Professional Documents
Culture Documents
RECORD OF REVISIONS
Jadeja Associates
Project No. J3 Task 3A2 / 230097387 Date: 04.08.2020
Order/C
ontract
No.:
Prepared By: Mr. HASAN EMAM
Company Name: JADEJA ASSOCIATES
Building: N/A Area: Truck Parking Area - LC10, DTA
Pre-Task Briefings
Employees should be given the opportunity to talk about what is to be accomplished and what should
be avoided.
Possible negative consequences should be discussed to identify additional controls or barriers needed.
The supervisor and the employee can develop contingencies for the most likely and worst-case
outcomes.
Such thinking enhances situational awareness and improves application of error-prevention tools at
critical points in a task.
6.2. Injury to Persons Due 6.2.1. Keep Safe Distance from the
to hit the moving Part. Machines and Vehicles.
6.2.2. Wheel choke will be used while
parking of vehicle.
6.3.1. If depth of Pit more than 600 mm is
6.3. Injury Due To Topple to be Provided hard barricading.
of Hyva.
6.3.2. During vehicle driving, safe distance
will be maintained while passing nearby
any excavated area.
6.4. Injury due to fall of 6.4.1. No Excavation shall be left overnight
man in excavated area. without Barricades.
Jadeja Associates
6.4.2. Safe means of access will be ensured
to reach the work place in excavated
pit/trench.
6.5. Injury Due To Fall of
Material/Rock. 6.5.1. If the strenght of soil is week,
exacavation shall be carried out at an
angle of repose of soil & stepping for
access to be provided so as to avoid
danger of slide.
6.5.2. Trenches 1.2 Meters(4 Feet) Or
deeper must be shored or sloped back to
6.6. Collapse of Soil. the angle.
6.6.1. When The Depth Of Excavation is
more than 1.5 Meters, Properly
designed shoring and bracing shall
be placed on each bank side.
6.6.2. No Machinary or any crane or
Mobile Equipment shall be
positioned or operated nearby
edge of excavated area. Safe
distance i.e. 1.5 times of depth of
excavted pit/trench will be
maintained.
6.6.3. Dewatering from the pit shall be
done at remote location to avoid
back flow to the pit resulting in Soil
collapse.
6.7. Snake Bite.
6.7.1. Emergency Contact Numbers to be
displayed at Site.
6.7.2. Awarness to workmen will be given
about insect/snake bites.
6.7.3. All injury cases occurred at
worksite will be reported to RIL
medical center.
6.7.4. All Incident /Accident Should be
reported Immidiately to Supervisor,
Follow Instruction as Per HSE
Requirement.
7. Soil & rock Loading. 7.1. Vehicle (Hyva) 7.2.1. No overloading will be ensured.
topple due to overload 7.2.2. Safe distance will be ensured by
and Improper access. Driver during vehicle passing
nearby any excavted area.
Jadeja Associates
7.2. Vehicle Accident 7.2.3. Vehicle should not run with over
due to Traffic Problem. speed i.e. J3 construction area
speed limit will be followed.
7.2.4. Ensure vehicle is not parked on
road to avoid traffic problem.
7.2.5. Appoint/Assign Signal Man with
flags to control traffic problem at
site.
7.2.6. Traffic Safety Rules to be followed
at J3 premises.
7.2.7. Required Safety Signage Posters,
Caution Boards to be displayed at
prominent locations in worksite.
7.2.8. Reverse horn and indicators of
vehicle should be in working
condition always with audible
sound and it shall be ensured by
Driver before start the job.
7.2.9. Pre-use inspection of equipment
and tools. Defects to be reported
to supervisor and removed from
site or should be rectified
immediately.
8. Soil & rock Unloading 8.1. Fall of Dumper in 8.1.1. Ensure that dumping to be done at
Pond during 6 meter away from the edge of
unloading of pond.
excavated soil. 8.1.2. Ensure helper of Dumper being
assigned for signaling to the driver
from the backe side of Dumper.
8.1.3. Ensure dumping supervisor
available at Dumping Points.
9. Transportation of 9.1. Topple Of Dumper In 9.1.1. Provide Stopper on the edge of
materials excavated area. Excavation to Prevent falling of
Dumper in Excavation.
9.1.2.EnsureDumper involved in the Job
to be Provided with Reverse horn
with audible sound.
9.1.3. Signal man shall be assigned with
whistle to guide the movement of
Dumper & signaling during
backfilling.
Jadeja Associates
10. Work in Night Shift 10.1. Possibility of Incident 10.1.1. Ensure Proper Illumination is
due to Improper available at working area.
Illumination and 10.1.2. Competent supervision shall be
Supervision. ensured during night activities.
10.1.3. Provide Radium (reflective) type
Display board (Emergency Contact
Numbers, Assembly Point, Speed
Limit, Deep Excavation, First Aid
Box).
10.1.4. Ensure all Persons are using of
reflective Jacket.
11. Excavation by Using 11.1. Person Injury due to 11.1.1. Swing area of each Excavator
Machine. run over or hit by Should be barricaded.
Excavator or other Vehicle 11.1.2. Flag man to be provided with
. Flags/Whistle/On every roating
Equipements.
11.1.3. Ensure reverse horn to be in
working condition for all the
Vehicles.
11.1.4. Ensure the movement of
Equipements/Vehicles only after
getting signal from the Signal man.
11.1.5. Don’t allow any Person sitting
/taking rest under the
Equipements/Vehicles.
11.1.6. Routes of Traffic Movement should
be marked, Plan to be prepared &
Implemented.
11.1.7. Separate Pedistrian Path/ Walk
Way to be provided for the workers
movements.
11.2. Collapse of Soil. 11.2.1. Excavate the Pits or Trenches in
Slope or bench Cut as per code of
safety for excavation work. Place
the excavated soil away from the
pit/trench edge.
11.2.2. If the Strip Is less than 1 Mtr in
between two footings excavation
to be done for both footings
without any gap.
11.3. Fall of Equipements/ 11.3.1. Daily inspection of Excavated Pits
Vehicles in to Excavated to be carried out before entering
Pits. Fall Of Person Into into the Pits for identifying Cave in
Pits. Effects.
Jadeja Associates
11.3.2. Dewatering arrangements to be
Kept stand by depends on the
requirment.
11.3.3. Vehicles Movement shall not be
allowed at edge of excvated
portions.
11.3.4. Excavated Earth shall be stored
atleast away 1.8. Mtr from the
edge of pit.
11.3.5. Shoring shall be provided as per
Requirements of stanadard
Procedure.
11.3.6. Hard Barricading to be Provided
from 1.5 Mtr away from the Pit &
Stopper to be Provided at 500mm
away from the Barrier.
11.3.7. Necessary signage & blinkers to be
Provided.
11.3.8. Only Use Proper access& Ramp.
11.3.9. Ensure adequate Fall Protection to
11.4. Unauthorized be available.
Operation. 11.4.1. Vehicle operator should have valid
SDP, Unauthorised operation
strickly restricted.
11.5. Work nearby High 11.5.1. Area Isolation with Signage shall be
tenssion line. ensured.
11.5.2. Emergency contact numbers
should be known by all Group
Members.
12. Shifting of Excavated 12.1. Fall of Persons / 12.1.1. Provide Hard Barricading around
Soil/Rocks. Vehicles / Equipments the Excavated Pit to prevent
in to Excavated Vehicles coming closer to the Pit.
pit/trench. 12.1.2. Only Trained/Experienced
Operators should be Operate the
equipments/vehicles.
12.1.3. Inspected Equipements Shall be
used.
12.1.4. Avoid Stacking of Material near
edge of Excavated Pit.
12.1.5. Blinker to be provided at night.
12.1.6. Proper acess should be made
either by Providing ladders Or
Cutting Steps.
12.1.7. Make ramp with angle not more
than 15 shall be made if the
Jadeja Associates
excavated earth is to be moved by
Vehicles.
12.2.1. Only trained/experienced
12.2. Vehicles Accident operators should be operate the
While Moving on Equipements/Vehicles. Ensure
Common Roads. Inspected Equipements should be
used.
12.2.2. All Drivers Should be follow the
Road Traffic Safety Rules.
13. Genral Environment. 13.1. Oil Spillage. 13.3.1. Proper Maintenance Should be
done as per schedule of
Equipements/Vehicles and daily
inspection shall be done as per
Vehicle inspection checklist.
13.3.2. Drip Tray Should Be Provided.
13.3.3. Diesel Fueling by Diesel Browser.
13.3.4. Tray Should Be Provided While
Manual Fueling.
13.2. Soil Erosion Or 13.2.1. Proper dewatering arrangement
Warer Stragtion Inside will made available to avoid water
The Pit Due To Heavy Stagnation.
Rain, Or Spillage From
The Earth. 13.3.1. Use of Mandatory PPE (Nose Mask)
13.3. Dust Exposure.
14. Genral Habits. 14.1. Adopting short cut 14.1.1. STA to be prepared on daily basis
method, Negligence and TBT conducted for all Workers
Wrong Perception, Absent before beginning of the job.
mind, Using Cell Phone.
14.1.2. Training for Motivation is required.
14.2. Work Related Night 14.2.1. Same Person shall not allow for
Shift , Over Time. continuing work since day shift &
Night Shift.
14.2.2. More than 12 Hours Work should
not be Carried Out .
14.2.3. Driver should take rest atleast 15
Minutes for every 2 Hours.
14.2.4. Instruction will follow from the
respective supervisor according to
Job tasks.
Jadeja Associates
15. Vehicle Refueling . 15.1. Fire Hazards & 15.1.1. Only at designated place shall be
Contamination of used for refueling.
Soil. 15.1.2. Fire Preventive Measure& Spill Kit
must be available.
15.1.3. Arrange Drip Tray in order to avoid
Spillage.
15.2.1. Emergency Contact Numbers
Should be displayed.
15.2. Absence of
Emergency Vehicle. 15.2.2. Ensure of Transporting of Medical
Urgency is made available.
Lead Engineer