You are on page 1of 127

BILL NO.

1
PRELIMINARIES

Pages 1.1 - 1.7


BILL NO. 2
PREAMBLES
Pages 2.1 - 2.59
BILL NO. 3
TB-ISOLATION WARD
Pages 3.1 - 3.31
BILL NO. 4
FENCE,GATE AND GUARDHOUSE
Pages 4.1 - 4.30
BILL NO. 5
EXTERNAL WORKS
Pages 5.1 - 5.12
BILL NO. 6
LANDSCAPE
Pages 6.1 - 6.6
BILL NO. 7
PRIME COSTS AND PROVISIONAL SUMS
Page 7.1
BILL NO. 6
ESHS MANAGEMENT
Pages 8.1-8.4
MAIN SUMMARY
BILL NO.1 - PRELIMINARIES AND GENERAL
Item Description

PRELIMINARIES AND GENERAL ITEMS

These Preliminaries shall be priced in full with amounts against the


individual items or parts of items for which payment is required. Items
or parts of items against which no price is entered shall be deemed to
be covered by the other prices entered elsewhere by the contractor.

GENERAL MATTERS

2.1 Provision of Performance Security

2.2 Provision of Insurance

2.3 Furnishing the Engineer's Site Office including all furniture and basic
office equipment

2.4 Plant
Provide for all plant necessary for the proper execution of the works
comprising:-

i. Mechanical plant, vehicles and the like


ii Non-mechanical plant, tools, equipment and the like

2.5 Safeguarding the works, materials and plant

Provide for all necessary watching and lighting and take general
security measures to safeguard the works, materials and plant,
including sub-contractor's property, against damage and theft.

Provide all necessary measures for the safety of the public for the
duration of the contract.

2.6 Maintenance of roads and foot paths

Provide for maintaining all public and private roads and footpaths
adjacent to or upon the site. The contractor shall be held responsible
for making good at his own expense any damage thereto including that
caused by sub-contractors or the transport of suppliers and shall pay all
costs and charges in connection therewith.
CARRIED TO COLLECTION
1.1
Item Description

2.4 Protection of services


Allow for ascertaining from the various statutory undertakings the
position of any live services within the confines of the site.

Provide for protecting, upholding and maintaining all pipes, ducts,


sewers, cables and the like which form part of public or private services
adjacent to or upon the site. The contractor shall make good at his own
expense any damage due to any cause which his proper control would
have prevented and shall pay all costs and charges in connection
therewith

OBLIGATIONS IMPOSED BY THE EMPLOYER

2.5 Programme of operations

The contractor shall within twenty-eight days from the date for
possession of the site, submit to the Engineer for his approval and
information and in a form approved by him, three copies of a
programme in which is set forth the sequence of all operations and the
time limits which the contractor proposes that each operation shall be
commenced and completed. The agreed programme may be varied
with the consent of the Engineer but the responsibility for completion
within the time stated shall remain with the contractor

The programme shall be in such a form as to enable the programme


and sequence of work to be compared with the actual progress of the
works. A copy of the agreed programme and progress shall be kept up
to date upon the works.

2.6 Protection of existing buildings


Allow for protecting the existing buildings, pavings and cultivated areas
including providing temporary casings and guard rails etc where
necessary

2.7 Working within the site

The contractor shall confine all goods, materials and plant, within the
boundaries of the site and only in positions approved by the Engineer

Allow for preventing workmen from trespassing upon the property


beyond the confines of the works at all times.
CARRIED TO COLLECTION
1.2
Item Description

2.8 Notice board and Direction Signs

The contractor shall provide, erect, paint, letter as requiredand maintain


in a position, approved by the Engineer on a main road, 1No double
faced notice boards overall size 2.74 x 5.80 metres. The wording
permitted on the notice board shall be only that which is specifically
authorized by the Engineer. All signs and the notice board shall be
removed and disturbed areas made good upon completion of the works

Personnel

2.9 Expatriate personnel recruited for the project shall be subject to the
current Laws of Malawi. Bidders attention drawn to the Customs
Regulation relating to first entry previleges.

The contractor shall allow in his bid for the time and costs involved in
carrying out the above procedures and making the necessary
applications.
CARRIED TO COLLECTION
1.3
Item Description

Temporary Roads

2.9 Provide and maintain all necessary temporary roads, gangways tracks,
hardstandings, crossings and the like required for the proper execution
of the works.

Temporary Screens

2.10 Provide, erect and maintain such temporary screens and the like as
may be specifically required.

Temporary hoardings and gantries

2.11 The contractor shall provide, erect and maintain all necessary
temporary fencing, hoardings fans with a minimum height of 5 meters,
planked footways, guard rails, gantries and the like for the proper
execution of the works and for the protection of the general public and
the occupants of adjacent premises and for meeting to requirements of
any relevant national or local regulations. The contractor shall allow for
altering, shifting and adapting any item of the foregoing as and when it
may be necessary and also for providing suitable to ensure its
effectiveness at all times during the execution of the works.

General Scaffolding

2.12 Provide and erect all scaffolding including all stages trestles, planks,
guard rails, barrow runs and the like required for the execution of the
works and maintain, alter and adapt as necessary and remove when no
longer required.

All scaffolding shall be in accordance with the provisions of the


Factories Act and current building (Safety, Health and Welfare)
regulations.

Water for the works


2.13

The contractor shall provide clean, fresh water, free from chemical or
organic impurities or other deleterious matter, for use on the works, pay
all charges in connection therewith, provide all temporary storage,
plumbing services, connections and the like and clear away and make
good upon completion of the works. Bidders should ascertain for
themselves that the site has adequate water services to enable the
construction of and allow for any additional costs that might be incurred.

Power for the site


2.14 Provision of electric power to Engineer's offices and Laboratory.

CARRIED TO COLLECTION
1.4
Item Description

WORKS BY PUBLIC BODIES

General

2.15 Works which are required to be carried out by a local authority or public
undertaking are dealt with separately

PROTECTING, DRYING AND CLEANING THE WORKS

Protection of the works

2.16 The contractor shall provide, erect and maintain all necessary
temporary casing, masking and screening to partly finished work
engaged by the Employer and shall also provide all necessary
temporary roofs, tarpaulins, screens, planking and general protection
necessary to protect the works from damage by frost and inclement
weather and provide all temporary gutters, pipes, surface water drains
and the like for conveyance of rainwater and clear away when no longer
required

Drying the works

2.17 The contractor shall be responsible for the adequate drying out of the
works and for maintaining them at a suitable temperature and humidity
until handed over.

2.18 Clean the works internally and externally upon completion to the
satisfaction of the Engineer
CARRIED TO COLLECTION
1.5
Item Description

2.18 Testing of Materials

Allow a provisional sum of K500,000.00 Kwacha in respect of testing of


materials

Demobilisation

2.19 Demobilisation of Contractor's equipment and labour, cleaning up the


areas to the satisfaction of the Engineer

2.20 Project Managers Equipments

Allow for a provisional sum of K5,000,000.00 (Five Million Malawi


Kwacha) for purchasing project manager's equipments
CARRIED TO COLLECTION
1.6
Item Description

COLLECTION

PAGE 1.1

PAGE 1.2

PAGE 1.3

PAGE 1.4

PAGE 1.5

PAGE 1.6
TOTAL PRELIMINARIES AND GENERAL ITEMS CARRIED TO
GRAND SUMMARY
1.7
Amount (MK)
-

Amount (MK)
-

Amount (MK)
-

Amount (MK)
-

Amount (MK)
-

Amount (MK)

500,000.00

5,000,000.00
5,500,000.00

Amount (MK)

5,500,000.00
5,500,000.00
TB ISOLATION WARD

Item SUBSTRUCTURE Unit Qty Rate K t


(ALL PROVISIONAL)

Refer SMM paragraph F19(a). It has been been assumed that strip footings,
bases, beds and the like within the ground will be poured against natural ground. If
formwork is required to such surfaces, the contractor must include for the same in
his excavations/concrete rates

EXCAVATIONS

A Excavate trench from reduced level for strip footing 0 to 1500mm deep. M3 299 1,000.00 299,000.00
-
B Pit from reduced level for isolated piers, not exceeding 1500mm deep M3 3 1,500.00 4,500.00
-
C Selected earth filling, deposited, spread and compacted 150mm layers around
foundations M3 170 2,500.00 425,000.00
-
Rock excavation -
-
D Extra over all types of excavation for excavating in rock
M3 45 15,000.00 675,000.00
Disposal -
-
E Surplus excuvated material from excavations, transported a distance average 100
linear metres from excavations, deposit, spread and level as directed M3 129 3,000.00 387,000.00
-
Hardcore filling to pass a 50mm ring all ways -
-
F 150mm thick (consolidated) filling well compacted and rolled M2 553 600.00 331,800.00
-
Sand blinding -
-
G 50mm Bed of sand on hardcore, rolled to receive damp proof membrane M2 553 600.00 331,800.00
-
Damp proof membrane -
-
H 125 microns(500 gauge) Polythene damp proof membrane with welted joints,
lapped 150mm at all joints and laid on blinded hardcore M2 575 600.00 345,000.00
-
Ant treatment -
-
I Saturate surface of hardcore and top of brick walls with approved ant repellant M2 575 600.00 345,000.00
-
generally -

J To bottom and sides of excavated trenches M2 1183 600.00 709,800.00

-
-

CARRIED TO COLLECTION K 3,853,900.00


3.1

TB-ISOLATION WARD
TB ISOLATION WARD

Item SUBSTRUCTURE Unit Qty Rate K t


(ALL PROVISIONAL)

SUNDRIES

A Include for planking and strutting to faces of excavations Item

B Include for keeping all excavations free from water. Item

CONCRETE WORK

In-situ concrete; plain; Class 15N/mm2/40mm

C Strip footings M3 45 100,000.00 4,500,000.00


-
D Ditto 400 x 400mm block columns M3 1 100,000.00 100,000.00

Plain in-situ concrete class 21N/mm2/20mm -


-
E 100mm thick horizontal bed, laid in bays generally 25 square metres, including
formwork to construction joints M2 575 20,000.00 11,500,000.00
-
Wrot Formwork -
-
F Edge of slab; 75 to 150mm wide M1 168 3,500.00 588,000.00
-
Reinforcement -
-
G Hard drawn mild steel fabric reinforcement reference A142 weighing 2.22kg/m2
embedded in concrete slab to BS 4483 (measured net; no allowance made for
laps). M2 575 4,500.00 2,587,500.00
-
BLOCKWORK -
-
Hollow precast cement and sand blocks in cement mortar (1:4) filled solid with
concrete (grade 15/40) -
-
H 200mm Walls M2 444 20,000.00 8,880,000.00
-
I Ditto for 400 x 400mm columns M 8 5,000.00 40,000.00
-
-
-
-
-
-
-
-
-
-

CARRIED TO COLLECTION K 28,195,500.00


3.2

TB-ISOLATION WARD
TB ISOLATION WARD

Item SUBSTRUCTURE Unit Qty Rate K t


(ALL PROVISIONAL)

PLASTERWORK

15mm Rendering (1:4) cement and sand, finished


with a wood float

A Block/ concrete walls M2 252 3,500.00 882,000.00


-
-
B Ditto for 400 x 400mm columns M 32 3,000.00 96,000.00

PAINTWORK -
-
Prepare and apply black bituminous paint -
-
C Rendered walls M2 252 4,500.00 1,134,000.00
-
D Ditto for 400 x 400mm columns M 32 3,500.00 112,000.00

CARRIED TO COLLECTION
2,224,000.00

COLLECTION Page
No

3.1 3,853,900.00

3.2 28,195,500.00

3.3 2,224,000.00

SUBSTRUCTURE - CARRIED TO SUMMARY K 34,273,400.00

TB-ISOLATION WARD
TB ISOLATION WARD

3.3

Item ROOF Unit Qty Rate K t


(ALL PROVISIONAL)

"CHROMADEK" CLADDING

A 0.50mm (26 gauge) "Chromadek" IBR profile prefinished steel cladding, laid with
one flute side laps and 300mm minimum end laps, fixed to timber purlins with and
including 75mm long drive screws (purlins generally at 1050mm centres) and side
laps with 6 x 25mm sheet bolts at 600mm centres. All fixings to be complete with
bitumen and flat galvanised steel washers. M2 843 25,000.00 21,075,000.00
-
Flashing shall be 0.55mm (26 Gauge) "Chromadek" steel sheet, bent to required
shape, fixed as required and shall include all labours, nails, clips, welges and laps
and joints in the running length -
-
B Ridge flashing, 450mm girth, once bent, dressed to ribs of roofing and fixed to
timber M 52 3,500.00 182,000.00
-
C Hip flashing ditto M 128 3,500.00 448,000.00
-
D Serrated ridge closer piece, fixed to timber M 360 3,500.00 1,260,000.00

E Valley gutter, 450mm girth once bent and fixed to timber M 94 3,500.00 329,000.00
-
CARPENTRY -
-
Framing -
-
Treated sawn softwood -
-
F 150 x 50mm rafter M 699 1,000.00 699,000.00

G 150 x 50mm king post M 184 1,000.00 184,000.00


-
H 150 x 50mm tie beam M 646 1,000.00 646,000.00
-
I 75 x 50mm purlins M 762 1,000.00 762,000.00
-
J 100 x 50mm wall plate M 303 1,000.00 303,000.00
-
K 150 x 50mm struts M 649 1,000.00 649,000.00

Metal work -
-
L 1200 x 50 x 1.63mm (16 gauge) galvanised hoop No 95 10,000.00 950,000.00
iron wall plate anchor one end split, bent and built into -
brickwork, twice holed and spiked to rafters. -
-
-

CARRIED TO COLLECTION K 27,487,000.00


3.4

TB-ISOLATION WARD
TB ISOLATION WARD

Item ROOF Unit Qty Rate K t


(ALL PROVISIONAL)

Fascia/ Barge board

A 247 x 15mm NUTEC Fascia/ barge board M 303 2,000.00 606,000.00


-
PAINTING AND DECORATING -
-
Prepare, knot, stop, prime and apply one undercoat and two finishing coats of
Exterior PVA Paint on -
-
B Timber general surfaces not exceeding 300mm girth M 303 3,500.00 1,060,500.00
-
Rainwater System shall be "Marley Vynadeep" -

C 125mm Half round section gutter DGH520 fixed to M 303 2,000.00 606,000.00
falls with brackets at 900mm centres, screw fixed to -
fascia board -
-
D Extra over for 80mm diameter outlet DO503. No 26 6,000.00 156,000.00
-
E Extra over for corner angle DA503. No 31 6,000.00 186,000.00
-
F 80mm Diameter downpipe DPH308 fixed to wall with M 39 2,000.00 78,000.00
brackets. -
-
G Extra over for swanneck bend DNB30. No 31 6,000.00 186,000.00
-
H Extra over for shoe No 31 6,000.00 186,000.00
-
-
-

CARRIED TO COLLECTION 3,064,500.00

COLLECTION Page
No

3.4 27,487,000.00

3.5 3,064,500.00

CARRIED TO COLLECTION K 30,551,500.00


3.5

TB-ISOLATION WARD
TB ISOLATION WARD

Item EXTERNAL AND INTERNAL WALLS Unit Qty Rate K t


(ALL PROVISIONAL)

CONCRETE WORK

Reinforced vibrated in-situ concrete class 21N/mm2/20mm

A Ring beam M3 14 200,000.00 2,800,000.00


-
B Retaining wall M3 16 200,000.00 3,200,000.00

Sawn Formwork -
-
C Sides and soffit of beam M2 155 18,000.00 2,790,000.00
-
Reinforcement (Provisional) -
-
D 12mm diameter mild steel rod reinforcement Kg 642 2,500.00 1,605,000.00
-
E 8 mm diameter ditto Kg 362 2,500.00 905,000.00
-
BLOCKWORK -

EXTERNAL WALLS
-
Precast hollow cement and sand blocks in -
cement mortar (1:4 filled solid with concrete -
(Grade 15/40) -
-
F 200 mm Thick walls M2 495 20,000.00 9,900,000.00
-
G Ditto 400 x 400 columns M 24 5,000.00 120,000.00

DAMP PROOF COURSE -


-
H 3ply "Malthoid" damp proof course 200mm wide, laid under blockwall. M 329 600.00 197,400.00

INTERNAL WALLS -
-
Precast hollow cement and sand blocks in -
cement mortar (1:4 filled solid with concrete -
(Grade 15/40) -
-
I 200 mm Thick walls M2 791 20,000.00 15,820,000.00
-
-
-
-
-
-
-
-
-

CARRIED TO SUMMARY K 37,337,400.00


3.6

TB-ISOLATION WARD
TB ISOLATION WARD

Item WINDOWS AND DOORS Unit Qty Rate K t

WINDOW CILL

600 x 250 x 65mm thick block tiled window cill, splay rebated once grooved and
A exposed chamfered, finished fair on all exposed surfaces and built into blockwork No. 3 50,000.00 150,000.00
-

1200 x 250 x 65mm thick block tiled window cill, splay rebated once grooved and
B exposed chamfered, finished fair on all exposed surfaces and built into blockwork No. 48 20,000.00 960,000.00
-

1800 x 250 x 65mm thick block tiled window cill, splay rebated once grooved and
C exposed chamfered, finished fair on all exposed surfaces and built into blockwork No. 10 50,000.00 500,000.00
-
-
Doors -
-
Hardwood Doors -
-
Supply and fix hardwood doors, finished with clear vanish -
-
D 1500 x 2040mm high glazed hardwood double door No 3 100,000.00 300,000.00
-
E 1500 x 2100 mm high glazed hardwood double door No 2 100,000.00 200,000.00
-
Flush panel doors shall be 45mm finished thickness, faced both sides with internal
quality plywood finish lipping on sides -
-
F 800 x 2100mm High semi Solid core flush door No 13 60,000.00 780,000.00
-
G 900 x 2100mm High Solid core flush door No 15 60,000.00 900,000.00
-
Steel Door frames -
-
Rates shall include for lugs welded to back, buiding into blockwork and filling cavity
with cement and sand (1:3) -
-
H Door frame (1.2mm thick) size 1500 x 2100mm overall suitable for 200mm wall,
complete with one and half pair of butts No 5 40,000.00 200,000.00
-
I Ditto, size 800 x 2100mm ditto No 13 40,000.00 520,000.00
-
J Ditto, size 900 x 2100mm ditto No 15 40,000.00 600,000.00

-
-
-
-
-
-
-
-
-

CARRIED TO COLLECTION K 5,110,000.00


3.7

TB-ISOLATION WARD
TB ISOLATION WARD

Item WINDOWS AND DOORS Unit Qty Rate K t

Window Frames

Steel windows frames

Purpose made mild steel horizontal bar windows with lugs welded. All
opening lights complete with ironmongery, including projecting hinges and
whole to be treated before delivery with one coat of red oxide primer, built
into blockwork
-
A 600 x 650 mm high window frame No 3 40,000.00 120,000.00
-
B 1200 x 650 mm high, ditto No 48 40,000.00 1,920,000.00
-
C 1800 x 1200 mm high, ditto No 10 40,000.00 400,000.00
-
-
-
GLAZING -
-
Clear sheet glass -
-
D 4mm thick Glass, fixed to metal/steel with mastic putty in panes, 0.10 to 1.00m2
M2 62 18,000.00 1,116,000.00
-
Obsure sheet glass -
-
E 4mm thick fixed to metal/steel with mastic putty in panes, 0.10 to 1.00m2 M2 48 18,000.00 864,000.00
-
PVC/ STEEL/HARDWOOD -
-
F Supply and Install, Curtain Rods M 77 1,500.00 115,500.00
-
G White pvc curtain rod bar and accessories or equal and approved M 48 1,500.00 72,000.00
-
H Extra; curtain rod ends No 122 3,000.00 366,000.00

PAINTING AND DECORATING -


-
Prepare and apply three coats wood guard double life vanish on -
-
I Hardwood doors M2 33 4,500.00 148,500.00
-
Prepare, prime and apply one undercoat and two finishing coats of full gloss -
enamel on
-
J Metal general surfaces M2 337 4,500.00 1,516,500.00
-
Prepare, knot, prime, stop and apply one undercoat and two finishing coats of -
gloss paint on
-
K Flush doors M2 104 4,500.00 468,000.00

CARRIED TO COLLECTION 7,106,500.00

COLLECTION Page
No

3.7 5,110,000.00

3.8 7,106,500.00

CARRIED TO SUMMARY K 12,216,500.00


3.8

TB-ISOLATION WARD
TB ISOLATION WARD

Item IRONMONGERY Unit Qty Rate K t


(ALL PROVISIONAL)

Supply and fix the following ironmongery: Locks and furniture where applicable are
to be equal to those manufactured by "ASSA Abloy" and approved by the Architect

Doors

A 1.5 Pairs 100 mm Brass Butt Hinges No 68 9,000.00 612,000.00


-
B 3 lever mortice lockset union cat; 2295-76 PL or similar -
approved No 39 20,000.00 780,000.00
-
C Door signage/ Engraved plates as by ASSA ABLOY Catalogue 2017/2018; No 39 10,000.00 390,000.00
SS5066-06SSS
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

CARRIED TO SUMMARY K 1,782,000.00


3.9

TB-ISOLATION WARD
TB ISOLATION WARD

Item WALL FINISHES Unit Qty Rate K t


(ALL PROVISIONAL)

INTERNAL

Plasterwork

15mm Rendering (1:4) cement and sand, finished with a final coat of lime putty,
steel trowelled

A Blockwalls M2 2077 3,500.00 7,269,500.00


-
15mm Rendering (1:4) cement and sand backing, finished to receive tiles -

B block/concrete walls; over 300mm wide M2 195 3,500.00


-
TILER -
-
C 300 x 300 x 6mm white glazed cushion edged tiles, adhesive fixed and pointed
with grout to rendered walls subject to architect's samples approval M2 195 20,000.00 3,900,000.00
-
PAINTING AND DECORATING -
-
Prepare and apply one water thinned and two coats of Wash and Wear paint on
-
-
D rendered walls M2 2077 4,500.00 9,346,500.00
-
EXTERNAL -
-
Plasterwork -
-
15mm Rendering (1:4) cement and sand, finished with wood float on -
-

E Blockwalls M2 496 3,500.00 1,736,000.00


-
PAINTING AND DECORATING -

Prepare and apply one water thinned and two coats of Wash and Wear paint on
-
-
F rendered walls M2 496 4,500.00 2,232,000.00
-
-

WALL FINISHES - CARRIED TO SUMMARY 24,484,000.00


3.10

TB-ISOLATION WARD
TB ISOLATION WARD

Item FLOOR FINISHES Unit Qty Rate K t


(ALL PROVISIONAL)

SCREED

30mm cement and sand (1:3) backing finished to receive tiles

A Concrete floors M2 575 3,500.00 2,012,500.00


-
EPOXY FINISH -
-
Etching, cleaning the floor screed using sugar soap, prepare and apply, three
coats of epoxy on -
-
B over 300mm wide M2 575 3,500.00 2,012,500.00
-
C Less than 300mm wide M 410 3,000.00 1,230,000.00
-
TILES -

300 x 300 x 6mm thick approved Non slip porcelain floor tiles : bedded and jointed

in approved adhesive : pointed with approved coloured grout :on -


-
D Concrete floors in all water borne areas M2 86 20,000.00 1,720,000.00
-
-
E 10 x 100mm high porcelain tile skirting m 97 3,500.00 339,500.00

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-

FLOOR FINISHES - CARRIED TO SUMMARY K 7,314,500.00


3.11

TB-ISOLATION WARD
TB ISOLATION WARD

Item CEILING FINISHES Unit Qty Rate K t


(ALL PROVISIONAL)

INTERNAL

CARPENTRY

Framing

Unless otherwise stated, all timber shall be treated wrot softwood -


-
A 50 x 50mm Brandering M 2546 1,500.00 3,819,000.00
-
B Ditto fixed along block/concrete wall M 410 1,500.00 615,000.00
-
JOINERY -
-
Panneling -
-
Ceiling board -
-
C 6mm thick Nulite ceiling board fixed to timber M2 575 6,000.00 3,450,000.00
-
Battens -
-
D 50mm Hardwood cornice M 481 3,500.00 1,683,500.00
-
PAINTING AND DECORATING -
-
Prepare and apply one thinned coat and two coats of internal quality PVA on -
-
E Nulite ceiling board M2 575 4,500.00 2,587,500.00
-
Prepare, knot, stop, prime and apply one undercoat and two finishing coats of full
gloss enamel on -
-
F Hardwood cornice, 0 to 100mm girth M 481 4,000.00 1,924,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

CEILING FINISHES - CARRIED TO SUMMARY K 14,079,000.00


3.12

TB-ISOLATION WARD
TB ISOLATION WARD

Item FITTINGS AND FURNISHINGS Unit Qty Rate K t


(PROVISIONAL)

PROVISIONAL SUM

Include the following sums to be deducted in full


in the Final Account; any work ordered against
the sums to be valued in accordance with the
conditions of contract

A Allow the Provisional Sum of K6,000,000.00 (Four Million Kwacha) for fittings and
furnishings which cannot be entirely fore-seen, defined or detailed 6,000,000.00

JOINERY AND FITTINGS - CARRIED TO SUMMARY K 6,000,000.00


3.13

TB-ISOLATION WARD
TB ISOLATION WARD

Item SANITARY FITTINGS Unit Qty Rate K t

Sanitary fittings; Supply and fix sanitary ware approved by the Architect

A WC suite, comprising white grazed Vaal washdown "S" trap pan, 9 litre low level
Vaal cistern, complete with ball valve and flush pipe and plastic seat and cover.
Fix to concrete slab and block/concrete wall. No 11 150,000.00 1,650,000.00
-
B White glazed Vaal lavatory basin, 560 x 405mm, complete with integral overflow,
32mm diameter chromium plated anti-theft waste outlet, set basin on and including
pair of concealed hanger brackets fixed to block/ concrete wall No 12 100,000.00 1,200,000.00
-
C
Stainless steel sink size 1200 x 550 mm with single 'bowl single drainer to BS 1244
complete with integral overflows, 40 mm diameter chromium plated waste outlet
with plugs and chromium plated chain and fix in position to sink unit and block wall No 1 100,000.00 100,000.00
-
D 150 x 150mm white glazed vitreous china recessed toilet roll holder, set in and
including 50mm deep recess in brick/ concrete wall No 11 10,000.00 110,000.00
-
Sundries -
-
E 600 x 450mm glazed mirror with filed beveled edges No 12 20,000.00 240,000.00
-
F 600mm Long x 20mm Diameter chromium plated towel rail No 12 15,000.00 180,000.00

G 1000mm Long x 20mm Diameter chromium plated shower No 10 10,000.00 100,000.00

H Shower tray No 10 10,000.00 100,000.00


-
I Soap holder No 12 10,000.00 120,000.00
-
J Soap dispenser No 12 10,000.00 120,000.00

Taps and valves; Cobra Watertech -


-
Prices shall include for joining to paperwork -

K 20mm Diameter stop cock No 14 10,000.00 140,000.00


-
L 15mm, ditto No 16 6,000.00 96,000.00
-
M 15mm Diameter CP Bib tap. No 12 6,000.00 72,000.00
-
N 15mm kitchen swivel mixer wall mounted Cobra Stella Bright product code
3366/041/10SB No 1 100,000.00 100,000.00
-
O Shower mixer complete with rose and spout No 10 100,000.00 1,000,000.00
-
-
-
-
-
-
-

SANITARY FITTINGS - CARRIED TO COLLECTION K 5,328,000.00


3.14

TB-ISOLATION WARD
TB ISOLATION WARD

Item SANITARY FITTINGS Unit Qty K t


(PROVISIONAL)

Overflow pipes to cistern

A 20mm Medium quality galvanised mild steel pipe to BS 1387 with screwed joints in
running length and standard pipe clips fixed to concrete/blockwall, include for all
bends, tees, fittings etc as required. M 15 5,000.00 75,000.00
-
B Joint of 20mm galvanised pipe to cistern. No 12 6,000.00 72,000.00
-

Connector pipes -
-
C 12mm Diameter copper connector 300mm girth, bent as required, including joint to
union of fitting and galvanised mild steel pipe with gunmetal connector. No 12 6,000.00 72,000.00
-
12mm Diameter copper connector 450mm girth, bent as required, including joint to
D union of fitting and galvanised mild steel pipe with gunmetal connector. No 11 6,000.00 66,000.00

Testing -
-
E Allow to test the foregoing sanitary fittings and overflow pipes as sp[ecified to the
satisfaction of the Architect Item -
-
285,000.00
CARRIED TO COLLECTION

COLLECTION Page
No

3.14 5,328,000.00

3.15 285,000.00

SANITARY FITTINGS - CARRIED TO SUMMARY 5,613,000.00


3.15

TB-ISOLATION WARD
TB ISOLATION WARD

Item SOIL, WASTE AND VENT SERVICES Unit Qty Rate K t


(PROVISIONAL)

This section has been measured from fittings up to gully or first manhole

Waste Installation

Pipe work and fittings

Soil system shall be "Key Terrain 100" PVC to BS 4514

Waste system shall be "Key Terrain 200" UPVC

Generally joints are solvent welded

Fittingss to walls, slabs, etc shall be with standard pipe clips, plugged and screwed

Waste Installation

U.P.V.C. Pipes And Fittings

A 40 mm Diameter pipe fixed to block walls including clips M 66 2,000.00 132,000.00


-
B Ditto, under concrete slab M 42 2,000.00 84,000.00
-
C 50 mm Diameter pipe ditto M 65 2,000.00 130,000.00
-
D 50 mm Diameter pipe under 100 mm concrete slab M 54 2,000.00 108,000.00
-
Extra Over The Foregoing Pipes For The Following Fittings -
-
E 40 mm Diameter bend No 18 6,000.00 108,000.00
-
F 40 mm Diameter inspection bend No 18 6,000.00 108,000.00
-
G Splay cut end of 40 mm diameter pipe No 18 6,000.00 108,000.00
-
H 50 mm Diameter bend No 12 6,000.00 72,000.00
-
I 50 mm Diameter inspection bend No 12 6,000.00 72,000.00
-
J Splay cut end of 50 mm diameter pipe No 12 6,000.00 72,000.00
-
Sanitary Installation -
-
U.P.V.C. Pipes And Fittings -
-
K 110 mm Diameter soil and vent pipe and including holder bats M 78 10,000.00 780,000.00
-

CARRIED TO COLLECTION K 1,774,000.00


3.16

TB-ISOLATION WARD
TB ISOLATION WARD

Item SOIL, WASTE AND VENT SERVICES Unit Qty Rate K t


(PROVISIONAL)

Sanitary Installation

U.P.V.C. Pipes And Fittings

A 110 mm Diameter pipe M 35 3,000.00 105,000.00


-
Extra Over The Foregoing Pipes For The Following Fittings -
-
B 110 mm Diameter straight W.C. connector 305 mm long including joint to outlet of
pan No 12 6,000.00 72,000.00
-
C 110 mm Diameter bend No 12 6,000.00 72,000.00
-
D 110 mm Diameter tee junction with inspection eye No 13 6,000.00 78,000.00
-
E 110 mm Diameter vent cowl and set on top of 100 mm diameter pipe No 10 6,000.00 60,000.00
-
F Joint of 110 mm diameter u.p.v.c. soil and vent pipe to u.p.v.c. drain pipe including
necessary adaptors No 10 6,000.00 60,000.00
-
Upvc Trapped Gulley -
-
G
110 mm Diameter upvc trapped gulley with 150 x 150mm grating and joint into
upvc drain pipe including all necessary adaptors and blockwork surround plastered
internally and externally and concrete bedding and include for excavation, back
filling and disposal of surplus excavated material where directed on site No 14 6,000.00 84,000.00
-
Sundries -
-
H 40 mm Diameter PVC bottle trap and joint to fitting and UPVC pipe including any
necessary adaptors No 12 6,000.00 72,000.00
-
I 50 mm Diameter PVC "S:" trap and joint to fitting, waste and UPVC pipe No 2 6,000.00 12,000.00
-
J 50 mm Diameter galvanized P-trap complete with chromium plated grated waste
outlet set in floor slab and connected to UPVC pipe No 14 6,000.00 84,000.00
-
-
-
-
-
-
-
-

SOIL, WASTE AND VENT SERVICES - CARRIED TO COLLECTION K 699,000.00


3.17

TB-ISOLATION WARD
TB ISOLATION WARD

Item SOIL, WASTE AND VENT SERVICES Unit Qty Rate K t


(PROVISIONAL)

Testing

A Include for testing of the whole of the Waste and Sanitary Installation to the
satisfaction of the Architect/Supervising Officer

Builder's Work In Connection

B Make hole through block wall for small pipe and make good No 14 3,000.00 42,000.00
-
C Ditto for large pipe and make good No 6 3,000.00 18,000.00
-
D Form sleeve in concrete slab for small diameter pipe and make (include for
covering the sleeve/opening) M 6 3,000.00 18,000.00
-
E Trench excavation for large diameter pipe M 69 3,000.00 207,000.00
-
-

285,000.00
CARRIED TO COLLECTION

COLLECTION Page
No

3.16 1,774,000.00

3.17 699,000.00

3.18 285,000.00

SOIL, WASTE AND VENT SERVICES - CARRIED TO SUMMARY K 2,758,000.00


3.18

TB-ISOLATION WARD
TB ISOLATION WARD

Item DOMESTIC COLD WATER SERVICES Unit Qty Rate K t


(ALL PROVISIONAL)

Reticulation to fittings

The following in reticulation from outside of building to:-

4 No WC (s)

3 No WHB (s)

1No Urinal

1 No Sink

All pipes shall be medium quality galvanised mild steel to BS with joints as
described, fixed with and including the relevant pipe supports

Generally all pipes are concealed

Rates for pipework 20mm diameter and under shall include for all bends, tees,
fittings, etc as required

Rates for all bends, tees, valves, fittings, etc shall include for the corresponding

screwed/ flanged joints to adjoining pipework with screwed joints to BS 21 Part 1

COLD WATER SERVICES

Galvanized Steel Pipes And Fittings

A 40mm diameter incoming pipe laid in trench M 16 3,000.00 48,000.00


-
B Ditto, bends No 4 6,000.00 24,000.00
-
C Ditto, tee No 4 6,000.00 24,000.00
-
D 40 -25mm reducer No 8 6,000.00 48,000.00
-
E 25mm diameter pipe in trench M 85 3,000.00 255,000.00
-
F Ditto, 25-20mm reducer No 16 6,000.00 96,000.00
-
G Ditto, bend No 26 6,000.00 156,000.00
-
H Ditto, tees No 15 6,000.00 90,000.00
-
I 20mm diameter vertically fixed to block wall M 17 3,000.00 51,000.00
-
J 20mm diameter pipe horizontally fixed to wall M 41 3,000.00 123,000.00
-
K 20mm diameter pipe fixed in roof space/ceiling space M 25 3,000.00 75,000.00
-
L 20mm diameter bend No 16 6,000.00 96,000.00
-
M Ditto, tee No 9 6,000.00 54,000.00
-
N 20-15mm reducer No 20 6,000.00 120,000.00
-
O 15mm diameter pipe fixed to the wall M 21 3,000.00 63,000.00
-
P Ditto , bend No 16 6,000.00 96,000.00
-
-
-
-
-
-
-
-

CARRIED TO COLLECTION K 1,419,000.00


3.19

TB-ISOLATION WARD
TB ISOLATION WARD

Item DOMESTIC COLD WATER SERVICES Unit Qty Rate K t


(ALL PROVISIONAL)

Sundries

A 40mm Diameter brass screw down gate valve to B.S. 1010 with capstan head and
joint pipe No 2 6,000.00 12,000.00

B Ditto, 25mm diameter No 9 6,000.00 54,000.00

Testing

C Include testing of the whole of cold and hot water installations in sections during
construction and on completion, by approved means, including re - testing until
perfect to the satisfaction of the Architect/Supervising Officer Item

Builder's Work In Connection

D Make hole through blockwall and include for making good No 36 3,000.00 108,000.00
-
E Excavate trench, 300mm wide for large pipe M 61 3,000.00 183,000.00
-
357,000.00

COLLECTION Page
No

3.19 1,419,000.00

3.20 357,000.00

CARRIED TO COLLECTION
3.20 1,776,000.00

TB-ISOLATION WARD
TB ISOLATION WARD

Item DOMESTIC HOT WATER SERVICES Unit Qty Rate K t


(ALL PROVISIONAL)

Reticulation to fittings

The following in reticulation from hot


water heaters to:-
1No. Kitchen Sinks
11No. Lavatory Basins
2No. Shower
With screwed joints to BS 21 Part 1

All pipes shall be medium quality galvanised mild steel to BS with joints as
described, fixed with and including the relevant pipe supports

Generally all pipes are concealed

Rates for pipework 20mm diameter and under shall include for all bends, tees,
fittings, etc as required

Rates for all bends, tees, valves, fittings, etc shall include for the corresponding

screwed/ flanged joints to adjoining pipework with screwed joints to BS 21 Part 1

HOT WATER SERVICES

Galvanized Steel Pipes And Fittings

A 20mm diameter fixed in ceiling space M 66 3,000.00 198,000.00

B Ditto, in brick wall M 6 3,000.00 18,000.00

C Ditto, bends No 25 6,000.00 150,000.00

D Ditto, tee No 15 6,000.00 90,000.00

SUPPLY AND FIX

Electric water heater

E Electric water heater; ceiling mounted; Kwikot or equal approved


200 litres capacity; complete with inlet/outlet and overflow connections No 1 1,000,000.00 1,000,000.00
-
F extra; galvanised steel drip tray 1000 x 800 x 200mmhigh with 25mm -
overflow pipework No 1 500,000.00 500,000.00
-
Insulation

G 20mm Thick preformed fibreglass lagging to 20mm diameter pipe, finished


with reinforced aluminium foil and banded at 450mm centres with
identification to BS 1710, including lagging to all bends, tees, fittings etc
450mm centres with identification
to BS 1710, including lagging to all bends, M 70 3,000.00 210,000.00

Sundries

H 15mm Diameter , stop cok No 15 5,000.00 75,000.00

Testing

I Include testing of the whole of cold and hot water installations in sections during
construction and on completion, by approved means, including re - testing until
perfect to the satisfaction of the Architect/Supervising Officer -
-
Builder's Work In Connection -
-
J Make hole through blockwall and include for making good No 14 3,000.00 42,000.00

DOMESTIC HOT WATER SERVICES TO COLLECTION K 2,283,000.00


3.21

TB-ISOLATION WARD
TB ISOLATION WARD

Item HOT AND COLD WATER SERVICES COLLECTION PAGE Unit Qty Rate K t

PAGE

COLD WATER SERVICES 3.20 1,776,000.00

HOT WATER SERVICES 3.21 2,283,000.00

COLD AND HOT WATER SERVICES TO SUMMARY K 4,059,000.00


3.22

TB-ISOLATION WARD
TB ISOLATION WARD

FIRE FIGHTING INSTALLATION

Pipe work

All pipe works and fittings for fire fighting are measured under cold water
services

Equipment

Equipment to BS 5306 Part 1 and BS 5274

A Fire hose reels; Chubb; 19mm diameter x 35m long non-kinkable hose
6mm fixing bolts swiveling pulley with slide and housing short lenghth
of tube and 25mm non return valve fixing to backgrounds requiring
pluggings No 4 600,000.00 2,400,000.00

B Fire extinguisher; Angus; hand operated 9kg dry chemical powder, fixing
brackets to background requiring plugging No 4 500,000.00 2,000,000.00
-
C 4.5kg carbon dioxide; fixing brackets to backgrounds requiring
plugging No 4 200,000.00 800,000.00

SUNDRIES

D Allow for testing the foregoing fire fighting services Item

E Allow for testing the foregoing fire fighting services, including pipe work
to twice the working pressure Item

5,200,000.00
FIRE FIGHTING TO SUMMARY K
3.23

TB-ISOLATION WARD
TB ISOLATION WARD

Item ELECTRICAL INSTALLATION Unit Qty Rate K t

This section is to be read in conjunction with Drawings No.:

MAIN SUPPLY CABLES (all provisional)

A Supply and install 16mm2 CU/PVC/PVC/SWA/PVC 4 Core Cable m 64 2,500.00 160,000.00

B Allow for connections to the cables Item 1 100,000.00 100,000.00

DISTRIBUTION BOARD - DB/ISOL

C Supply and install distribution board as manufactured by C & S Electric WinTrip or


equal approved complete with the following accessories:

1No. 60A SP & N ELCB


4No. 10A MCCB's
1No. 20A MCCB's
3No. 30A MCCB's
3No. Blanks
Busbars
Phase separate barriers
Maskin Plates
Labels
Circuit Charts
Recessed in Brickwork No 1 500,000.00 500,000.00

EARTHING

D Allow to provide an earthing system in accordance with drawings, regulations and


best trade practices all the completed electrical installation. Item 1 500,000.00 500,000.00

CIRCUITS (LIGHT AND POWER)

Not in accordance with SMM

All wiring shall be run concealed with outlets,


etc. flush mounted

Unless otherwise stated, outlets are as follows

Wall light outlets - in brick/concrete walls

Light switches - in brick/concrete walls

Socket outlets - in brick/concrete walls

CARRIED TO COLLECTION K 1,260,000.00


3.24

TB-ISOLATION WARD
TB ISOLATION WARD

Item ELECTRICAL INSTALLATION Unit Qty Rate K t

Circuits (Light and Power) continued

Unless otherwise stated all round pin sockets outlets


complete with plastic matching round pin fused top
plug as LEGRAND CAT NO 03723 or equal and
approved
Unless otherwise stated all equipment switches to be
with Red Led Indicator as LEGRAND SYNERGY WHITE
CAT NO 7300 12 or equal and approved

Unless otherwise stated switches to be LEGRAND


or equal and approved

Switches shall be ganged as shown on the drawing

Circuits shall be phase balanced as required fixed to


brick/concrete wall
Items have been identified/measured as follows:-
Sockets, light outlets and switches within each circuit

In pricing each item, it is recognised that bidders will


rely on their own measurements as taken from the
bidding drawings and the specification note as
contained in this document

Prices for the following shall include for supply,


installation and connection of PVC conduit, junction
boxes, accessories, cabling, flush/surface mounted
outlets, switches, sockets and all builders work to
complete the installation

LIGHTING CIRCUITS

DISTRIBUTION BOARD DB/ISOL - LIGHTING

Circuit CIR-DB/ISOL - 1 (1.5mm2)

A 6 Ceiling lighting point controlled by 2 gang 2 way switch (Corridor) No 3 6,000.00 18,000.00

Circuit CIR-DB/ISOL - 2 (1.5mm2)

B 1 Ceiling lighting point controlled by 1 gang 1 way switch (Ward 1, Ward 2, Ward 3, No 11 6,000.00 66,000.00
Ward 4, )

Circuit CIR-DB/ISOL - 2 (1.5mm2)

C 1 Ceiling lighting point controlled by 1 gang 1 way switch (Ward 5, Ward 6, Ward 7, No 11 6,000.00 66,000.00
Ward 8, )

CARRIED TO COLLECTION K 150,000.00


3.25

TB-ISOLATION WARD
TB ISOLATION WARD

Item ELECTRICAL INSTALLATION Unit Qty Rate K t

Circuit CIR-DB/ISOL - 3 (1.5mm2)

A 1 Ceiling lighting points controlled by 1 gang 1 way switch (Examination room, No 6 6,000.00 36,000.00
Waiting Area, Nursing station)

Circuit CIR-DB/ISOL - 4 (1.5mm2)

B 9 Wall mounted lighting points controlled by 1 gang 1 way switch (Security Lights) No 4 6,000.00 24,000.00

POWER CIRCUITS

DISTRIBUTION BOARD DB/ISOL - POWER

Circuit CIR-DB/ISOL - 5 (2.5mm2)

C Ring Circuit to13A Twin socket switch (Ward 1, Ward 2, Ward 3, Ward 4) No 4 6,000.00 24,000.00

Circuit CIR-DB/ISOL - 5 (2.5mm2)

D Ring Circuit to13A Twin socket switch (Ward 5, Ward 6) No 2 6,000.00 12,000.00

Circuit CIR-DB/ISOL - 5 (2.5mm2)

E Ring Circuit to13A Twin socket switch (Ward 7, Ward 8) No 2 6,000.00 12,000.00

Circuit CIR-DB/ISOL - 5 (2.5mm2)

F Ring Circuit to13A Twin socket switch (Examination room, waiting area, nursing No 3 6,000.00 18,000.00
station)

Circuit CIR-DB/ISOL - 8 (4.0mm2)

G Radial Circuit to a Fire Alarm Unit (Waiting Area) No 1 6,000.00 6,000.00

Circuit CIR-DB/ISOL - 9 (4.0mm2)

H Radial Circuit to a Water Heater (Corridor) No 1 6,000.00 6,000.00

CARRIED TO COLLECTION K 138,000.00


3.26

TB-ISOLATION WARD
TB ISOLATION WARD

Item ELECTRICAL INSTALLATION Unit Qty Rate K t

LIGHT FITTINGS

All light fittings are complete with appropriate lamps

A 4ft single LED Fluorescent fitting, complete with tube No 27 6,000.00 162,000.00

B 100w x 240V black bulkhead lighting, die - cast aluminium body Body with No 8 6,000.00 48,000.00
polycarbonate lens and an E27 incandescent lamp

SWITCHES

C Supply and Install 1 gang 1 Way Switch No 26 6,000.00 156,000.00

D Supply and Install 1 gang 2 Way Switch No 7 6,000.00 42,000.00

E Photocell daylight switch No 3 6,000.00 18,000.00

POWER OUTLETS

F Supply and Install 13A Twin rectangular pin switched socket Outlet No 23 6,000.00 138,000.00

G Water heater Spur outlet With Neon Indicator No 1 6,000.00 6,000.00

H Switch box with Neon Indicator controlling ceiling fan No 5 6,000.00 30,000.00

COMMUNICATION ACCESSORIES

I Telephone Line Jack outlet as MK422 White Range No 18 10,000.00 180,000.00

EQUIPMENT

J 300mm diameter whirl Bird ventilator No 12 6,000.00 72,000.00

CARRIED TO COLLECTION K 852,000.00


3.27

TB-ISOLATION WARD
TB ISOLATION WARD

Item ELECTRICAL INSTALLATION Unit Qty Rate K t

ESCOM CONNECTION (ALL PROVISIONAL)

A Allow the provisional sum of Two Million for ESCOM connections to the
Isolation Ward (MK 2,000,000.00) Item 2,000,000.00

B Allow for testing and commisioning electricity in the building Item

TO ELECTRICAL INSTALLATION TO COLLECTION 2,000,000.00

TB-ISOLATION WARD
TB ISOLATION WARD

Item ELECTRICAL INSTALLATION Unit Qty Rate K t


3.28

FIRE ALARM SYSTEM

Unless otherwise stated, outlets are as follows :-

Bell outlets : in brick/concrete


Break glass outlets : in brick/concrete
Smoke detector outlets : in brick/concrete

Unless otherwise stated, all wiring shall be pair fire resistant


cables of the sizes specified.

All skirt trunking shall be legrand or as approved

Circuits shall be phase balanced as required

In pricing each item,it is recognised that tenderers will rely on


their own measurements as taken from the tender drawings
and the specification notes as contained in this document

The following to be wired with cable on screwed steel junction


boxes,draw boxes,accessories,flush mounted outlets and all
work necessary to complete installation

A Ceiling points No 14 6,000.00 84,000.00

B Wall points No 19 6,000.00 114,000.00

EQUIPMENT

C Five zone analogue addressable fire alarm panel as Gent or equal approved No 2 6,000.00 12,000.00

D Repeat Panel as Gent or equal approved No 2 6,000.00 12,000.00

E "Gent 7430" break glass or equal approved No 12 6,000.00 72,000.00

F "Gent 500/500" alarm bell or equal approved No 12 6,000.00 72,000.00

G "Gent 1195/1195M" smoke detector or equal approved No 13 6,000.00 78,000.00

CARRIED TO COLLECTION K 444,000.00


3.29

TB-ISOLATION WARD
TB ISOLATION WARD

SUMMARY K T

Page
No.

3.24 1,260,000.00

3.25 150,000.00

3.26 138,000.00

3.27 444,000.00

3.28 2,000,000.00

3.29 444,000.00

ELECTRICAL INSTALLATION CARRIED TO SUMMARY K 4,436,000.00


3.30

TB-ISOLATION WARD
TB ISOLATION WARD

SUMMARY K T

TB ISOLATION WARD SUMMARY


Page
No.

A SUBSTRUCTURE 3.3 34,273,400.00

B ROOF 3.5 30,551,500.00

C EXTERNAL AND INTERNAL WALLS 3.6 37,337,400.00

D WINDOWS AND DOORS 3.8 12,216,500.00

E IRONMONGERY 3.9 1,782,000.00

F WALL FINISHES 3.10 24,484,000.00

G FLOOR FINISHES 3.11 7,314,500.00

H CEILING FINISHES 3.12 14,079,000.00

I FITTINGS AND FURNISHES 3.13 6,000,000.00

J SANITARY FITTINGS 3.15 5,613,000.00

K SOIL, WASTE AND VENT SERVICES 3.18 2,758,000.00

L COLD AND HOT WATER WATER SERVICES 3.22 4,059,000.00

M FIRE FIGHTING INSTALLATIONS 3.23 5,200,000.00

N ELECTRICAL WORKS 3.30 4,436,000.00

SUMMARY PAGE TO MAIN SUMMARY K 190,104,300.00


3.31

TB-ISOLATION WARD
EXTERNAL SERVICES (PALISADE WALL)

ITEM DESCRIPTION QTY UNIT RATE K t

SUBSTRUCTURE

Refer SMM paragraph F19 (a). It has been


assumed that strip footings, bases, beds and
the like within the ground will be poured
against natural ground. If formwork is
required to such surfaces, the Contractor
must include for same in his excavation/
concrete rates

The quantities in this section have been


measured using the following key
dimensions:-

(a) Depth of excavation for trenches


is 1500mm below site strip/reduced level
level

(b) Thickness of concrete foundations


is 200mm

(c) Height of foundation brickwork


from top of concrete foundation
to underside of ground floor slab
is 1300mm

EXCAVATION

Excavating / filling (PROVISIONAL)

Excavate trenches from reduced level for strip footings


from reduced level

A not exceeding 1.5m, deep 193 m3 3,000.00 579,000.00

B Ditto, Attached Piers 84 m3 3,000.00 252,000.00

C Selected earth filling, deposited, spread and compacted around


fooundation trenches 125 m3 3,000.00 375,000.00

Rock excavation (PROVISIONAL)

Extra over all types of excavation for


D excavating in rock 28 m3 15,000.00 420,000.00

4.57
To Collection 1,626,000.00

EXTERNAL SERVICES (PALISADE WALL)

ITEM DESCRIPTION QTY UNIT K t

Disposal (PROVISIONAL)

A Surplus excavated material from excavations, transported


an average distance of 100 linear meteres from excavations
desposit, spread, and level where directed on site 152 m3 3,000.00 456,000.00

DAMP-PROOF COURSE

125 micron, (500 gauge) polythene sheeting

Horizontal; lapped 150mm at joints; laid on


sand blinding

B Less than 300mm wide 200 m1 600.00 120,000.00


-
ANTI-TERMITE TREATMENT -
-
Ant-repellant; surface treatment -
-
-
C Bottom of trenches 720 m2 600.00 432,000.00
-
-
SUNDRIES -
-
Disposal of water -

Keeping excavations free from

D general water item

PLANKING AND STRUTTING

Sides of all kinds of excavations irrespective


of depth

E generally item

4.58
To Collection 1,008,000.00

EXTERNAL SERVICES (PALISADE WALL)

ITEM DESCRIPTION QTY UNIT K t

CONCRETE WORK

IN-SITU CONCRETE; PLAIN

Normal; designed mix 15N/mm2 40mm


aggregate

Foundations in trenches

A Strip footings 33 m3 100,000.00 3,300,000.00

B Ditto, Attached Piers 15 m3 100,000.00 1,500,000.00

WALLING (below ground)

BLOCKWORK

Load bearing Precast sand and cement Blocks bedded and


jointed in cement mortar (1:3)

190mm thick; block wall in Stretcher bond;


reinforced with one layer of 'brickforce'
reinforcement every third course

C walls 254 m2 20,000.00 5,080,000.00

D Attached piers; 390 x 560mm 102 m1 5,000.00 510,000.00

IN-SITU FINISHES

E Point in cement and sand (1:3) recessed joints of brickwork; 85 m2 3,500.00 297,500.00
external

F Ditto in narrow widths 5 m2 3,500.00 17,500.00

PAINTING AND DECORATING

Prepare and Apply two coats of Styrene Acrylic Emulsion Clear sealer on

G Rendered walls 85 m2 4,500.00 382,500.00

4.59
To Collection 11,087,500.00

EXTERNAL SERVICES (PALISADE WALL)

ITEM DESCRIPTION QTY UNIT K t

WALLING (above ground)

BLOCKWORK

Load bearing Precast sand and cement Blocks bedded and


jointed in cement mortar (1:3)

190mm thick; block wall in Stretcher bond;


reinforced with one layer of 'brickforce'
reinforcement every third course

A walls 320 m2 20,000.00 6,400,000.00

B Attaced piers; 390 x 560mm 95 m1 5,000.00 475,000.00

IN-SITU FINISHES

C Point in cement and sand (1:3) recessed joints of brickwork; 640 m2 3,500.00 2,240,000.00
external -
-
D Ditto in narrow widths 16 m2 3,500.00 56,000.00
-
PAINTING AND DECORATING -
-
Prepare and Apply two coats of Styrene Acrylic Emulsion Clear sealer on -
-
G Pointed walls 640 m2 4,500.00 2,880,000.00
-
H Ditto in narrow widths 32 m2 4,500.00 144,000.00
-
CONCRETE WORK -
-
PRECAST CONCRETE; PLAIN -
-
Normal; designed mix 21N/mm2; 20mm -
aggregate; vibrated -
-
75 mm Thick precast vibrated concrete Coping (Class 21N/
mm2/10mm) slabs,
having smooth finish, bedded, jointed and pointed in

K 240 x 75mm Coping 200 m1 3,600.00 720,000.00

L 440 x 630mm Coping 67 No 4,158.00 278,586.00


-
-
METALWORK -
-
PALISADE PANELS -
-
Palisade wall consisting of 1200mm high Palisade Metal Fence, of -
38 x 25 x 1mm rectangular tubing, fitted on blockwork, delivered and -
installed -
-
4530 x 755mm high palisade panel 34 No 10,000.00 340,000.00
-
PAINTING AND DECORATING -
-
TWO COATS METAL GUARD BLACK PAINT -
-
Dulux/Plascon Paints Reference 164-0770; or -

4.60
equal and approved -
-
Palisade Panels -
-
over 300mm girth 275 m2 4,500.00 1,237,500.00
-
-
-
-
-

To Collection 14,771,086.00

0 DESCRIPTION QTY UNIT K t

GATES
A Pair of mild steel sliding gates, 5000 x 2100mm high,
fabricated having 50mm RHS pipe frame and vertical -
braces, with 25mm RHS intermediates, all welded
together.Hang on and including a pair of pin hinges,
welded to gate with 50 x 50mm hasp and staple to
meeting stiles and 300mm drop bolt with keep set in and
including 150 x 150 x 150mm deep plain in-situ concrete -
(Class 14N/mm2/40mm) foundation 1 No 1,500,000.00 1,500,000.00
-
B 1175 x 2000mm high pedestrian gate 1 No 500,000.00 500,000.00
-
Metal work -
-
UBM 1234. 150. 301 254mm padlock bolts 4 No 10,000.00 40,000.00
-
PAINTING AND DECORATING -
-
Prepare, knot, stop, prime and apply one -
undercoat and two finishing coats of full -
gloss enamel on -
-
Metal General surface 42 m2 4,500.00 189,000.00
-
PAINTING AND DECORATING

Prepare , prime and apply one undercoat (red oxide) and two finishing coats of
Dulux gloss enamel or equally approved

C RHS steel pipes (measured overall) 8 m2 4,500.00 36,000.00


-
D Mild steel gate 26 m2 4,500.00 117,000.00
-
-

4.61
To Collection 2,382,000.00

EXTERNAL SERVICES (PALISADE WALL)


ITEM DESCRIPTION QTY UNIT K t

COLLECTION Page

4.1 1,626,000.00

4.2 1,008,000.00

4.3 11,087,500.00

4.4 14,771,086.00

4.5 2,382,000.00

4.62
EXTERNAL SERVICES (PALISADE WALL)
TO SUMMARY 30,874,586.00

GUARD HOUSE
ITEM SUBSTRUCTURE (ALL PROVISIONAL) QTY UNIT RATE K T

BILL NO. 3

Substructure

Refer SMM paragraph F19(a). It has been


assumed that strip footings, bases, beds
and the like within the ground will be
poured against natural ground. If formwork
is required to such surfaces the Contractor
must include for same in his excavation /concrete rates

The quantities in this section have been


measured using the following key
dimensions :-
(a) Depth of excavation for trenches - 1000
mm below site strip / reduced level
(b) Thickness of concrete foundations - 230 mm
Height of foundation brickwork from top of
concrete foundation to underside of ground
floor slab - 770 mm

PLANT

A Bring to site all plant and equipmnet required for this


section Item

B Maintening on site all plant and equipment required for


this section ( Time related) Item

C Removing from site all plant and equipment required


for this work Item

EXCAVATION

Excavation / filling

D Excavate trench from reduced level for


strip footings, 0 to 1500mm deep 8 M3 3,000.00 24,000.00

E Excavate trench from reduced level for slab


thicknessing, 0 to 1500 mm deep 1 M3 3,000.00

F Selected earth filling, deposited, spread and


compacted in 150 mm layers around foundations 5
M3 3,000.00 15,000.00

Rock excavation

G Extra over all type of excavation for excavating


in rock 1
M3 15,000.00 15,000.00

4.63
H Surplus excavation materials from excavations,
transported a distance average 100 linear metres
from excavations and deposit in spoil heaps on site 4 M3 3,000.00 12,000.00

To Collection 66,000.00
GUARD HOUSE

ITEM SUBSTRUCTURE (ALL PROVISIONAL) QTY UNIT K T

Hard-core filling to pass a 50mm ring


all ways -
A 150mm Thick (Consolidated) filling well -
compacted and rolled 9 M2 600.00 5,400.00
-
Sand blinding -
B 50mm Bed of sand on hard-core rolled to -
receive damp proof membrane 9
M2 600.00 5,400.00
-
Damp proof membrane -
-
C 125 microns(500 gauge) Polythene damp proof -
membrane with welted joints, lapped 150mm at -
joints and laid on blinded hardcore 10 M2 600.00 6,000.00
-
Ant Treatment -
D Saturate surface of hard-core and top of -
brickwork with approved ant repellent
10 M2 800.00 8,000.00
-
Sundries -
E Allow for keeping excavations free from -
water -
-
F Allow for plunking and strutting to sides of -
excavations -
-
CONCRETE WORK -
Plain in-situ concrete ( Class 15N/mm2/40mm ) -
-
G Strip footings 2 M3 100,000.00 200,000.00
-
Reinforced in-situ concrete ( Class 25N/mm2/40mm) -
-
H 100mm Thick horizontal bed , laid in bays -
generally 30 square metres including -
formwork to construction joints 10 M2 20,000.00 200,000.00
-
Reinforcement -
-
I Hard drawn mild steel fabric reinforcement (Ref A142), -
weighing 2.22 Kg/m2 in beds 10 M2 4,500.00 45,000.00
-

4.64
Wrot form work -
-
J Edge of slab, 100 to 200 mm wide 13 M1 3,500.00 45,500.00
-
-
-
-
-

To Collection 515,300.00
GUARD HOUSE

ITEM SUBSTRUCTURE (ALL PROVISIONAL) QTY UNIT K T

BLOCK WORK

Hollow precast cement and sand blocks in cement


mortar (1:4) filled with concrete (grade 15/40) -

A 200mm thick walls 13 M2 20,000.00 260,000.00


-
Plasterwork -
-
15mm Rendering (1:4) cement and sand, -
finished with a wood float -
-
B Block / concrete walls 9 M2 3,500.00 31,500.00
-
Painting and Decorations -
-
Prepare and apply one coat Dulux new plaster Primer -
code (192-0802) and two coats of Dulux wallguard -
exterior PVA black code (164-0770) or equally approved on -
-
C Rendered walls 9 M2 4,500.00 40,500.00
-
-
-
-
-
-
-
-
-
-
-

4.65
To Collection 332,000.00
GUARD HOUSE

ITEM SUBSTRUCTURE (ALL PROVISIONAL) QTY UNIT K T

COLLECTION

4.8

4.9 66,000.00

4.10
515,300.00

332,000.00

4.66
To Summary 913,300.00
GUARD HOUSE

ITEM ROOF QTY UNIT RATE K T

0.00
Plant -
-
A Bring to site all plant and equipment equal required -
for this section of work Item
-
B Maintening on site all palnt and equipment required -
for this section of work (Time related) Item
-
C Removing from site all plant and equipment required -
for this work Item
-
CONCRETE WORK

Reinforced Vibrated Concrete Grade 25N/mm2/20mm aggregate

D 150mm Thick suspended slab m2 23 30,000.00 690,000.00


-
E Gutter Beam m2 4 30,000.00 120,000.00
-
-
FORMWORK -
-
Sawn formwork -
-
F Soffit of suspended slab m2 22 18,000.00 396,000.00

REINFORCEMENT (PROVISIONAL)

G 12mm diameter; ditto kg 426 2,500.00 1,065,000.00


-
BLOCK WORK (PROVISIONAL) -
-
Precast cement and sand blocks in cement -
mortar (1:4) filled with concrete (grade 15/40) -

4.67
-
H 150mm thick walls 18 M² 20,000.00 360,000.00
-
-
-
-
-

-
-
-
-
-

-
To Collection K 2,631,000.00
GUARD HOUSE

ITEM ROOF QTY UNIT RATE K T


ROOFING

RAIN WATER INSTALLATION -


-
2.0mm Mild Steel Plates required shape, -
fixed as required and shall include -
all labours, nails, clips, wedges, welded and -
soldered seams and laps and joints in the running -
length -
-
-
600mm Diameter downpipe, fixed with and -
A including 4 x 25mm girth mild steel straps -
at 1200mm centres, twice bent and twice -
countersunk, drilled and screwed to -
brickwork / concrete, include for plugging 3 M1 3,500.00 10,500.00
-
B Extra over for bend 2 No 3,500.00 7,000.00
-
C Ditto, for shoe with 250mm projection 1 No 3,500.00 3,500.00
-
-
PAINTING AND DECORATING -
-
Prepare and apply one undercoat and two coats of super gloss enamel paint on -
-
D fibre cement general surfaces; 200 - 300mm girth 27 M1 3,500.00 94,500.00
-
-
-
-
-
-

4.68
-
-
-
-
-
-
-
-

To Collection K 115,500.00
GUARD HOUSE

Item Roof QTY Unit K T

Collection

4.12 115,500.00

4.13

4.69
To Summary 115,500.00
Roof

4.70
ITEM EXTERNAL AND INTERNAL WALLS QTY UNIT K T

Plant

A Bring to site all plant and equipment equal required


for this section of work Item -

B Maintening on site all palnt and equipment


required for this section of work (Time related) Item -

C Removing from site all plant and equipment


required for this work Item -

CONCRETE WORK

IN-SITU CONCRETE; REINFORCED


-
In-situ concrete ( Class 25N/20mm; vibrated ) -
-
D Beams 1 M3 200,000.00 200,000.00
-
REINFORCEMENT (Provisional) -
-
Bars; mild steel; hot rolled -
-
E 8mm diameter deformed high yield mild steel rod reinforcement 43 Kg 2,500.00 107,500.00
-
Bars; high yield steel; cold worked -
-
F 12mm diameter deformed high yield mild steel bars reinforcement 89 Kg 2,500.00 222,500.00
-

FORMWORK -
-
To soffit; wrot horizontal -
-
G Sides and soffit of beam 6 M2 18,000.00 108,000.00
-
BLOCK WORK (PROVISIONAL) -
-
Precast cement and sand blocks in cement -
mortar (1:4) filled with concrete (grade 15/40) -
-
H 200mm thick walls 56 M² 20,000.00 1,120,000.00
-
-

4.71
-
TO COLLECTION 1,758,000.00
GUARD HOUSE

ITEM EXTERNAL AND INTERNAL WALLS QTY UNIT K T

A Half block thick eaves filling, 225mm high


splay cut and fitted and wedged to underside
of IBR roofing sheets 16 M1 5,000.00 80,000.00

Damp proof course (Provisional)

B 3 Ply "Malthoid" damp proof course,190mm wide, laid


under blockwork 16 M1 600.00 9,600.00

COLLECTION

4.15 1,758,000.00

4.16

4.72
To Summary 1,758,000.00
GUARD HOUSE

ITEM DOORS AND WINDOWS QTY UNIT K T

PLANT

A Bring to site all plant and equipment equal required


for this section of work Item -

B Maintening on site all palnt and equipment


required for this section of work (Time related) Item -

C Removing from site all plant and equipment


required for this work Item -

CONCRETE

Precast vibrated concrete (class


21N/mm2 x 10mm) bedded, jointed and
pointed in cement mortar

D 275 x 65mm sill, splay rebated once


grooved and top edges chamfered, finished
fair on all exposed surfaces and built into
blockwork 4 M1 3,510.00 14,040.00
-
Pelmets -
-
E Double metal curtain rail 2 M1 6,000.00 12,000.00
-
Doors -
-
Hardwood pannelled doors having 2No. 200 x -
250mm panels, 2No. 200 x 400mm panels, -
2No. 200 x 600mm panels and 20 x 25mm -
beads to panels -
-
F 900 x 2100mm hardwood panelled door 1 No 100,000.00 100,000.00
-
-
-
-
-
-
-

4.73
To Collection 126,040.00
GUARD HOUSE

ITEM DOORS AND WINDOWS QTY UNIT K T


-
Window frames -
-
Standard mild steel horizontal bar windows with lugs -
welded, all opening lights complete with ironmongery -
including projecting hinges and whole to be treated at -
works with one coat red oxide primer, built into blockwork -
-
A 1000 x 890 mm high overall size; 3 No 35,000.00 105,000.00
-
-

4.74
To Collection 105,000.00
GUARD HOUSE

ITEM DOORS AND WINDOWS QTY UNIT K T

Door frames

Rates shall include for lugs welded to back,


building into brickwork and filling cavity
with cement and sand (1:3)

A Standard metal door frame, size 900 x 2100mm overall, -


suitable for 140mm blockwall, complete with one pair of -
butts frabricated from 1.2mm thick pressed steel. 1 No 35,000.00 35,000.00
-
GLAZING -
-
Clear sheet glass -
-
B 6 mm Glass, fixed to metal with mastic -
putty,in panes, 0.10 to 0.50 m2 3 M2 18,000.00 54,000.00

PAINTING AND DECORATING -


-
Prepare and apply one coat Dulux clear varnish or equally -
approved -
-
C Hardwood panelled doors 6 M2 4,500.00 27,000.00
-
Prepare , prime and apply one undercoat -
and two finishing coats of Dulux gloss -
enamel or equally approved -
-
-
D Metal window frames 4 M2 4,500.00 18,000.00
-
E Metal door frames 200-200mm girth 7 M1 3,500.00 24,500.00

4.75
-

To Collection 158,500.00
GUARD HOUSE

ITEM DOORS AND WINDOWS QTY UNIT K T

COLLECTION

4.17 126,040.00

4.18 105,000.00

4.19 158,500.00

4.76
To Summary 389,540.00
GUARD HOUSE

ITEM IRONMONGERY QTY UNIT K T

Unless otherwise stated, fixing is to timber

SUPPLY AND FIX


-
Doors -
-
A "Union CZ682-24-52CH" 3 lever lockset and furniture set 1 No 20,000.00 20,000.00
-
B Door stop 9002AS 1 No 5,000.00 5,000.00
-
C Window Handles 6 No 6,000.00 36,000.00
-
D Window Stays 6 No 6,000.00 36,000.00
-
-

4.77
To Summary 97,000.00
GUARD HOUSE

4.78
ITEM WALL FINISHES QTY UNIT K T

Plant

A Bring to site all plant and equipment equal


required for this section of work Item

B Maintening on site all palnt and equipment


required for this section of work (Time related) Item

C Removing from site all plant and equipment


required for this work Item

EXTERNAL WALLS

PLASTERWORK

Pointing

D Point in cement and sand mortar (1:4) 31 M2 3,500.00 108,500.00


-
E Ditto in narrow widths 2 M2 3,500.00 7,000.00
-
15mm Rendering in (1:1:6) cement, and -
sand, finished with a steel trowel -
-
F Block/ concrete walls(PROVISIONAL) 2 M2 20,000.00 40,000.00
-
G Ditto in narrow widths 1 M2 20,000.00 20,000.00
-
PAINTING AND DECORATING -
-
Prepare and apply two coats of styrene acrylic emulsion -
coloured sealer on -
-
H Rendered walls 31 M2 4,500.00 139,500.00
-
I Ditto in narrow widths 2 M2 4,500.00 9,000.00
-
Prepare and apply one water thinned coat -
and two finishing coats of external quality washable -
paint or equal approved on -
-
J Rendered walls (PROVISIONAL) 2 M2 4,500.00 9,000.00
-
K Ditto in narrow widths 1 M2 4,500.00 4,500.00

To Collection 108,500.00

4.79
GUARD HOUSE

ITEM WALL FINISHES QTY UNIT K T

INTERNAL

PLASTERWORK

15mm Rendering (1:4) cement and sand, finished


with a final coat of lime putty steel trowelled -
-
A Brick / concrete walls 29 M2
3,500.00 101,500.00
-
B Ditto, narrow widths 2 M2 3,500.00 7,000.00
-
PAINTING AND DECORATING -
-
Prepare and apply one coat Dulux new plaster Primer -
code (192-0802) and two coats of Dulux wallguard -
interior wash 'n wear silk -
or equally approved on -
-
C Rendered wall 29 M2 4,500.00 130,500.00
-
D Ditto, narrow widths 2 M2
4,500.00 9,000.00
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-

4.80
To Collection 248,000.00
GUARD HOUSE

ITEM WALL FINISHES QTY UNIT K T

COLLECTION

108,500.00
4.22

4.23 248,000.00

4.81
TO SUMMARY 356,500.00
GUARD HOUSE

ITEM FLOOR FINISHES (All Provisional) QTY UNIT K T

Plant

A Bring to site all plant and equipment equal


required for this section of work Item

B Maintening on site all palnt and equipment


required for this section of work (Time related) Item

C Removing from site all plant and equipment


required for this work Item

FLOOR FINISHES

40mm 1:3 Cement and sand granolithic screed finished


with a steel trowel

D 40 mm Thick to concrete slab 9 M2 3,500.00 31,500.00


-
E 100mm High cement and sand (1:3) mix skirting 10 M1 3,500.00 35,000.00
-
-
-

4.82
TO SUMMARY 66,500.00
GUARD HOUSE

ITEM CEILING FINISHES QTY UNIT K T

Plant

A Bring to site all plant and equipment equal


required for this section of work Item -

B Maintening on site all palnt and equipment


required for this section of work (Time related) Item -

C Removing from site all plant and equipment


required for this work Item

CARPENTRY

Unless otherwise stated, all timber shall


be treated wrot softwood

D 50 X 50 mm Brandering 30 M1 1,500.00 45,000.00


-

E Ditto, fixed to brickwork / concrete 10 M1 1,500.00 15,000.00


-
JOINERY -
-
Unless otherwise stated, all timber -
is hardwood -
-
Panelling -
-
F 6mm Thick 'Nulite' ceiling board to BS 1142 -
part 3, butt jointed with chamfered edges, -
fixed with galvanised clout nails to timber -
framed ceiling 9 M2 10,000.00 90,000.00
-

G Extra over Nulite board for 600 x 600 mm -


access panel, include trimming opening with -
25 x 100 mm frame, 25 x 25 mm stop and -
25 x 100 mm architrave 1 No 20,000.00 20,000.00
-
-
-

4.83
To Collection 170,000.00
GUARD HOUSE

ITEM CEILING FINISHES QTY UNIT K T

Battens

A 75 x 75 mm nu-cornice, two labour (s) 10 M1 4,000.00 40,000.00


-
Prepare and apply one undercoat code -
196-0763 and two coats interial PVA -
white code 172-0734 or equally approved on -
-
B 6mm Nu-lite ceiling 9 M2 4,500.00 40,500.00
-

Prepare and apply one coat pink primer code -


(9191-0801), one undercoat code (196-0763) and two -
coats gloss enamel - quartz flint 2 code (50BG 64/02B) -
or equally approved on -
-
C Nu-cornice, 0 to 100 mm girth 10 M1 3,500.00 35,000.00
-
-
-

4.84
To Collection 115,500.00
GUARD HOUSE

ITEM CEILING FINISHES QTY UNIT K T

COLLECTION

4.26 170,000.00

4.27 115,500.00

4.85
TO SUMMARY 285,500.00
GUARD HOUSE

ITEM SUMMARY PAGE No. K T

A SUBSTRUCTURE 4.11 913,300.00

B ROOF 4.14 115,500.00

C EXTERNAL AND INTERNAL WALL 4.16 1,758,000.00

D WINDOWS AND DOORS 4.20 389,540.00

E IRONMONGERY 4.21 97,000.00

F WALL FINISHES 4.24 356,500.00

G FLOOR FINISHES 4.25 66,500.00

H CEILING FINISHES 4.28 285,500.00

4.86
TO MAIN SUMMARY K 3,981,840.00
GUARD HOUSE

SUMMARY
PAGE NO.

A FENCE AND GATES 4.6 30,874,586.00


-
B GUARD HOUSE 4.29 3,981,840.00
-

4.87
FENCE, GUARD HOUSE AND GATE - TOTAL CARRIED TO MAIN SUMMARY 34,856,426.00
34,856,426.00

4.88
TB-ISOLATION WARD

Item SITEWORKS Unit Qty Rate


(ALL PROVISIONAL)

PARKING AND ACCESS DRIVEWAYS


SITE CLEARANCE

A Clear site of all bushes, shrubs and under growth and cutting down trees not M2 3,500 300.00
exceeding 1500mm girth, including grubbing up roots and removing away
from site
B Ditto, trees exceeding 4500mm girth No. 8 20,000.00
C Excavate average 150mm deep to remove vegetable soil; wheel and remove M2 3,500 450.00
from site.
D Mass excavation to reduce levels commencing from stripped level not M3 5,250 2,500.00
exceeding 1.5m deep; deposit in temporary spoil heaps on site.
E Ditto, 1.5 to 3m deep M3 2,625 2,500.00
F Ditto, 3 to 4.5m deep M3 1,313 2,500.00
G Load and cart away surplus excavated material from site. M3 9,188 2,500.00

FILL TO MAKE UP LEVELS


H Approved imported murram fill: well compacted in layers not exceeding M3 525 6,000.00
150mm thick using 15 ton vibrating roller to 95% MDD ASHTO to Engineer's
approval.
I Compact existing subgrade to 93% MDD, (MOD AASHTO), CBR>15% M2 3,500 1,200.00

PRECAST CONCRETE heavy duty paving blocks or any other equal and
approved : quadblock pattern.

J 80 mm Thick concrete block size 205 x 110 mm laid on falls and including 50 M2 350 16,000.00
mm thick sand bed, allow for compaction, rolling and vibration, spread and
brush into joints and compact.

CARRIED TO SUMMARY K

External Works 5.89


TB-ISOLATION WARD

Item STORM WATER DRAINAGE Unit Qty Rate

Dished Drain

A 675mm Girth blockwork Channel drain, rendered (15mm thick 1;4 cement
and sand) on sides, laid to falls on 50mm thick concrete slab and include
50mm thick sand bed, include for excavations and disporsal of surplus spoil M 188
as required
15,000.00
B Drain size 500 x 400 mm, average depth internally
comprising half brick sides and brick on base, laid to
falls and including 13 mm cement and sand (1:4) M 72 15,000.00
rendering to all internal surfaces and including all
excavations and disposal

Channel Drains

C 400 x 400mm deep internally channel drain having


75mm thick plain in situ concrete (14N/mm2/40mm)
base, and precast concrete covers and one brick thick sides in extra
hard burnt bricks bedded and jointed in cement mortar (1:4), top edge of
sides,sides and base rendered with 15mm thick cement
and sand render (1:4),laid to fall,include for all
excavations and disposal of surplus spoil as required M 107 15,000.00

CARRIED TO SUMMARY K

External Works 5.90


TB-ISOLATION WARD

External Works 5.91


TB-ISOLATION WARD

Item ROADS AND CARPARKS Unit Qty Rate


(ALL PROVISIONAL)

ROADS AND CARPARKS

Roads and Carparks

A Excavate/rip and scarify oversite to reduce levels M3 86 2,000.00

B Compact surface of reduced excavation by an


approved method to achieve a Mod AASHO of
of 95% M2 570 750.00

C 150mm thick laterite sub base course,graded to falls and


cross falls and compacted to achieve a MOD AASHO of 95% M2 570 1,000.00

D 150mm thick laterite base course,graded to falls and


cross falls and compacted to achieve a MOD AASHO of 98% M2 570 1,000.00

CONCRETE WORK

PLAIN IN-SITU CONCRETE (CLASS 10N/MM2/


40 MM)
F 125 x 250 mm High precast concrete (Class 21N/mm2/
10mm) kerb, splayed on one face, generally in 890 mm
lengths, bed and haunched in and including 0.03m3/m
excavation, formwork, jointing, etc M 332 5,000.00

G Ditto, curved to varying radii M 332 5,000.00

IN-SITU CONCRETE; REINFORCED

Normal; designed mix 20N/mm2; 40mm


aggregate; vibrated

Beds; horizontal; cast in bays

H 150mm thick M2 375 8,000.00

REINFORCEMENT

Fabric; BS 4483

Hard drawn mild steel fabric reinforcement (Reference A142),


weight 2.22kg/m2; 150mm side and end laps

I in beds M2 375 4,500.00

FORMWORK

Sawn Formwork;

Edges, sides or risers

J projecting edges of bed 75-150mm girth M 200 3,500.00

PREPARE AND APPLY TWO FULL COATS


OF "ROAD MARKING" PAINT ON

K Concrete kerb M 332 5,000.00

L Carparking spaces demarcation M 186 5,000.00

CARRIED TO SUMMARY K

External Works 5.92


TB-ISOLATION WARD

Item PATHS AND PAVINGS Unit Qty Rate


(ALL PROVISIONAL)

CONCRETE WORK

PLAIN IN-SITU CONCRETE (CLASS 10N/


MM2/40MM) (Cont'd)

A 50 mm Thick precast vibrated concrete (Class 21N/


mm2/10mm) slabs, general size 600 x 600 mm
having smooth finish, bedded, jointed and pointed in
cement mortar (1:3) laid to falls and cross falls on
sand bed (measured separately) include for all
cutting and / or mortar packing to edge and joints and
for pattern as shown on the drawings m2 302 10,000.00

CARRIED TO SUMMARY K

External Works 5.93


TB-ISOLATION WARD

Item FOUL DRAINAGE Unit Qty Rate


(ALL PROVISIONAL)

TRENCH EXCAVATIONS

EXCAVATION AND EARTHWORK

A Excavate trench from reduced level for large diameter


pipe, 0-1500 mm deep, avarage 750 mm deep M 205 1,000.00

B Extra over excavation for excavating in hard and


compacted material M 205 1,000.00

PIPEWORK

110 mm Diameter class 4 uPVC pipe, having socketed "O" ring joints in the
C running length, laid on and including 50mm sand blinding in trench M 205 1,500.00

D Extra over pipework for 180.45 junction No 38 6,000.00

E Ditto, for 1805.4.87 long radius bend No 22 6,000.00

MANHOLES

14 NO. MANHOLES

EXCAVATION AND EARTHWORK

F Excavate pit from reduced level for manhole bases 0-1500mm deep m3 12 2,000.00

DISPOSAL OF EXCAVATED MATERIAL

G Backfilled into excavation m3 3 3,000.00

H Remove surplus material from site m3 9 3,000.00

CONCRETE WORK

REINFORCED VIBRATED CONCRETE CLASS

25N/MM2/20MM AGGREGATE

I Plain insitu concrete 150 mm Thick in bed m2 10 30,000.00

J Ditto, in benching average 200mm thick with steep slopes to channels and
branches in bottom of manhole finished with 15mm cement, lime and sand
(1:1:6) rendering, trowelled smooth m2 9 30,000.00

CARRIED TO COLLECTION K

External Works 5.94


TB-ISOLATION WARD

Item FOUL DRAINAGE Unit Qty Rate


(ALL PROVISIONAL)

SAWN FORMWORK

A Sawn formwork to soffit of slab, include for withdrawing


from confined space M2 15 18,000.00

B Ditto, to edge of slab, 75 to 150mm wide M 62 3,500.00

SUNDRIES

C Form 450 x 600 mm opening in 125 mm slab, include for edge formwork No 14 20,000.00

REINFORCEMENT

D Hard drawn mild steel fabric reinforcement, Ref A142 weighing 2.22kg/m2 in
slabs M2 15 4,500.00

BLOCKWORK

Precast Hollow Cement and Sand Blocks In


cement mortar (1:4) Filled Solid with concrete
(Grade 15/14)

E 200mm Thick walls m2 43 18,000.00

PLASTERWORK

F 15 mm Rendering (1:4) cement and sand, finished with a steel trowel on


internal faces of blockwork M2 43 3,500.00

G Ditto, finished with a steel trowel on external faces of blockwork M2 15 3,500.00

H Build in end of 110 mm diameter pipe to one block wall and make good
rendering one side No 23 3,000.00

METALWORK

I Galvanised malleable cast iron step to BS 1247 with 125mm tail and build
into block side of manhole No 28 60,000.00

J Medium duty manhole cover and frame (BS 497, Table 6, GradeB) 450 x
600mm, including bedding frame in cement mortar (1:3) and seal cover in
heavy grease No 14 60,000.00

CARRIED TO COLLECTION K

External Works 5.95


TB-ISOLATION WARD

Item FOUL DRAINAGE Unit Qty Rate


(ALL PROVISIONAL)

1 No. SEPTIC TANK (INCLUDING ENTRY MANHOLE

A Excavate pit from reduced level for septic tank 0-1500mm deep M3 13 3,000.00

B Ditto 1500 -3000 mm deep M3 2 5,000.00

DISPOSAL OF EXCAVATED MATERIAL

C Disposal of surplus material from excavations,


transported a distance average of 250 m from
excavation, deposit, spread and level where directed
on site M3 15 3,000.00

CONCRETE WORK

PLAIN CONCRETET CLASS 25N/MM2/20MM


AGGREGATE

D 100 mm Thick bed laid to falls M2 6 20,000.00

E 150 mm Thick bed ditto M2 6 20,000.00

F Ditto in benching, average 200 mm thick, with steep slopes to channels and
branches, laid to falls, steel trowelled smooth, including a neat and even joint
to edge of channels and branches M2 1 20,000.00

G 150 mm Thick suspended slab M2 7 20,000.00

PRECAST REINFORCED VIBRATED CONCRETE


CLASS 25N/MM2/20MM AGGREGATE

H 300 x 230 x 2360 mm Lintel, reinforced with and


including 30 kg of mild steel bar reinforcement No 5 30,000.00

SAWN FORMWORK

I To soffit of suspended slab M2 7 18,000.00

REINFORCEMENT

J
Hard drawn mild steel fabric reinforcement, A142 weighing 2.22kg/m2 in slab M2 7 4,500.00

CARRIED TO COLLECTION K

External Works 5.96


TB-ISOLATION WARD

Item FOUL DRAINAGE Unit Qty Rate


(ALL PROVISIONAL)

SUNDRIES

A Form 450 x 600 mm opening in 125mm slab, including for edge formwork No 3 12,000.00

BLOCKWORK

Precast Hollow Cement and Sand Blocks In


cement mortar (1:4) Filled Solid with concrete
(Grade 15/14)

B 200mm Thick walls M2 15 20,000.00

PLASTERWORK

C 15 mm Rendering (1:4) cement and sand, finished


with a steel trowel on internal faces of brickwork M2 15 3,500.00

D Ditto, finished with a steel trowel on external faces


of brickwork M2 3 3,500.00

E Build in end of 110 mm diameter pipe to one brick


wall and make good rendering one side No 3 6,000.00

METALWORK

F Galvanised malleable cast cover step to BS 1247


with 125 mm tail and build into brick side of manhole No 8 60,000.00

G Medium duty manhole cover and frame (BS 497,


Table 6, GradeB) 450 x 600 mm, including bedding
frame in cement mortar (1:3) and seal cover in heavy
grease No 3 60,000.00

PIPEWORK

H 110 mm Diameter class 4 uPVC pipe square junction


and 450 mm length of pipe with socketted "O" ring
joints including building in blockwork and connecting
to septic tank No 6 6,000.00

I 110 mm Diameter uPVC straight main channel


800mm long No 2 6,000.00

CARRIED TO COLLECTION K

External Works 5.97


TB-ISOLATION WARD

Item FOUL DRAINAGE Unit Qty Rate


(ALL PROVISIONAL)

SOAKWAY PIT

A Excavate pit from reduced/ natural ground level for


dispersal chamber, 0 -1500 mm deep M3 7 3,000.00

B Ditto 1500 - 3000 mm deep M3 1 3,000.00

C Graded stone filling around chamber M3 8 6,000.00

DISPOSAL OF EXCAVATED MATERIAL

D Disposal of surplus material from excavations,


transported a distance average of 250 m from
excavation, deposit, spread and level where directed
on site M3 8 3,000.00

CONCRETE WORK

PLAIN CONCRETE CLASS 25N/MM2/20MM


AGGREGATE

E 200 mm Thick footing M2 3 20,000.00

F 150 mm Thick suspended slab M2 5 20,000.00

SAWN FORM WORK

G To soffit of suspended slab M2 5 18,000.00

H To edge of strip footing curved on plan, 1730 mm


radius 225- 300 mm wide M 9 3,500.00

REINFORCEMENT

I Hard drawn mild steel fabric reinforcement, A142


weighing 2.22 kg/m2 in slab M2 5 4,500.00

SUNDRIES

J Form 450 x 600 mm opening in 125 mm slab,


including for edge formwork No 1 3,500.00

K Built-in ends of 110 mm diameter pipe to half brick


wall No 2 6,000.00

CARRIED TO COLLECTION K

External Works 5.98


TB-ISOLATION WARD

Item FOUL DRAINAGE Unit Qty Rate


(ALL PROVISIONAL)

BLOCKWORK

Precast Hollow Cement and Sand Blocks In


cement mortar (1:4) Filled Solid with concrete
(Grade 15/14)

A 200mm Thick walls M2 12 18,000.00

METALWORK

B Medium duty manhole cover and frame (BS 497,


Table 6, GradeB) 450 x 600 mm, including bedding
frame in cement mortar (1:3) and seal cover in heavy
grease No 1 60,000.00

FRENCH DRAINS

EXCAVATION AND FILLING

C Excavate trench for large diameter pipe 0 - 1500 mm


average width 750 mm M3 68 3,000.00

D 20 mm Aggregate loose clean filling around pipe M3 52 3,000.00

E Graded stone filling backfilled into trench M3 13 3,000.00

DISPOSAL OF EXCAVATED MATERIAL

F Disposal of surplus material from excavations,


transported a distance average of 250 m from
excavation, deposit, spread and level where directed
on site M3 55 3,000.00

DAMP PROOF MEMBRANE

G 250 Microns polythene sheeting laid on aggregate


filling in trenches M2 45 600.00

PIPEWORK

H 110 mm Diameter UPVC perforated pipe lain in


aggregate filling in trenches M 60 3,000.00

CARRIED TO COLLECTION K

External Works 5.99


TB-ISOLATION WARD

Item FOUL DRAINAGE Unit Qty Rate


(ALL PROVISIONAL)

SUNDRIES

A Allow for testing and commissioning Item 100,000.00

CARRIED TO COLLECTION

COLLECTION Page
No

5.5

5.6

5.7

5.8

5.9

5.10

5.11

CARRIED TO COLLECTION K

External Works 5.100


TB-ISOLATION WARD

SUMMARY
Item EXTERNAL WORKS

Page
No

A SITE WORKS 5.1

B STORM WATER DRAINAGE 5.2

C ROADS AND CARPARKS 5.3

D PATHS AND PAVINGS 5.4

E FOUL DRAINAGE 5.11

EXTERNAL WORKS - TOTAL CARRIED TO MAIN SUMMARY K

External Works 5.101


TB-ISOLATION WARD

K t

-
-

1,050,000.00

160,000.00
1,575,000.00

13,125,000.00

6,562,500.00
3,281,250.00
22,968,750.00

-
3,150,000.00

4,200,000.00

5,600,000.00

-
-

61,672,500.00

External Works 5.102


TB-ISOLATION WARD

K t

2,820,000.00
-
-
1,080,000.00
-
-
-
-
-
-
-
-
-
-
-
1,605,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-

-
-
-

5,505,000.00

External Works 5.103


TB-ISOLATION WARD

External Works 5.104


TB-ISOLATION WARD

K t

-
171,000.00
-
-
-
427,500.00
-
-
570,000.00
-
-
570,000.00
-
-
-
-
-
-
-
-
1,660,000.00
-
1,660,000.00
-
-
-
-
-
-
-
-
3,000,000.00
-
-
-
-
-
-
-
-
1,687,500.00
-
-
-
-
-
-
-
700,000.00
-
-
-
-
1,660,000.00
-
930,000.00
-
-
-

12,437,500.00

External Works 5.105


TB-ISOLATION WARD

K t

3,020,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-

3,020,000.00

External Works 5.106


TB-ISOLATION WARD

K t

205,000.00
-
-
205,000.00
-
-
-

307,500.00
-
228,000.00
-
132,000.00
-
-
-
-
-
-
-
24,000.00
-
-
-
9,000.00
-
27,000.00
-
-
-
-

-
-
300,000.00
-

270,000.00
-
-

1,707,500.00

External Works 5.107


TB-ISOLATION WARD

K t

270,000.00
-
217,000.00
-
-
-

280,000.00
-
-
-

67,500.00
-
-
-
-
-
-
-
774,000.00

150,500.00
-
52,500.00
-

69,000.00
-
-
-

1,680,000.00
-

840,000.00
-
-
-
-

4,400,500.00

External Works 5.108


TB-ISOLATION WARD

K t

39,000.00
-
10,000.00
-
-
-
-
-
-
45,000.00
-
-
-
-
-
-
120,000.00
-
120,000.00
-

20,000.00
-
140,000.00
-
-
-
-
-
150,000.00
-
-
-
126,000.00
-
-
-

31,500.00
-
-
-
-
-
-

801,500.00

External Works 5.109


TB-ISOLATION WARD

K t

36,000.00
-
-
-
-
-

-
300,000.00
-
-
-
-
52,500.00
-
-
10,500.00
-
-
18,000.00
-
-
-
-
480,000.00
-
-
-
-
180,000.00
-
-
-
-
-
-
36,000.00
-
-
12,000.00
-
-
-
-
-
-
-

1,125,000.00

External Works 5.110


TB-ISOLATION WARD

K t

-
21,000.00
-
3,000.00
-
48,000.00
-
-
-
-
-
-
24,000.00
-
-
-
-
-
-
60,000.00
-
100,000.00
-
-
-
90,000.00
-
-
31,500.00
-
-
-
-
22,500.00
-
-
-
-
3,500.00
-
-
12,000.00
-
-
-
-
-

415,500.00

External Works 5.111


TB-ISOLATION WARD

K t

216,000.00
-
-
-
-
-
-
60,000.00
-
-
-
-
-
-

-
156,000.00
-
39,000.00
-
-
-
-
-
-
165,000.00
-
-
-
-
27,000.00
-
-
-
-
180,000.00
-
-
-
-
-
-
-

843,000.00

External Works 5.112


TB-ISOLATION WARD

K t

100,000.00

100,000.00

4,400,500.00

801,500.00

1,125,000.00

415,500.00

843,000.00

100,000.00

7,685,500.00

External Works 5.113


TB-ISOLATION WARD

K t

61,672,500.00

5,505,000.00

12,437,500.00

3,020,000.00

7,685,500.00

90,320,500.00

External Works 5.114


ITEM GROUND PREPARATION QTY UNIT RATE AMOUNT

PREPARATION

Refer to Scope of Works, Technical Specifications


and Drawings. All areas will be cultivated to a
minimum depth of 150mm and all large stones,
perennial weeds and rubbish removed to a tip.

Site Clearance (Provisional)

A Clear site of all rubbish ,concrete materials ,rubbles 2,100 M² 600.00 1,260,000.00
stones and any unwanted material in all planting areas -
-
Levelling -
B Break all soil and clods and rake it out to 1,100 M² 600.00 660,000.00
make fine levels. -
C Trimming sides of excavations to slope 50 M² 600.00 30,000.00
-
Top Soil -
-
D Supply fertile top soil to all cultivated grounds using -
using a 7 tonne lorry / tipper 4 Trip 150,000.00 600,000.00
-
E Thoroughly apply and mix top soil average 100mm deep -
to all cultivated grounds then level back the soil. 4 Trip 100,000.00 400,000.00
-
Manure (Provisional) -
-
F Provide well decomposed composite or dung manure
average 50mm deep using a 7 tonne lorry 4 Trips 100,000.00 400,000.00
to all cultivated areas.

G Thoroughly apply and mix to all planting areas including areas 4 Trip 100,000.00 400,000.00
for lawn,shrubs and trees

Total carried to summary page 3,750,000.00

6.115
ITEM GRASS (LAWN) QTY UNIT RATE AMOUNT

LAWN (Provisional)

A Provide and plant grass at 100mm centres average

cynodon dactylon incooporated with paspulum 1,200 M² 1,000.00 1,200,000.00


notatum -
FERTILIZER -
-
B Provide 23:21:0+4S basic fertilizer at the -
rate of 60g/m² 2 50kg Bag 100,000.00 200,000.00
-
C Provide Urea fertilizer at the rate of 60g/m² 2 50kg Bag 100,000.00 200,000.00
-

-
SUNDRIES -
-
D Lawn Maintenance until it is fully established by replanting 6 Month 300,000.00 1,800,000.00
dead grass, watering,weeding,fertilizer application and mowing. -
-
WATER BILLS (Provisional) -
E Provide for monthly water bills used for 6 Month 300,000.00 1,800,000.00
Lawn irrigation. -

Total carried to Summary Page 5,200,000.00

6.116
ITEM TREES QTY UNIT RATE AMOUNT

A EXCAVATION (Provisional)
Excavate holes of not less than 10000mm² and 112 No 6,000.00 672,000.00
not less than 1000mm deep for tree planting

B Selected filling of compost manure, deposited, 112 No 5,000.00 560,000.00


spread and mixed with approved topsoil

DISPOSAL (Provisional)

C Surplus excavated material from excavations


transported a distance average 100 linear
metres from excavations, deposited,
Spread and level where directed on site 25 M3 3,000.00 75,000.00

TREES (Provisional)

D Provide and plant the following trees according


to specifications

Callistemon viminalis 24 No. 3,500.00 84,000.00


Mango trees 5 No. 3,500.00 17,500.00
Jacaranda mimosifolia 35 No. 3,500.00 122,500.00
Khaya nyasica 48 No. 3,500.00 168,000.00

E Provide treated stakes and ties to trees


as per specification 112 No. 6,000.00 672,000.00

SUNDRIES

F Trees maintenance, as per Scope of Works 6 Month 300,000.00 1,800,000.00


and Technical Specifications until they are fully established.

Total carried to Summary Page 4,171,000.00

6.117
ITEM PASTURE PLOTS QTY UNIT RATE AMOUNT

EXCAVATION

A Excavate pits not exceeding 200mm deep for


pasture plants ( Chloris gayana and pennnisetum 198 No. 6,000.00 1,188,000.00
purpureum and 500mm deep for Leacaena leucophala -

B Selected filling of compost manure, deposited, 1,100 M² 600.00 660,000.00


spread and mixed with approved topsoil

C DISPOSAL (Provisional) 100 M² 600.00 60,000.00


Surplus excavated material from excavated material
from excavations transported a distance
average 100 linear metres from excavations,
deposit,spread and level where directed on site

PASTURE PLANTS

Chloris gayana (Rhodes grass) 152 No. 3,000.00 456,000.00


Leacaena leucocephala 152 No. 3,000.00 456,000.00

E SUNDRIES
Pasture plants maintenance, as per 6 Month 300,000.00 1,800,000.00
Scope of Works and Technical Specifications

4,620,000.00
Total carried to Collection Page

6.118
ITEM SHRUBS AND HERBACEOUS PLANTS QTY UNIT RATE AMOUNT

EXCAVATION

A Excavate pits not exceeding 500mmx500mmx500mm deep


for shrub planting and 200mm deep for herbaceous 90 No 500.00 45,000.00
plants.
B Selected filling of compost manure, deposited, 270 No 500.00 135,000.00
spread and mixed with approved topsoil

C DISPOSAL (Provisional) 20 M² 3,000.00 60,000.00


Surplus excavated material from excavated material
from excavations transported a distance
average 100 linear metres from excavations,
deposit,spread and level where directed on site

D SHRUBS
Provide and plant shrubs according
to specifications

Acalypha microphylla l wilkesiana 5 No. 3,500.00 17,500.00


Codiaeum Variegatum 'Medio-picta Broad' 5 No. 3,500.00 17,500.00
Codiaeum Marginata 5 No. 3,500.00 17,500.00
Euphorbia Pulcherima 5 No. 3,500.00 17,500.00
Malvaviscus arboreus 5 No. 3,500.00 17,500.00
Megaskepasma erythrochlamys 5 No. 3,500.00 17,500.00

HERBACEOUS PLANTS (GROUNDCOVERS)

Agapanthus Africanus 10 No. 3,000.00 30,000.00


Ophiopogon jaburan 'Green' 10 No. 3,000.00 30,000.00
Tradescantia spathacea 10 No. 3,000.00 30,000.00
Tulbaghia Violacea 10 No. 3,000.00 30,000.00
Euphorbia milli 20 No. 3,000.00 60,000.00

E SUNDRIES
Shrubs and Herbaceous plants maintenance, as per 6 Month 300,000.00 1,800,000.00
Scope of Works and Technical Specifications

2,325,000.00
Total carried to Summary Page

6.119
ITEM SUMMARY PAGE NO.

A GROUND PREPARATION 6.1 3,750,000.00

B GRASS (LAWN) 6.2 5,200,000.00

C TREES 6.3 4,171,000.00

D PASTURE PLOTS 6.4 4,620,000.00

E SHRUBS AND HERBACEOUS PLANTS 6.5 2,325,000.00

6.120
SUMMARY 20,066,000.00

6.121
Item PRIME COST SUMS AND PROVISIONAL SUMS Unit Qty Rate K t

PROVISIONAL SUMS

A Allow the Provisional Sum of K2,000,000.00 (Two 2,000,000.00


Million Kwacha) for foul drainage
-

CARRIED TO SUMMARY K 2,000,000.00

7.1
BILL NO.1 - ENVIRONMENTAL, SOCIAL, HEALTH AND SAFETY MANAGEMENT (ESHS)

Item N° Description Unit Amount (MK)


Resources allocated to ESHS
ESHS 1 Lump sum 500,000.00
management

Drafting and updating the ESHS


ESHS 2 Lump sum 500,000.00
documentation, reporting, inspections

Implementation of the Health and


Safety Plan:

ESHS 3 Meetings, health care center, medical Lump sum 500,000.00


check‑ups, emergencies and
evacuations, safety protective
equipment, hygiene

Induction Training

(*) : The Bidder shall detail the financial


conditions of the supply of
ESHS 4 accommodation, meals and transport to
its staff and Induction trainer (to be
advised by Client):

-        Accommodation Lump sum 500,000.00


-        Meals Lump sum 500,000.00
-        Transport Lump sum 500,000.00
Training and local recruitment
ESHS 5 Lump sum 500,000.00
management costs

Protection of adjacent areas,


ESHS 6 biodiversity, prevention of erosion and Lump sum 500,000.00
wastewater management

CARRIED TO COLLECTION 4,000,000.00


8.1
Item N° Description Unit Amount (MK)
Traffic, noise and atmospheric
ESHS 7 Lump sum 500,000.00
emissions management, land take

Waste and hazardous products


ESHS 8 Lump sum 500,000.00
management

Vegetation clearing and site


ESHS 9 Lump sum 500,000.00
rehabilitation

Firefighting training

Trainer allowance and purchase of fire


ESHS10 Lump sum 500,000.00
extinguishers

Work at height training

Trainer allowance and Need for fund to


ESHS11 Lump sum 500,000.00
purchase safety harness and scaffolds

HIV/AIDS, Gender Based Violence


training/awareness campaign

Funds for awareness campaign (trainer


ESHS 12 allowance) posters on HIV/AIDS, Lump sum 500,000.00
distribution of condoms

COVID19 awareness training

ESHS12 Allowance for the one carrying the talk Lump sum 500000

Replacing cut down trees in the ration


of 1:10

Need for funds to purchase the required


ESHS13 Lump sum 500000
seedlings

CARRIED TO COLLECTION
4,000,000.00

8.2

Item N° Description Unit Amount (MK)


Allow for funds for first aid training
ESHS14 (trainer allowance) and acquiring a first Lump sum 500000
aid box

Provision for PPE

Price the purchasing of boots, working


ESHS15 suits, helmets, dust masks, groves, ear Lump sum 500000
muffs and safety goggles

Provision for ESHS Sign Board

ESHS 16 Notice board with signs labelling Lump sum 500000

Price for acquisition of such permits


Provision for obtaining waste disposal
ESHS 17 Lump sum 500000
permits / letters

CARRIED TO COLLECTION 10,000,000.00


8.3

COLLECTION

Page No.

8.1 4,000,000.00
8.2 4,000,000.00
8.3 10,000,000.00

TOTAL ESHS CARRIED TO GRAND SUMMARY 18,000,000.00

8.4
TB-ISOLATION WARD

Item No. MAIN SUMMARY

Page
No.

A BILL NO. 1- PRELIMINARIES 1.7

B BILL NO. 2- PREAMBLES 2.59

C BILL NO. 3- TB-ISOLATION WARD 3.31

D BILL NO. 4-FENCE,GATE AND


GUARD HOUSE 4.30

E BILL NO. 5-EXTERNAL WORKS 5.12

F BILL NO. 6-LANDSCAPE 6.6

G BILL NO. 7-PROVISIONAL SUMS 7.1

H BILL NO. 8-ESHS MANAGEMENT 8.4

SUB-TOTAL K

Add:Contingency for design, physical


and price changes to be spent or
deducted at the descretion of the
Architect/Supervising Officer 15% K

Add: VALUE ADDED TAX (V.A.T) 16.5% K

Add: N.C.I.C LEVY 1.0% K

MAIN SUMMARY TOTAL CARRIED


TO GRAND SUMMARY

MAIN SUMMARY
TB-ISOLATION WARD

K t

5,500,000.00

190,104,300.00

34,856,426.00

90,320,500.00

20,066,000.00

2,000,000.00

18,000,000.00

360,847,226.00

54,127,083.90

414,974,309.90

68,470,761.13

4,149,743.10

487,594,814.13

MAIN SUMMARY

You might also like