Professional Documents
Culture Documents
METHOD
STATEMENT FOR
ROAD LAYING WORKS Client :
(ANNEXTURE-A)
1
Contractor :
METHOD
STATEMENT FOR
ROAD LAYING WORKS Client :
PMC/CLIENT
REVIEWED BY APPROVED BY
NAME NAME
SIGNATURE SIGNATURE
2
Contractor :
METHOD
STATEMENT FOR
ROAD LAYING WORKS Client :
INDEX
1.0 SCOPE
4.0 REFERENCES
5.0 RESPONSIBILITIES
3
Contractor :
METHOD
STATEMENT FOR
ROAD LAYING WORKS Client :
1.0 Scope:
This Work Method Statement is prepared to provide guidelines for carrying out the
Road Laying works as per the drawings and work orders.
2.0 Scope:
This Method statement is applicable for Road Laying works of WTE, Dundigal.
Location of Road laying works shall be wherever applicable in WTE-Dundigal, as per the Work
order and GFC drawings.
4.0 References:
1. GFC Drawings
2. BOQ
3. Relevant IS codes wherever applicable
5.0 Responsibilities:
Site Engineer
QA/QC Representative
4
Contractor :
METHOD
STATEMENT FOR
ROAD LAYING WORKS Client :
6. If the results are satisfactory then leveling will be done & will
proceed to further, if the results are not satisfactory then compaction will be done
using baby roller to the required level of compaction on the mother soil.
7. Due to the loose soil conditions, if any excavation goes beyond the
required level, either the surface shall be dressed up to the lower most level to
maintain the uniform thickness of roads or filled up using the same material
excavated in the other area(CBR<15) of the roads or C&D GSB will be used. Where
ever required cutting & filling will be done in layers.
8. Both excavated soil(CBR,LLPL & MDD) as well as C&D GSB(AIV & MDD)
test reports for will be submitted.
5
Contractor :
METHOD
STATEMENT FOR
ROAD LAYING WORKS Client :
10. Using 10 ton capacity vibrator roller compaction will be done to the
required level by protecting the edges of the road up to kerb line.
11. Alternate panels will be casted while concreting as per drawing &
site conditions. Panel measurements are 5M length & 3.5M width.
13. Pouring of concrete will not be done not more than 1.5 M heights, if
the height exceeds 1.5M chute will be used for placing concrete.
14. Approved concrete mix design is used for concreting along with
Recron 3s fibers & broom finishing will be carried out.
15. Concrete compaction will be ensured with 60mm needle vibrator &
cubes shall be casted only if the concrete quantity is more than 3m3.
17. Curing bunds will be prepared for curing period of 7 days & site
engineer will be responsible for the same.
18. At every 20M interval expansion joint is provided with mastic pad
along with the dowel bars(reinforcement bars of 25mm or 32mm dia) as shown in
the drawing..
19. Alignment & straightness of the Road laying will be followed as per
drawings.
21. Dowel bars of dia 25mm or 32mm with 200mm center to center
spacing & PVC pipes along with caps will be placed before placing concrete as per
drawing at expansion joint
22. Turning radius of the road will be provided & maintained as per
drawings.
6
Contractor :
METHOD
STATEMENT FOR
ROAD LAYING WORKS Client :
23. After every 3rd Kerb stone a spacing of 150mm will be given to drain
out the water.
Joints:
The exact location & type of joint to be transferred at site as mentioned in drawing. All joints
shall be provided as per drawing. Mastic pad will be used as per site requirements.
Joint grooved will be constructed to an additional depth/width of 6mm width & 25mm
depth. The grooves shall be cleaned, dried, cleaned from dirt & loose material by air blasting.
Bitumen of grade 80/100 will be used in the Construction & Expansion Joints.