CR-F04
SITE VISIT REPORT
Rev : 0
Project / Job : PEMBINAAN TANGKI AIR BUKIT BATU SERTA KERJA-KERJA BERKAITAN
Date of Visit : 19 / 12 / 2022 Any Photograph attached
/ Yes No
Visited By : NASRUL ZUBAINI
Description of Report :
Project : CADANGAN PEMBESARAN LOJI RAWATAN AIR MERLIMAU FASA 2 DAN SISTEM AGIHAN
PAKEJ 4 - CADANGAN PEMBINAAN TANGKI AIR BUKIT BATU SERTA KERJA-KERJA BERKAITAN
Participants : 15 to 20
Scope of Works : 1) The works include the supply of all materials, labor, plant and others, necessary for the execution, completion, testing, commissioning and
maintenance of the works. The Civil, Structural and associated M&E works to be carried out under this Contract as follows:
Sales of Tender Documents : 21 December 2022 - 30 December 2022 ( Office hour only)
*Remark: Kindly refer to the tender briefing summary and site visit briefing for more detail.
1) Tender Bond/Earnest Money - in form for Bank Draft payable to PENGURUSAN ASET AIR BERHAD
and the mount of Tender Bond/Earnest Money is RM20,000.00
2) Performance Bond – 5% of the Contract Sum in Bank Guarantee format.
3) Retention Sum – equivalent of 10% of total value of work including materials on site up to 5% of
the Contract Sum shall be retained.
4) Lithography Expenses – successful tenderer will be required an additional of RM7,300.00 in the
form of Bank Draft payable to PENGURUSAN ASET AIR BERHAD.
5) Contract Duration – 18 months from the date of Site Possession Fix Contract Duration).
6) Tender Validity Period – Tender shall remain valid for a period of 120 days from the date of
tender closing.
7) Defect Liability Period (DLP) – 24 Months
2) Contractor must provide site office (shop lot) and site cabin at site.
3) Road access:
a. Contractor needs to deal with land owner (palm oil plantation)
b. No allocation for access road to site in the BQ
4) Client preferred contractor use same material brand with package 1. Kindly refer to the table
below:
MATERIAL BRAND
MS Pipe ALLPIPES
VALVE AVK
DI Pipe UDI
Table 1: material detail on site
5) Distance from existing reservoir (on going) to new reservoir is 6m and will have road in between
the reservoir.
TENDER BRIEFING
Photo 1: Tender Briefing - Cadangan Pembesaran Loji Rawatan Air Merlimau Fasa 2 dan Sistem
Agihan