area B is in progress .
Shuttering for manholes reinforced footings is completed ( to be placed in its
proper positions) .
Water proofing for septic tank plain concrete with membrane sheets is completed
.
Material arrangement and housekeeping at site.
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for R.G is completed and for sub-station is hold because
of Kahramaah Company .
Block work for ground floor at area B is in progress .
Reinforcement for septic tank footing is in progress .
Formwork for septic tank reinforced footing is started .
Material arrangement and housekeeping at site.
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
SITE DIARY
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Material Deliveries : 1440 Nos of 8" hollow blocks are Plants,Equipments and/off site :
received . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-
1 , bobcat-1
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Material Deliveries : 1650 Nos of 4" hollow blocks are Plants,Equipments and/off site :
received . Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-
1 , bobcat-1
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
SITE DIARY
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
RFT for screed for ground floor hollow core slabs at area B is started .
Material arrangement and housekeeping at site.
# Working is stopped because of Windy sandy storm from 10:00 am to 12:00 .
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Material Deliveries : 350 Nos of 6" hollow blocks . Plants,Equipments and/off site :
Generator-1,Roller Compactor-1,Plate
Compactor-1,Vibrator-2,Mixer Machine-
1,Bending Machine-1, Grinder-1,Wood Cutting
Machine-1,Water Pump-2,Hilty-1,Drill Machine-
1,
SITE DIARY
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Coordinates marking for 1st floor columns at area B by surveyor is completed .
Formwork for 1st floor columns at area B is started .
Material arrangement and housekeeping at site.
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for 1st floor columns at area B is in progress .
Erection of precast hollow core slabs at area C ( ground floor ) is completed .
Stirrups for parapet columns fixing at area C is completed .
Material arrangement and housekeeping at site.
Concrete Work :
SITE DIARY
Site Work : Excavation by poclain for sub-station is hold because of Kahramaah Company .
Formwork for 1st floor columns at area B is in progress .
Formwork for ground floor hollow core slabs ready mix concrete at area C is
started .
RFT for ground floor hollow core slabs ready mix concrete at area C is started .
Material arrangement and housekeeping at site.
# Work is stopped from 9:00am to 3:00pm because of windy sand storm .
Concrete Work :
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for drainage slabs at area D is completed .
RFT for drainage slabs at area D is completed .
Parapet block work at area C is in progress .
Material arrangement and housekeeping at site.
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Excavation by poclain for sub-station is hold because of Kahramaa Company .
Formwork for drainage slabs at area D is completed .
RFT for drainage slabs at area D is completed .
Parapet block work at area C is in progress .
Material arrangement and housekeeping at site.
Concrete Work : Concreting with 27 Cu.M. of 30N-SRC for septic tank walls is completed .
Concreting with 4 Cu.M. of 20N-OPC for 20 parapet columns at area A is
completed .
Concreting with 3.5 Cu.M. of 20N-OPC for A.Cs. footings at area A is completed.
Concreting
with 1.5 Cu.M. of 20N-OPC for drainage slab at area A is completed .
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
Concrete Work :
SITE DIARY
Concrete Work :
SITE DIARY
MEP Work:
Concrete Work :
SITE DIARY
MEP Work:
Concrete Work :
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
Site Work : Surface cleaning after sealer in area A and area B is started .
Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after sealer in area A and area B is in progress .
Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after sealer in area A and area B is in progress .
Housekeeping at site .
Beam work for F.F. is on hold .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after sealer in area A and area B is in progress .
Housekeeping at site .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are in progress .
Formwork for parapet columns at area C is started .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after sealer in area A and area B is in progress .
Housekeeping at site .
Internal plaster work in area C is in progress .
Manholes walls reinforcement and shuttering are completed .
Formwork for parapet columns at area C is in progress .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after sealer in area A and area B is completed .
Housekeeping at site .
Internal plaster work in area C is in progress .
Formwork for parapet columns at area C is completed .
Concrete Work : Concreting with 9 Cu.M. of 30N-SRC for manholes walls and 9 Cu.M. of 30N-OPC
for parapet columns at area C is completed .
Arr. Dep. QECE & other visitors comments
SITE DIARY
MEP Work:
Site Work : Filler 1st coat for internal painting at area A and area B is started .
Housekeeping at site .
Internal plaster work in area C is completed .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Filler 1st coat for internal painting at area A and area B is in progress .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Filler 1st coat for internal painting at area A and area B is completed .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after Filler 1st coat for internal painting at area A and area B is
started .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after Filler 1st coat for internal painting at area A and area B is in
proress .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after Filler 1st coat for internal painting at area A and area B is in
proress .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after Filler 1st coat for internal painting at area A and area B is
completed .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Filler 2nd coat for internal painting at area A and area B is started .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Filler 2nd coat for internal painting at area A and area B is in progress .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Filler 2nd coat for internal painting at area A and area B is completed .
Housekeeping at site .
Concrete Work :
SITE DIARY
MEP Work:
Site Work : Surface cleaning after Filler 2nd coat for internal painting at area A and area B is
started .
Housekeeping at site .
Sealer for internal painting at area C is completed .
Backfilling with fine sand and leveling up to sewage pipes bottom levels back side the
building is started
SITE DIARY
MEP Work:
Site Work : Surface cleaning after Filler 2nd coat for internal painting at area A and area B in
progress .
Housekeeping at site .
Surface cleaning after sealer for internal painting at area C is completed .
Filler 1st coat for internal painting at area C is started .
Backfilling with fine sand and leveling up to sewage pipes bottom levels back side the
building is completed .
SITE DIARY
MEP Work:
Site Work : Surface cleaning after Filler 2nd coat for internal painting at area A and area B is
completed .
Housekeeping at site .
Filler 1st coat for internal painting at area C is completed .
Sewage pipes installation back side the building is started .
False ceiling installation at areas A and B is in progress .
Formwork for roof beams at area D is started .
Reinforcement for roof beams at area D is started .
Internal plaster for parapet at areas A and C is completed .
Concrete Work :
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
Direct:
Mason-1, Welders-3, ( all working as labors )
Royal Commission for Jubail & Yanbu
Royal Commission in Jubail
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
SITE DIARY
MEP Work:
Site Work :
Concrete Work :
Direct:
Weather :