Professional Documents
Culture Documents
To,
M/s China Overseas Engineering Co. Ltd., (COVEC)
Sunkoshi Marin Diversion Multipurpose Project
Sindhuli, Nepal
Subject: Application for Approval of Suppliers and Materials Intended for the Permanent Works
References:
1. Contract No: Civil-01/HRT/SMDMP/2077-78, Construction of Headrace Tunnel and Associated Structures for SMDMP
2. Volume II of III, Technical Specification, Sub-Clause 1.10 Suppliers of Materials
3. Volume II of III, Technical Specification, Sub-Clause 6.1.1 Cement
4. GCC Sub-clause 7.2 Samples
5. Contractor's letter Ref. no.: COVEC/NEPAL/SMDMP/2022081 dated 27 May 2022
6. Contractor’s e-mail dated 20 June 2022
Dear Sir,
We have no objection to the suppliers and materials intended for the permanent works proposed in the Contractor’s
above referenced letter (ref. 5) and supplemented by ref. 6 above.
The Contractor is requested to submit the samples of materials, and relevant information, to the Engineer for consent
prior to using the material in or for the Works, pursuant to Sub-clause 7.2 (a) of the GCC.
Yours sincerely,
Enclosure:
- N/A
Copy to:
- The Project Director, Sunkoshi Marin Diversion Multipurpose Project, Sindhuli, Nepal
- Mr. Salim Jahan Fahim, Country Director – Nepal, SMEC
- Mr. Bulent Demirca, Board Member, EMAY
- Mr. Ganesh Bahadur Shahi, AGM, Technical Department, Jade
- Mr. Krishna Prasad Paudel
- Mr. Naresh Kumar Neupane, ECoCoDE