Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Quality Assurance Manual (Engineering, Procurement, Construction etc.)
Insurance Plan
Yard Fabrication Plan
Commissioning Plan
Transport Plan
Documents register / Issue Schedule / Status Register
Document Status Reports
Material Status Reports
Subcontract Status Reports
QA Audit Reports
Insurance Claim Reports
Site Survey Reports (all disciplines)
Method Statements as required
Basis of Design (all disciplines)
Scope of Work for Subcontracts
Engineering Close-out Report
Material Requisitions (all disciplines)
Technical Bid Evaluation and Reports (all disciplines)
Vendor technical recommendation report (all disciplines)
Preparation of purchase requisitions (all disciplines)
Purchase Orders (all disciplines)
Review of VENDOR drawings/ procedures / inspection and test
requirements (all disciplines)
Vendor Quality Plan, Test Procedures, Test Formats and FAT SCHEDULE
(all disciplines)
Inspection and test plans (ITP) (all disciplines)
Note: Third Party Inspection (TPI) shall be assigned by CONTRACTOR
Carry out inspection of equipment on behalf of the COMPANY and appoint
third party inspection agencies for carrying out the inspection (all
disciplines). All reports, inspections etc shall be endorsed by TPI.
Review of VENDOR documents including final dossiers (all disciplines)
Define requirements of Spare parts (Two Year operational spares and Pre-
commissioning/Commissioning) (all disciplines) and submit complete list of
Page 3 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
spares with complete info, description , make, part number, model, spec,
supplier, etc.
Define packing / marking / storage requirements (all disciplines)
Construction Specifications (all disciplines)
Site Installation Details (all disciplines)
Equipment factory testing reports (all disciplines)
Implementation Strategy and SCHEDULE
Maintenance Job Plans
Inspection plan
Installation Check Lists
Pre-commissioning Test Procedures
Commissioning Procedures
Operating Manual (including Update of existing Operating Manual)
Mechanical Data books and O & M Manuals
Final As – Built documents and drawings (all disciplines)
Welders list and repair rate
All Other project deliverables as required, not listed in this section
Commissioning Hand-over Certification packs
Page 4 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
o To confirm the lowest temp and suitability of material downstream
of all Blow Down Valves and depressurization valves and also the
lowest temp that can be seen in the upstream system due to de-
pressurization. The study also consider hydrate formation
temperature to finalize the Bold blowdown start temperature
Process / Utility Flow Diagrams, Heat & Mass Balance
Design ppressure & temperature report
Material selection Diagram
Piping & Instrumentation Drawings(Process and Utilities)
Safeguarding Schematics
Safeguarding Philosophy
Interface Report
Tie-In & Shutdown Philosophy
Cause & Effect Matrix
Process calculations (Equipment/Instruments/Piping)
Relief and Blowdown report (including Flare Network modelling)
Control and Shutdown Philosophy
Integrated Control and shut down philosophy
Integrated Cause and Effect Diagram
Relief and Blowdown Philosophy
Isolation philosophy
Drain, Vent & Flaring philosophy
CEMS Operation and Maintenance philosophy
CEMS RATA Report of validation
Commissioning & Start Up Philosophy
Pigging Philosophy & Procedure
Fluid List
Line list
Pipeline List
In-plant Line List
Equipment List
Utility Load / Consumption List
Page 5 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Chemical Users and Consumption List
Alarm & Trip Index
Battery Limit Connection Schedule
Tie-In Point Schedule
Valve Register
Process Equipment Datasheets
Process Instrument Datasheets
Description of Process and Utilities
Thermal relief valve requirement Report
o CONTRACTOR shall review the requirement and provide the
sufficient number of thermal relief valves (TRV) based on the
estimated entrapped volume during detailed engineering.
Integrated Operating Manuals
Integrated operating and maintenance procedures
Page 6 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
SIL Study Report
SIL Study Report for Vendor Packages
SIL Verification Study Report (including Vendor Packages)
SIMOPS report
Constructability report
Assumptions Register for QRA (inclusive of FEA) Study
QRA Report
Study Report for Air Quality Dispersion Modeling for Vents & Combustion
Sources
F&G Mapping Study Report
Purchase Requisition for Safety Studies
RFQ for Fire Fighting, Safety Equipment & Safety Sign
HSE action Tracking Register
RFQ for all Safety studies
Technical Bid Evaluation for fire extinguisher, Safety Equipment & safety
signs
Technical Bid Evaluation for Safety Studies
F&G Detector layouts
F&G Cause and Effect Chart
Gaseous fixed fire extinguishing system specification
Fire Extinguishers & Safety Equipment Specification and datasheets
MR for Fire Extinguishers, Safety Equipment & safety signs
Technical Bid Evaluation of Fire Extinguishers, Safety Equipment & safety
signs
Construction MS/RA
As built drawings/documents
Any other documents as identified during detail engineering for completion
of the project.
Page 7 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Equipment Baseline Survey Information with space for records of
subsequent inspections
Specifications
Material requisitions
Bid evaluation reports
Purchase requisitions
Vendor documents of Equipment / Package as per VDRL
Mechanical Handling Philosophy
Material Handling Report
Site visit reports
Any other documents as identified during detail engineering for completion
of the project.
Non Destructive Examination (NDE) Records.
Manufacturer Record Books
Page 8 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Piping component specifications, including pipe, fittings, flanges, manual
valves, gasket, bolting, pipe supports and special piping items (for items
not covered in COMPANY specification)
Material requisitions for all piping materials, including manual valves
Technical bid evaluation reports for all piping materials, including
deviation list
Piping speciality items list and datasheets
Manual valve datasheets
Critical line list
Piping stress analysis reports
Piping material take-off, including contingencies.
Manual valve list, including contingencies.
Detailed site survey reports, including piping interfaces
Piping construction standards, including sketches.
Piping welding specifications
NDT Procedures
NDT reports and material certification
PWHT procedure
Pressure test procedures
Pressure test packages
Inspection and test plans for piping construction
Piping quality control procedures
Piping commissioning and handover procedures
Comprehensive Inspection Plan for In Service Monitoring of Piping
Systems with Suggested types / techniques of Inspection and Suggested
frequency of Inspection
Key Plans of Monitoring Locations – Piping Systems (in service
monitoring)
Isometrics marked with Monitoring Locations – Piping Systems (in service
monitoring)
Baseline Survey Information with space for records of subsequent
inspections – Piping Systems (in service monitoring)
Any other deliverable not listed above but required for completeness of
project
Page 9 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Non Destructive Examination (NDE) Records.
Manufacturer Record Books
Dissimilar material connection specification /test procedures
Surface preparation / protective coating /wrapping
Valve tagging /stenciling details
Page 10 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Design Calculations for LCF and Electrical Substation buildings , supporting
structure and other related works, transformer foundations etc.,
Design calculations for drain drum pit
Layout and details of equipment foundations
Layout and details of pump foundations
Layout and details of package foundations
Layout and details of piperacks, pipe supports, flare support and foundations
Layout and details of pump shelters
General Arrangement and details of Transformer Gates and fence
Layout & details of internal roads, walkways & paving
Layout & details of fence & gates
Details of underground pits.
Details of Equipment & Package supporting structures
Layout and complete architectural, structural, electrical, mechanical and air-
conditioning details of LCF and Electrical substation buildings.
General Arrangement & Details of Stairs, Hand rails, Cat ladder and other
miscellaneous details
e) Bill of Quantities
Detailed Bill of Quantities for each construction deliverable shall be prepared
f) Any other deliverable not listed above but required for completeness of project
Lighting Calculations
Earthing Calculations
Page 11 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Earthing layouts
Cable schedule
Control schematics
Interconnection diagram
Demolition drawings
Construction Specifications
Page 12 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Road crossing standard drawings
Any other deliverable not listed above but required for completeness of
project
Basis of Design
Instrument IO list
Instrument Index
Instrument Specifications
Material Requisitions
Page 13 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Instrument sizing calculations for control Valves, Orifice plates, Safety Relief
Valves wake frequency calculation for TWs, Sizing calculation for Cables etc.
Separate Logic diagrams for all control systems such as DCS, ESD,F&G etc.
MAC Specification
DCS Specification
ESD/F&G Specification
Network drawing
Page 14 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Design manual - reports on EIA, Hazops etc.
Rotating equipment
Static equipment
Welding procedures
Fire protection and detection
Specifications Instruments
and Data Sheets Safety equipment
Structure and pipelines
Valves, vessels and pipe work
IT & communications equipment
HSEQ data sheets
Page 15 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Troubleshooting guide
2 Years operating spares and costs
Commissioning spares and costs
Capital spares and cost/approx. delivery times
Spare Parts Special tools
Recommendation
s Parts lists/bill of material/ cross sectional drawings
Purchase Order list with descriptions
Manufacturers contact details
Spare part storage & preservation requirements
Instrumentation and control systems (including cause & effect
matrices)
Plot plan and list of the major systems/equipment
PFDS, P&IDS, cause & effect matrices
Overall layout and area classification
Project and Piping layouts and isometrics
Vendor Drawings
Layout of each significant equipment item
Vessel general arrangement & internals
Electrical single line diagrams
Instrument loop diagrams
Control panel layouts and wiring diagrams
Master equipment lists
Fire and Gas Schedules
Equipment Lists
and Schedules Instrument Schedules
(including
Safety equipment Lists
manufacturer,
model / type, Piping Schedules
serial number,etc.
Cable Schedules
IT & Communications Equipment Schedule
Mechanical Quality Assurance Plan
Equipment
Certification and Equipment Certification
Test Reports Material Certification
Page 16 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Performance Curves
Baseline survey results for all pipework and static equipment.
All Test Reports
List of Hydro test pressures for pipework and static equipment.
LV Cable test cert
HV Cable test cert
Switchboards/busbar test cert
Circuit breaker test cert
Contactor/starter test cert
Fused switch test cert
Power transformer test cert
a. Soft copies in PDF of all drawings and DOCUMENTS prepared by CONTRACTOR shall
be submitted to COMPANY for review/comments and APPROVAL.
b. CONTRACTOR to submit Project Deliverables list for COMPANY approval and to identify
the ‘purpose of issued’ for each deliverable type (Issued for Information(IFI) or Issued for
Page 17 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Review(IFR)). The list shall cover all the disciplines. The Deliverables List shall be
submitted within four(4) weeks from the contract award date.
c. CONTRACTOR shall attach all reference files, which shall be bound to relevant 2D
AutoCAD files prior to forwarding to COMPANY for review.
d. SUBCONTRACTOR/VENDOR documents must be revised to “As-built” status by the
CONTRACTOR/VENDOR as part of their respective purchase orders and verified by the
CONTRACTOR.
e. CONTRACTOR shall prepare a detailed Document Management Plan, for the COMPANY
APPROVAL, to include the format for the COMPANY’s comment(s) or APPROVAL.
f. APPROVAL by the COMPANY shall not in any way relieve the CONTRACTOR of any of
their responsibilities or liabilities under the contract.
g. Any deliverable requiring the COMPANY APPROVAL shall first be submitted for the
COMPANY’s review and comments. After incorporation of the COMPANY’s comments,
the documentation shall then be submitted for COMPANY APPROVAL.
h. If COMPANY rejects any DOCUMENT, CONTRACTOR shall re-issue DOCUMENTS with
amendments as necessary for the COMPANY’s Review/ Approval.
i. CONTRACTOR shall submit COMPANY with all software native files (including input, pre-
processing, post processing and output files) of all software used in the detail engineering.
Those files should enable COMPANY to review, edit and run the undertaken analysis
independently.
j. Drawings / Documents Register
Within four (4) Weeks of the Effective Date of Award of the CONTRACT, the
CONTRACTOR shall provide a Master Document Register (MDR) for all documents /
drawings proposed for the Project execution. COMPANY document/drawing numbering
system shall be followed for execution of the Project.
The Register shall indicate for each drawing:
Page 18 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
CONTRACTOR shall prepare an index of the proposed manuals and submit this in
advance to the COMPANY for review. CONTRACTOR shall propose for the
COMPANY APPROVAL the proposed contents and formats for the DOCUMENTS.
e. The main reason for DOCUMENT handling through electronic data transfer is to
facilitate timely transmission of DOCUMENTS due for review and APPROVAL and to
avoid stacking of such DOCUMENTS to be approved in a tight time slot and also to
avoid unnecessary time delay encountered in document transmittal via courier
services together with the risk involved of miss-handling and damage to those
documents.
f. CONTRACTOR at the end of MECHANICAL COMPLETION activities shall handover
to the COMPANY at no cost all CD’s / DVD’s their back-up on the As-built status.
g. CONTRACTOR/VENDOR Drawings and Documentation shall be delivered in a
uniform book form. The books (grouping together drawings, indices, lists and
schedule) shall be of loose-leaf design and with a rigid CONTRACT specific cover
which gives protection for the complete set of copies reduced to A4/A3 format. Each
volume shall not be more than 75 mm thick. Index and format of these shall be agreed
with the COMPANY in advance.
Page 19 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
f. Flow assurance study – PIPESIM for steady state and OLGA for transient
analysis
o. Planning – Primavera
q. CONTRACTOR may utilise software other than that stipulated, on condition that
all relevant data is converted electronically and verified to the above formats prior
to handover to COMPANY.
Page 20 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
The CONTRACTOR shall prepare and issue DETAIL ENGINEERING Report after the
Approved for construction documents.
CONTRACTOR shall prepare final design dossier for COMPANY review and approval.
The design dossier covering all the design aspects shall include as a minimum the
following:
b. Specifications
d. Description of Systems.
f. Drawing index.
g. Document index.
Page 21 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
CONTRACTOR shall submit the dossiers for COMPANY review, comments and
approval. The dossiers shall include drawings, specifications, data sheets, material take-
offs and bills of material.
CONTRACTOR shall submit the list of contents and the format for the dossier for
COMPANY approval. As a minimum all design analysis and installation aspects shall be
covered in the design dossier.
Any assumptions made in the design analysis shall be fully explained and justified.
CONTRACTOR to provide sketches wherever possible.
Within two weeks of PROJECT completion CONTRACTOR shall provide the PROJECT
Close Out report, comprising as a minimum, but not limited to, the following topics:
a. PROJECT Description
i. Introduction
b. Scope of Services
g. List of Meetings
h. Lessons Learned
Page 22 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
j. Man-hour Histogram: Planned / Actual
c. VENDOR drawings
d. Installation instructions
e. Operating instructions
f. Maintenance instructions
g. Parts list with part identification including exploded views, itemized references,
cross sectional drawings, etc.
h. Lubrication schedule
a. HSE philosophy
Page 23 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
c. Operating Philosophy
d. Safety Systems
f. Material balances
g. Process description
h. Design conditions
l. Equipment list
b. Chemical pickling
f. Instrument checks
In general all the checks are required to ensure that the equipment is installed in
conformity with the specifications and drawings and is READY FOR COMMISSIONING.
Page 24 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
Some of the above checks can be performed on the modules prior to load out. The
CONTRACTOR shall define for each package (deck module, skid units, packages units)
the checks and test runs. The specification of these tests and checks will be included in
the purchase orders and contracts for fabrication.
a. Start-up procedures in both cases of initial start up and start up after shutdown
CONTRACTOR shall prepare Manufacturing Data records (MDR) consisting of all quality
assurance / quality control documentation of the material, manufacturer, fabrication,
erection and test history of the EQUIPMENT and BULK MATERIAL incorporated into the
PROJECT.
Manufacturing Data Records (MDR) are required to ensure that quality assurance and
quality control documents originating at the engineering, procurement, fabrication,
erection and pre-commissioning stages from multiple sources (CONTRACTOR, SUB-
CONTRACTORs, VENDORs, Suppliers, etc) shall be easily retrievable in order to verify
that EQUIPMENT and MATERIALS incorporated comply with all the CONTRACT
requirements at all stages of the PROJECT.
Page 25 of 26
Provision of Non-Associated Gas Compression Facilities (NCF03-7)
Project Deliverables & Requirements
_____________________________________________________________________________________
4.10 E-Manual
Note: CONTRACTOR shall comply with COMPANY drawing, document and Tag
numbering procedure indicated in COMPANY specification FEC-011, issued with Tender
package
CONTRACTOR shall prepare “As Built Drawings” based on the approved mark-ups,
progressively as they are being built and installed. All as built drawings shall reflect the
mechanical completion and pre-commissioning true status.