CONTENTS
1. GENERAL 1
2. TEMPORARY WORKS 1
2.1 Temporary Construction Facilities 1
2.2 Construction Camp Accommodations 2
2.3 Temporary Site Facilities and Laydown Areas 2
2.4 Space Requirements 2
2.5 Medical Facility 2
2.6 First Aid and Emergency Services 2
3. ACCESS ROADS 2
3.1 Routes 2
3.2 Safety 2
3.3 Common Roadways 3
3.4 Contractor’s Roadways 3
4. FENCING 3
5. TEMPORARY POWER 3
6. CONSTRUCTION WATER 3
7. GENERAL SERVICES 3
7.1 General 3
7.2 Site Specific General Services 4
8. Transport - Personnel and Equipment 4
8.1 Vehicle Contract 4
8.2 Personnel and Equipment Transport 4
9. Construction Equipment 4
9.1 Equipment Requirements 4
9.2 Supplier Survey 5
10. Cement Supply 5
11. Materials Testing 5
1. GENERAL
Immediately after the Commencement Date, Contractor shall begin planning for the
Temporary Works required at Site to support the construction phase, from initial
mobilization through demobilization on completion of the Work. As Temporary Works are
a major cost, care must be taken to plan efficient and practical facilities. These facilities
shall be designed to support the field effort but shall be removed after Project completion
and the area restored to its original condition.
Note: All temporary facilities and camp accommodation shall be designed and
managed keeping in view and in accordance with Company’s and Government of
Pakistan’s established COVID-19 protocols.
2. TEMPORARY WORKS
2.1 Temporary Construction Facilities
Temporary construction facilities include, but are not limited to the following:
Area leveling & grading
Administrative and field offices
First aid, ambulance and medical services
Buildings, sanitary facilities, and sewage disposal
Access Roads
Fences, gates, and area lighting
Site fabrication facilities
Warehouse and laydown yards
Personnel and material transport
Concrete Batch Plant
Communication facilities
Security services
Utilities
Electrical Power
Site lunch facilities
3. ACCESS ROADS
3.1 Routes
Access roads shall be the responsibility of Contractor with the intent to enhance
construction mobility while mitigating the effects of traffic on existing roads.
3.2 Safety
Safety is a major consideration in planning for construction traffic. Therefore traffic lights
are suggested wherever construction traffic must cross existing roads. Also, construction
traffic must be limited to specific routes, which minimizes contact with, and impact on
existing roadways.
Shrubbery, bushes, trees and anything else that restricts vision at intersections should
be cleared for a minimum of 25 meters on either side and replaced with grasses or small
plants.
Trees and bushes may be replaced after all construction is complete but it would be
highly advisable to maintain the sight distances at the intersections permanently.
4. FENCING
Contractor shall properly fence the site accommodation camp, office, warehouse,
laydown areas, etc. Moreover, in order to restrict unauthorized movement of Contractor
resources within the operational facility while undertaking site construction, the
Contractor shall install fence all around the major work site area, as part of its scope of
work. The installed fence shall be removed by the Contractor once the construction
activities are completed, prior to demobilizing from site.
5. TEMPORARY POWER
Temporary power will not be available. Contractor shall determine needs and source
alternative methods for supplying power to work areas, offices, shops, warehouses and
camp, etc. at its own cost.
6. CONSTRUCTION WATER
Contractor is responsible for the supply of all water for construction activities including
temporary site facilities. Contractor shall determine needs, source and methods of
transport, storage and distribution for all construction/camp requirements, including
testing and flushing of all classes of piping systems and tanks.
Contractor shall also arrange for the reclamation and disposal of all water used for
hydro-testing, flushing and cleaning of pipe and equipment in compliance with the
applicable laws.
7. GENERAL SERVICES
7.1 General
The following activities shall be performed on a daily basis site-wide to support both the
infrastructure and the construction of the work:
Roadway maintenance
Trash removal and disposal
General clean-up of common areas and roadways
9. CONSTRUCTION EQUIPMENT
9.1 Equipment Requirements
Contractor shall supply all equipment required to complete the Work including that
needed for heavy lifts and transport.
Contractor shall fully comply with the requirements of all local regulatory bodies in
contracting construction equipment.
Company shall approve the cement supplier, batch pant, materials, and mix designs.