Professional Documents
Culture Documents
1
PRELIMINARIES
GENERAL MATTERS
2.3 Furnishing the Engineer's Site Office including all furniture and basic
office equipment
2.4 Plant
Provide for all plant necessary for the proper execution of the works
comprising:-
Provide for all necessary watching and lighting and take general
security measures to safeguard the works, materials and plant,
including sub-contractor's property, against damage and theft.
Provide all necessary measures for the safety of the public for the
duration of the contract.
Provide for maintaining all public and private roads and footpaths
adjacent to or upon the site. The contractor shall be held responsible
for making good at his own expense any damage thereto including that
caused by sub-contractors or the transport of suppliers and shall pay all
costs and charges in connection therewith.
CARRIED TO COLLECTION
1.1
Item Description
The contractor shall within twenty-eight days from the date for
possession of the site, submit to the Engineer for his approval and
information and in a form approved by him, three copies of a
programme in which is set forth the sequence of all operations and the
time limits which the contractor proposes that each operation shall be
commenced and completed. The agreed programme may be varied
with the consent of the Engineer but the responsibility for completion
within the time stated shall remain with the contractor
The contractor shall confine all goods, materials and plant, within the
boundaries of the site and only in positions approved by the Engineer
Personnel
2.9 Expatriate personnel recruited for the project shall be subject to the
current Laws of Malawi. Bidders attention drawn to the Customs
Regulation relating to first entry previleges.
The contractor shall allow in his bid for the time and costs involved in
carrying out the above procedures and making the necessary
applications.
CARRIED TO COLLECTION
1.3
Item Description
Temporary Roads
2.9 Provide and maintain all necessary temporary roads, gangways tracks,
hardstandings, crossings and the like required for the proper execution
of the works.
Temporary Screens
2.10 Provide, erect and maintain such temporary screens and the like as
may be specifically required.
2.11 The contractor shall provide, erect and maintain all necessary
temporary fencing, hoardings fans with a minimum height of 5 meters,
planked footways, guard rails, gantries and the like for the proper
execution of the works and for the protection of the general public and
the occupants of adjacent premises and for meeting to requirements of
any relevant national or local regulations. The contractor shall allow for
altering, shifting and adapting any item of the foregoing as and when it
may be necessary and also for providing suitable to ensure its
effectiveness at all times during the execution of the works.
General Scaffolding
2.12 Provide and erect all scaffolding including all stages trestles, planks,
guard rails, barrow runs and the like required for the execution of the
works and maintain, alter and adapt as necessary and remove when no
longer required.
The contractor shall provide clean, fresh water, free from chemical or
organic impurities or other deleterious matter, for use on the works, pay
all charges in connection therewith, provide all temporary storage,
plumbing services, connections and the like and clear away and make
good upon completion of the works. Bidders should ascertain for
themselves that the site has adequate water services to enable the
construction of and allow for any additional costs that might be incurred.
CARRIED TO COLLECTION
1.4
Item Description
General
2.15 Works which are required to be carried out by a local authority or public
undertaking are dealt with separately
2.16 The contractor shall provide, erect and maintain all necessary
temporary casing, masking and screening to partly finished work
engaged by the Employer and shall also provide all necessary
temporary roofs, tarpaulins, screens, planking and general protection
necessary to protect the works from damage by frost and inclement
weather and provide all temporary gutters, pipes, surface water drains
and the like for conveyance of rainwater and clear away when no longer
required
2.17 The contractor shall be responsible for the adequate drying out of the
works and for maintaining them at a suitable temperature and humidity
until handed over.
2.18 Clean the works internally and externally upon completion to the
satisfaction of the Engineer
CARRIED TO COLLECTION
1.5
Item Description
Demobilisation
COLLECTION
PAGE 1.1
PAGE 1.2
PAGE 1.3
PAGE 1.4
PAGE 1.5
PAGE 1.6
TOTAL PRELIMINARIES AND GENERAL ITEMS CARRIED TO
GRAND SUMMARY
1.7
Amount (MK)
-
Amount (MK)
-
Amount (MK)
-
Amount (MK)
-
Amount (MK)
-
Amount (MK)
500,000.00
5,000,000.00
5,500,000.00
Amount (MK)
5,500,000.00
5,500,000.00
TB ISOLATION WARD
Refer SMM paragraph F19(a). It has been been assumed that strip footings,
bases, beds and the like within the ground will be poured against natural ground. If
formwork is required to such surfaces, the contractor must include for the same in
his excavations/concrete rates
EXCAVATIONS
A Excavate trench from reduced level for strip footing 0 to 1500mm deep. M3 299 1,000.00 299,000.00
-
B Pit from reduced level for isolated piers, not exceeding 1500mm deep M3 3 1,500.00 4,500.00
-
C Selected earth filling, deposited, spread and compacted 150mm layers around
foundations M3 170 2,500.00 425,000.00
-
Rock excavation -
-
D Extra over all types of excavation for excavating in rock
M3 45 15,000.00 675,000.00
Disposal -
-
E Surplus excuvated material from excavations, transported a distance average 100
linear metres from excavations, deposit, spread and level as directed M3 129 3,000.00 387,000.00
-
Hardcore filling to pass a 50mm ring all ways -
-
F 150mm thick (consolidated) filling well compacted and rolled M2 553 600.00 331,800.00
-
Sand blinding -
-
G 50mm Bed of sand on hardcore, rolled to receive damp proof membrane M2 553 600.00 331,800.00
-
Damp proof membrane -
-
H 125 microns(500 gauge) Polythene damp proof membrane with welted joints,
lapped 150mm at all joints and laid on blinded hardcore M2 575 600.00 345,000.00
-
Ant treatment -
-
I Saturate surface of hardcore and top of brick walls with approved ant repellant M2 575 600.00 345,000.00
-
generally -
-
-
TB-ISOLATION WARD
TB ISOLATION WARD
SUNDRIES
CONCRETE WORK
TB-ISOLATION WARD
TB ISOLATION WARD
PLASTERWORK
PAINTWORK -
-
Prepare and apply black bituminous paint -
-
C Rendered walls M2 252 4,500.00 1,134,000.00
-
D Ditto for 400 x 400mm columns M 32 3,500.00 112,000.00
CARRIED TO COLLECTION
2,224,000.00
COLLECTION Page
No
3.1 3,853,900.00
3.2 28,195,500.00
3.3 2,224,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
3.3
"CHROMADEK" CLADDING
A 0.50mm (26 gauge) "Chromadek" IBR profile prefinished steel cladding, laid with
one flute side laps and 300mm minimum end laps, fixed to timber purlins with and
including 75mm long drive screws (purlins generally at 1050mm centres) and side
laps with 6 x 25mm sheet bolts at 600mm centres. All fixings to be complete with
bitumen and flat galvanised steel washers. M2 843 25,000.00 21,075,000.00
-
Flashing shall be 0.55mm (26 Gauge) "Chromadek" steel sheet, bent to required
shape, fixed as required and shall include all labours, nails, clips, welges and laps
and joints in the running length -
-
B Ridge flashing, 450mm girth, once bent, dressed to ribs of roofing and fixed to
timber M 52 3,500.00 182,000.00
-
C Hip flashing ditto M 128 3,500.00 448,000.00
-
D Serrated ridge closer piece, fixed to timber M 360 3,500.00 1,260,000.00
E Valley gutter, 450mm girth once bent and fixed to timber M 94 3,500.00 329,000.00
-
CARPENTRY -
-
Framing -
-
Treated sawn softwood -
-
F 150 x 50mm rafter M 699 1,000.00 699,000.00
Metal work -
-
L 1200 x 50 x 1.63mm (16 gauge) galvanised hoop No 95 10,000.00 950,000.00
iron wall plate anchor one end split, bent and built into -
brickwork, twice holed and spiked to rafters. -
-
-
TB-ISOLATION WARD
TB ISOLATION WARD
C 125mm Half round section gutter DGH520 fixed to M 303 2,000.00 606,000.00
falls with brackets at 900mm centres, screw fixed to -
fascia board -
-
D Extra over for 80mm diameter outlet DO503. No 26 6,000.00 156,000.00
-
E Extra over for corner angle DA503. No 31 6,000.00 186,000.00
-
F 80mm Diameter downpipe DPH308 fixed to wall with M 39 2,000.00 78,000.00
brackets. -
-
G Extra over for swanneck bend DNB30. No 31 6,000.00 186,000.00
-
H Extra over for shoe No 31 6,000.00 186,000.00
-
-
-
COLLECTION Page
No
3.4 27,487,000.00
3.5 3,064,500.00
TB-ISOLATION WARD
TB ISOLATION WARD
CONCRETE WORK
Sawn Formwork -
-
C Sides and soffit of beam M2 155 18,000.00 2,790,000.00
-
Reinforcement (Provisional) -
-
D 12mm diameter mild steel rod reinforcement Kg 642 2,500.00 1,605,000.00
-
E 8 mm diameter ditto Kg 362 2,500.00 905,000.00
-
BLOCKWORK -
EXTERNAL WALLS
-
Precast hollow cement and sand blocks in -
cement mortar (1:4 filled solid with concrete -
(Grade 15/40) -
-
F 200 mm Thick walls M2 495 20,000.00 9,900,000.00
-
G Ditto 400 x 400 columns M 24 5,000.00 120,000.00
INTERNAL WALLS -
-
Precast hollow cement and sand blocks in -
cement mortar (1:4 filled solid with concrete -
(Grade 15/40) -
-
I 200 mm Thick walls M2 791 20,000.00 15,820,000.00
-
-
-
-
-
-
-
-
-
TB-ISOLATION WARD
TB ISOLATION WARD
WINDOW CILL
600 x 250 x 65mm thick block tiled window cill, splay rebated once grooved and
A exposed chamfered, finished fair on all exposed surfaces and built into blockwork No. 3 50,000.00 150,000.00
-
1200 x 250 x 65mm thick block tiled window cill, splay rebated once grooved and
B exposed chamfered, finished fair on all exposed surfaces and built into blockwork No. 48 20,000.00 960,000.00
-
1800 x 250 x 65mm thick block tiled window cill, splay rebated once grooved and
C exposed chamfered, finished fair on all exposed surfaces and built into blockwork No. 10 50,000.00 500,000.00
-
-
Doors -
-
Hardwood Doors -
-
Supply and fix hardwood doors, finished with clear vanish -
-
D 1500 x 2040mm high glazed hardwood double door No 3 100,000.00 300,000.00
-
E 1500 x 2100 mm high glazed hardwood double door No 2 100,000.00 200,000.00
-
Flush panel doors shall be 45mm finished thickness, faced both sides with internal
quality plywood finish lipping on sides -
-
F 800 x 2100mm High semi Solid core flush door No 13 60,000.00 780,000.00
-
G 900 x 2100mm High Solid core flush door No 15 60,000.00 900,000.00
-
Steel Door frames -
-
Rates shall include for lugs welded to back, buiding into blockwork and filling cavity
with cement and sand (1:3) -
-
H Door frame (1.2mm thick) size 1500 x 2100mm overall suitable for 200mm wall,
complete with one and half pair of butts No 5 40,000.00 200,000.00
-
I Ditto, size 800 x 2100mm ditto No 13 40,000.00 520,000.00
-
J Ditto, size 900 x 2100mm ditto No 15 40,000.00 600,000.00
-
-
-
-
-
-
-
-
-
TB-ISOLATION WARD
TB ISOLATION WARD
Window Frames
Purpose made mild steel horizontal bar windows with lugs welded. All
opening lights complete with ironmongery, including projecting hinges and
whole to be treated before delivery with one coat of red oxide primer, built
into blockwork
-
A 600 x 650 mm high window frame No 3 40,000.00 120,000.00
-
B 1200 x 650 mm high, ditto No 48 40,000.00 1,920,000.00
-
C 1800 x 1200 mm high, ditto No 10 40,000.00 400,000.00
-
-
-
GLAZING -
-
Clear sheet glass -
-
D 4mm thick Glass, fixed to metal/steel with mastic putty in panes, 0.10 to 1.00m2
M2 62 18,000.00 1,116,000.00
-
Obsure sheet glass -
-
E 4mm thick fixed to metal/steel with mastic putty in panes, 0.10 to 1.00m2 M2 48 18,000.00 864,000.00
-
PVC/ STEEL/HARDWOOD -
-
F Supply and Install, Curtain Rods M 77 1,500.00 115,500.00
-
G White pvc curtain rod bar and accessories or equal and approved M 48 1,500.00 72,000.00
-
H Extra; curtain rod ends No 122 3,000.00 366,000.00
COLLECTION Page
No
3.7 5,110,000.00
3.8 7,106,500.00
TB-ISOLATION WARD
TB ISOLATION WARD
Supply and fix the following ironmongery: Locks and furniture where applicable are
to be equal to those manufactured by "ASSA Abloy" and approved by the Architect
Doors
TB-ISOLATION WARD
TB ISOLATION WARD
INTERNAL
Plasterwork
15mm Rendering (1:4) cement and sand, finished with a final coat of lime putty,
steel trowelled
Prepare and apply one water thinned and two coats of Wash and Wear paint on
-
-
F rendered walls M2 496 4,500.00 2,232,000.00
-
-
TB-ISOLATION WARD
TB ISOLATION WARD
SCREED
300 x 300 x 6mm thick approved Non slip porcelain floor tiles : bedded and jointed
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TB-ISOLATION WARD
TB ISOLATION WARD
INTERNAL
CARPENTRY
Framing
TB-ISOLATION WARD
TB ISOLATION WARD
PROVISIONAL SUM
A Allow the Provisional Sum of K6,000,000.00 (Four Million Kwacha) for fittings and
furnishings which cannot be entirely fore-seen, defined or detailed 6,000,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
Sanitary fittings; Supply and fix sanitary ware approved by the Architect
A WC suite, comprising white grazed Vaal washdown "S" trap pan, 9 litre low level
Vaal cistern, complete with ball valve and flush pipe and plastic seat and cover.
Fix to concrete slab and block/concrete wall. No 11 150,000.00 1,650,000.00
-
B White glazed Vaal lavatory basin, 560 x 405mm, complete with integral overflow,
32mm diameter chromium plated anti-theft waste outlet, set basin on and including
pair of concealed hanger brackets fixed to block/ concrete wall No 12 100,000.00 1,200,000.00
-
C
Stainless steel sink size 1200 x 550 mm with single 'bowl single drainer to BS 1244
complete with integral overflows, 40 mm diameter chromium plated waste outlet
with plugs and chromium plated chain and fix in position to sink unit and block wall No 1 100,000.00 100,000.00
-
D 150 x 150mm white glazed vitreous china recessed toilet roll holder, set in and
including 50mm deep recess in brick/ concrete wall No 11 10,000.00 110,000.00
-
Sundries -
-
E 600 x 450mm glazed mirror with filed beveled edges No 12 20,000.00 240,000.00
-
F 600mm Long x 20mm Diameter chromium plated towel rail No 12 15,000.00 180,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
A 20mm Medium quality galvanised mild steel pipe to BS 1387 with screwed joints in
running length and standard pipe clips fixed to concrete/blockwall, include for all
bends, tees, fittings etc as required. M 15 5,000.00 75,000.00
-
B Joint of 20mm galvanised pipe to cistern. No 12 6,000.00 72,000.00
-
Connector pipes -
-
C 12mm Diameter copper connector 300mm girth, bent as required, including joint to
union of fitting and galvanised mild steel pipe with gunmetal connector. No 12 6,000.00 72,000.00
-
12mm Diameter copper connector 450mm girth, bent as required, including joint to
D union of fitting and galvanised mild steel pipe with gunmetal connector. No 11 6,000.00 66,000.00
Testing -
-
E Allow to test the foregoing sanitary fittings and overflow pipes as sp[ecified to the
satisfaction of the Architect Item -
-
285,000.00
CARRIED TO COLLECTION
COLLECTION Page
No
3.14 5,328,000.00
3.15 285,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
This section has been measured from fittings up to gully or first manhole
Waste Installation
Fittingss to walls, slabs, etc shall be with standard pipe clips, plugged and screwed
Waste Installation
TB-ISOLATION WARD
TB ISOLATION WARD
Sanitary Installation
TB-ISOLATION WARD
TB ISOLATION WARD
Testing
A Include for testing of the whole of the Waste and Sanitary Installation to the
satisfaction of the Architect/Supervising Officer
B Make hole through block wall for small pipe and make good No 14 3,000.00 42,000.00
-
C Ditto for large pipe and make good No 6 3,000.00 18,000.00
-
D Form sleeve in concrete slab for small diameter pipe and make (include for
covering the sleeve/opening) M 6 3,000.00 18,000.00
-
E Trench excavation for large diameter pipe M 69 3,000.00 207,000.00
-
-
285,000.00
CARRIED TO COLLECTION
COLLECTION Page
No
3.16 1,774,000.00
3.17 699,000.00
3.18 285,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
Reticulation to fittings
4 No WC (s)
3 No WHB (s)
1No Urinal
1 No Sink
All pipes shall be medium quality galvanised mild steel to BS with joints as
described, fixed with and including the relevant pipe supports
Rates for pipework 20mm diameter and under shall include for all bends, tees,
fittings, etc as required
Rates for all bends, tees, valves, fittings, etc shall include for the corresponding
TB-ISOLATION WARD
TB ISOLATION WARD
Sundries
A 40mm Diameter brass screw down gate valve to B.S. 1010 with capstan head and
joint pipe No 2 6,000.00 12,000.00
Testing
C Include testing of the whole of cold and hot water installations in sections during
construction and on completion, by approved means, including re - testing until
perfect to the satisfaction of the Architect/Supervising Officer Item
D Make hole through blockwall and include for making good No 36 3,000.00 108,000.00
-
E Excavate trench, 300mm wide for large pipe M 61 3,000.00 183,000.00
-
357,000.00
COLLECTION Page
No
3.19 1,419,000.00
3.20 357,000.00
CARRIED TO COLLECTION
3.20 1,776,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
Reticulation to fittings
All pipes shall be medium quality galvanised mild steel to BS with joints as
described, fixed with and including the relevant pipe supports
Rates for pipework 20mm diameter and under shall include for all bends, tees,
fittings, etc as required
Rates for all bends, tees, valves, fittings, etc shall include for the corresponding
Sundries
Testing
I Include testing of the whole of cold and hot water installations in sections during
construction and on completion, by approved means, including re - testing until
perfect to the satisfaction of the Architect/Supervising Officer -
-
Builder's Work In Connection -
-
J Make hole through blockwall and include for making good No 14 3,000.00 42,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
Item HOT AND COLD WATER SERVICES COLLECTION PAGE Unit Qty Rate K t
PAGE
TB-ISOLATION WARD
TB ISOLATION WARD
Pipe work
All pipe works and fittings for fire fighting are measured under cold water
services
Equipment
A Fire hose reels; Chubb; 19mm diameter x 35m long non-kinkable hose
6mm fixing bolts swiveling pulley with slide and housing short lenghth
of tube and 25mm non return valve fixing to backgrounds requiring
pluggings No 4 600,000.00 2,400,000.00
B Fire extinguisher; Angus; hand operated 9kg dry chemical powder, fixing
brackets to background requiring plugging No 4 500,000.00 2,000,000.00
-
C 4.5kg carbon dioxide; fixing brackets to backgrounds requiring
plugging No 4 200,000.00 800,000.00
SUNDRIES
E Allow for testing the foregoing fire fighting services, including pipe work
to twice the working pressure Item
5,200,000.00
FIRE FIGHTING TO SUMMARY K
3.23
TB-ISOLATION WARD
TB ISOLATION WARD
EARTHING
TB-ISOLATION WARD
TB ISOLATION WARD
LIGHTING CIRCUITS
A 6 Ceiling lighting point controlled by 2 gang 2 way switch (Corridor) No 3 6,000.00 18,000.00
B 1 Ceiling lighting point controlled by 1 gang 1 way switch (Ward 1, Ward 2, Ward 3, No 11 6,000.00 66,000.00
Ward 4, )
C 1 Ceiling lighting point controlled by 1 gang 1 way switch (Ward 5, Ward 6, Ward 7, No 11 6,000.00 66,000.00
Ward 8, )
TB-ISOLATION WARD
TB ISOLATION WARD
A 1 Ceiling lighting points controlled by 1 gang 1 way switch (Examination room, No 6 6,000.00 36,000.00
Waiting Area, Nursing station)
B 9 Wall mounted lighting points controlled by 1 gang 1 way switch (Security Lights) No 4 6,000.00 24,000.00
POWER CIRCUITS
C Ring Circuit to13A Twin socket switch (Ward 1, Ward 2, Ward 3, Ward 4) No 4 6,000.00 24,000.00
D Ring Circuit to13A Twin socket switch (Ward 5, Ward 6) No 2 6,000.00 12,000.00
E Ring Circuit to13A Twin socket switch (Ward 7, Ward 8) No 2 6,000.00 12,000.00
F Ring Circuit to13A Twin socket switch (Examination room, waiting area, nursing No 3 6,000.00 18,000.00
station)
TB-ISOLATION WARD
TB ISOLATION WARD
LIGHT FITTINGS
A 4ft single LED Fluorescent fitting, complete with tube No 27 6,000.00 162,000.00
B 100w x 240V black bulkhead lighting, die - cast aluminium body Body with No 8 6,000.00 48,000.00
polycarbonate lens and an E27 incandescent lamp
SWITCHES
POWER OUTLETS
F Supply and Install 13A Twin rectangular pin switched socket Outlet No 23 6,000.00 138,000.00
H Switch box with Neon Indicator controlling ceiling fan No 5 6,000.00 30,000.00
COMMUNICATION ACCESSORIES
EQUIPMENT
TB-ISOLATION WARD
TB ISOLATION WARD
A Allow the provisional sum of Two Million for ESCOM connections to the
Isolation Ward (MK 2,000,000.00) Item 2,000,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
EQUIPMENT
C Five zone analogue addressable fire alarm panel as Gent or equal approved No 2 6,000.00 12,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
SUMMARY K T
Page
No.
3.24 1,260,000.00
3.25 150,000.00
3.26 138,000.00
3.27 444,000.00
3.28 2,000,000.00
3.29 444,000.00
TB-ISOLATION WARD
TB ISOLATION WARD
SUMMARY K T
TB-ISOLATION WARD
EXTERNAL SERVICES (PALISADE WALL)
SUBSTRUCTURE
EXCAVATION
4.57
To Collection 1,626,000.00
Disposal (PROVISIONAL)
DAMP-PROOF COURSE
E generally item
4.58
To Collection 1,008,000.00
CONCRETE WORK
Foundations in trenches
BLOCKWORK
IN-SITU FINISHES
E Point in cement and sand (1:3) recessed joints of brickwork; 85 m2 3,500.00 297,500.00
external
Prepare and Apply two coats of Styrene Acrylic Emulsion Clear sealer on
4.59
To Collection 11,087,500.00
BLOCKWORK
IN-SITU FINISHES
C Point in cement and sand (1:3) recessed joints of brickwork; 640 m2 3,500.00 2,240,000.00
external -
-
D Ditto in narrow widths 16 m2 3,500.00 56,000.00
-
PAINTING AND DECORATING -
-
Prepare and Apply two coats of Styrene Acrylic Emulsion Clear sealer on -
-
G Pointed walls 640 m2 4,500.00 2,880,000.00
-
H Ditto in narrow widths 32 m2 4,500.00 144,000.00
-
CONCRETE WORK -
-
PRECAST CONCRETE; PLAIN -
-
Normal; designed mix 21N/mm2; 20mm -
aggregate; vibrated -
-
75 mm Thick precast vibrated concrete Coping (Class 21N/
mm2/10mm) slabs,
having smooth finish, bedded, jointed and pointed in
4.60
equal and approved -
-
Palisade Panels -
-
over 300mm girth 275 m2 4,500.00 1,237,500.00
-
-
-
-
-
To Collection 14,771,086.00
GATES
A Pair of mild steel sliding gates, 5000 x 2100mm high,
fabricated having 50mm RHS pipe frame and vertical -
braces, with 25mm RHS intermediates, all welded
together.Hang on and including a pair of pin hinges,
welded to gate with 50 x 50mm hasp and staple to
meeting stiles and 300mm drop bolt with keep set in and
including 150 x 150 x 150mm deep plain in-situ concrete -
(Class 14N/mm2/40mm) foundation 1 No 1,500,000.00 1,500,000.00
-
B 1175 x 2000mm high pedestrian gate 1 No 500,000.00 500,000.00
-
Metal work -
-
UBM 1234. 150. 301 254mm padlock bolts 4 No 10,000.00 40,000.00
-
PAINTING AND DECORATING -
-
Prepare, knot, stop, prime and apply one -
undercoat and two finishing coats of full -
gloss enamel on -
-
Metal General surface 42 m2 4,500.00 189,000.00
-
PAINTING AND DECORATING
Prepare , prime and apply one undercoat (red oxide) and two finishing coats of
Dulux gloss enamel or equally approved
4.61
To Collection 2,382,000.00
COLLECTION Page
4.1 1,626,000.00
4.2 1,008,000.00
4.3 11,087,500.00
4.4 14,771,086.00
4.5 2,382,000.00
4.62
EXTERNAL SERVICES (PALISADE WALL)
TO SUMMARY 30,874,586.00
GUARD HOUSE
ITEM SUBSTRUCTURE (ALL PROVISIONAL) QTY UNIT RATE K T
BILL NO. 3
Substructure
PLANT
EXCAVATION
Excavation / filling
Rock excavation
4.63
H Surplus excavation materials from excavations,
transported a distance average 100 linear metres
from excavations and deposit in spoil heaps on site 4 M3 3,000.00 12,000.00
To Collection 66,000.00
GUARD HOUSE
4.64
Wrot form work -
-
J Edge of slab, 100 to 200 mm wide 13 M1 3,500.00 45,500.00
-
-
-
-
-
To Collection 515,300.00
GUARD HOUSE
BLOCK WORK
4.65
To Collection 332,000.00
GUARD HOUSE
COLLECTION
4.8
4.9 66,000.00
4.10
515,300.00
332,000.00
4.66
To Summary 913,300.00
GUARD HOUSE
0.00
Plant -
-
A Bring to site all plant and equipment equal required -
for this section of work Item
-
B Maintening on site all palnt and equipment required -
for this section of work (Time related) Item
-
C Removing from site all plant and equipment required -
for this work Item
-
CONCRETE WORK
REINFORCEMENT (PROVISIONAL)
4.67
-
H 150mm thick walls 18 M² 20,000.00 360,000.00
-
-
-
-
-
-
-
-
-
-
-
To Collection K 2,631,000.00
GUARD HOUSE
4.68
-
-
-
-
-
-
-
-
To Collection K 115,500.00
GUARD HOUSE
Collection
4.12 115,500.00
4.13
4.69
To Summary 115,500.00
Roof
4.70
ITEM EXTERNAL AND INTERNAL WALLS QTY UNIT K T
Plant
CONCRETE WORK
FORMWORK -
-
To soffit; wrot horizontal -
-
G Sides and soffit of beam 6 M2 18,000.00 108,000.00
-
BLOCK WORK (PROVISIONAL) -
-
Precast cement and sand blocks in cement -
mortar (1:4) filled with concrete (grade 15/40) -
-
H 200mm thick walls 56 M² 20,000.00 1,120,000.00
-
-
4.71
-
TO COLLECTION 1,758,000.00
GUARD HOUSE
COLLECTION
4.15 1,758,000.00
4.16
4.72
To Summary 1,758,000.00
GUARD HOUSE
PLANT
CONCRETE
4.73
To Collection 126,040.00
GUARD HOUSE
4.74
To Collection 105,000.00
GUARD HOUSE
Door frames
4.75
-
To Collection 158,500.00
GUARD HOUSE
COLLECTION
4.17 126,040.00
4.18 105,000.00
4.19 158,500.00
4.76
To Summary 389,540.00
GUARD HOUSE
4.77
To Summary 97,000.00
GUARD HOUSE
4.78
ITEM WALL FINISHES QTY UNIT K T
Plant
EXTERNAL WALLS
PLASTERWORK
Pointing
To Collection 108,500.00
4.79
GUARD HOUSE
INTERNAL
PLASTERWORK
-
-
-
-
-
-
-
-
-
4.80
To Collection 248,000.00
GUARD HOUSE
COLLECTION
108,500.00
4.22
4.23 248,000.00
4.81
TO SUMMARY 356,500.00
GUARD HOUSE
Plant
FLOOR FINISHES
4.82
TO SUMMARY 66,500.00
GUARD HOUSE
Plant
CARPENTRY
4.83
To Collection 170,000.00
GUARD HOUSE
Battens
4.84
To Collection 115,500.00
GUARD HOUSE
COLLECTION
4.26 170,000.00
4.27 115,500.00
4.85
TO SUMMARY 285,500.00
GUARD HOUSE
4.86
TO MAIN SUMMARY K 3,981,840.00
GUARD HOUSE
SUMMARY
PAGE NO.
4.87
FENCE, GUARD HOUSE AND GATE - TOTAL CARRIED TO MAIN SUMMARY 34,856,426.00
34,856,426.00
4.88
TB-ISOLATION WARD
A Clear site of all bushes, shrubs and under growth and cutting down trees not M2 3,500 300.00
exceeding 1500mm girth, including grubbing up roots and removing away
from site
B Ditto, trees exceeding 4500mm girth No. 8 20,000.00
C Excavate average 150mm deep to remove vegetable soil; wheel and remove M2 3,500 450.00
from site.
D Mass excavation to reduce levels commencing from stripped level not M3 5,250 2,500.00
exceeding 1.5m deep; deposit in temporary spoil heaps on site.
E Ditto, 1.5 to 3m deep M3 2,625 2,500.00
F Ditto, 3 to 4.5m deep M3 1,313 2,500.00
G Load and cart away surplus excavated material from site. M3 9,188 2,500.00
PRECAST CONCRETE heavy duty paving blocks or any other equal and
approved : quadblock pattern.
J 80 mm Thick concrete block size 205 x 110 mm laid on falls and including 50 M2 350 16,000.00
mm thick sand bed, allow for compaction, rolling and vibration, spread and
brush into joints and compact.
CARRIED TO SUMMARY K
Dished Drain
A 675mm Girth blockwork Channel drain, rendered (15mm thick 1;4 cement
and sand) on sides, laid to falls on 50mm thick concrete slab and include
50mm thick sand bed, include for excavations and disporsal of surplus spoil M 188
as required
15,000.00
B Drain size 500 x 400 mm, average depth internally
comprising half brick sides and brick on base, laid to
falls and including 13 mm cement and sand (1:4) M 72 15,000.00
rendering to all internal surfaces and including all
excavations and disposal
Channel Drains
CARRIED TO SUMMARY K
CONCRETE WORK
REINFORCEMENT
Fabric; BS 4483
FORMWORK
Sawn Formwork;
CARRIED TO SUMMARY K
CONCRETE WORK
CARRIED TO SUMMARY K
TRENCH EXCAVATIONS
PIPEWORK
110 mm Diameter class 4 uPVC pipe, having socketed "O" ring joints in the
C running length, laid on and including 50mm sand blinding in trench M 205 1,500.00
MANHOLES
14 NO. MANHOLES
F Excavate pit from reduced level for manhole bases 0-1500mm deep m3 12 2,000.00
CONCRETE WORK
25N/MM2/20MM AGGREGATE
J Ditto, in benching average 200mm thick with steep slopes to channels and
branches in bottom of manhole finished with 15mm cement, lime and sand
(1:1:6) rendering, trowelled smooth m2 9 30,000.00
CARRIED TO COLLECTION K
SAWN FORMWORK
SUNDRIES
C Form 450 x 600 mm opening in 125 mm slab, include for edge formwork No 14 20,000.00
REINFORCEMENT
D Hard drawn mild steel fabric reinforcement, Ref A142 weighing 2.22kg/m2 in
slabs M2 15 4,500.00
BLOCKWORK
PLASTERWORK
H Build in end of 110 mm diameter pipe to one block wall and make good
rendering one side No 23 3,000.00
METALWORK
I Galvanised malleable cast iron step to BS 1247 with 125mm tail and build
into block side of manhole No 28 60,000.00
J Medium duty manhole cover and frame (BS 497, Table 6, GradeB) 450 x
600mm, including bedding frame in cement mortar (1:3) and seal cover in
heavy grease No 14 60,000.00
CARRIED TO COLLECTION K
A Excavate pit from reduced level for septic tank 0-1500mm deep M3 13 3,000.00
CONCRETE WORK
F Ditto in benching, average 200 mm thick, with steep slopes to channels and
branches, laid to falls, steel trowelled smooth, including a neat and even joint
to edge of channels and branches M2 1 20,000.00
SAWN FORMWORK
REINFORCEMENT
J
Hard drawn mild steel fabric reinforcement, A142 weighing 2.22kg/m2 in slab M2 7 4,500.00
CARRIED TO COLLECTION K
SUNDRIES
A Form 450 x 600 mm opening in 125mm slab, including for edge formwork No 3 12,000.00
BLOCKWORK
PLASTERWORK
METALWORK
PIPEWORK
CARRIED TO COLLECTION K
SOAKWAY PIT
CONCRETE WORK
REINFORCEMENT
SUNDRIES
CARRIED TO COLLECTION K
BLOCKWORK
METALWORK
FRENCH DRAINS
PIPEWORK
CARRIED TO COLLECTION K
SUNDRIES
CARRIED TO COLLECTION
COLLECTION Page
No
5.5
5.6
5.7
5.8
5.9
5.10
5.11
CARRIED TO COLLECTION K
SUMMARY
Item EXTERNAL WORKS
Page
No
K t
-
-
1,050,000.00
160,000.00
1,575,000.00
13,125,000.00
6,562,500.00
3,281,250.00
22,968,750.00
-
3,150,000.00
4,200,000.00
5,600,000.00
-
-
61,672,500.00
K t
2,820,000.00
-
-
1,080,000.00
-
-
-
-
-
-
-
-
-
-
-
1,605,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
5,505,000.00
K t
-
171,000.00
-
-
-
427,500.00
-
-
570,000.00
-
-
570,000.00
-
-
-
-
-
-
-
-
1,660,000.00
-
1,660,000.00
-
-
-
-
-
-
-
-
3,000,000.00
-
-
-
-
-
-
-
-
1,687,500.00
-
-
-
-
-
-
-
700,000.00
-
-
-
-
1,660,000.00
-
930,000.00
-
-
-
12,437,500.00
K t
3,020,000.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
3,020,000.00
K t
205,000.00
-
-
205,000.00
-
-
-
307,500.00
-
228,000.00
-
132,000.00
-
-
-
-
-
-
-
24,000.00
-
-
-
9,000.00
-
27,000.00
-
-
-
-
-
-
300,000.00
-
270,000.00
-
-
1,707,500.00
K t
270,000.00
-
217,000.00
-
-
-
280,000.00
-
-
-
67,500.00
-
-
-
-
-
-
-
774,000.00
150,500.00
-
52,500.00
-
69,000.00
-
-
-
1,680,000.00
-
840,000.00
-
-
-
-
4,400,500.00
K t
39,000.00
-
10,000.00
-
-
-
-
-
-
45,000.00
-
-
-
-
-
-
120,000.00
-
120,000.00
-
20,000.00
-
140,000.00
-
-
-
-
-
150,000.00
-
-
-
126,000.00
-
-
-
31,500.00
-
-
-
-
-
-
801,500.00
K t
36,000.00
-
-
-
-
-
-
300,000.00
-
-
-
-
52,500.00
-
-
10,500.00
-
-
18,000.00
-
-
-
-
480,000.00
-
-
-
-
180,000.00
-
-
-
-
-
-
36,000.00
-
-
12,000.00
-
-
-
-
-
-
-
1,125,000.00
K t
-
21,000.00
-
3,000.00
-
48,000.00
-
-
-
-
-
-
24,000.00
-
-
-
-
-
-
60,000.00
-
100,000.00
-
-
-
90,000.00
-
-
31,500.00
-
-
-
-
22,500.00
-
-
-
-
3,500.00
-
-
12,000.00
-
-
-
-
-
415,500.00
K t
216,000.00
-
-
-
-
-
-
60,000.00
-
-
-
-
-
-
-
156,000.00
-
39,000.00
-
-
-
-
-
-
165,000.00
-
-
-
-
27,000.00
-
-
-
-
180,000.00
-
-
-
-
-
-
-
843,000.00
K t
100,000.00
100,000.00
4,400,500.00
801,500.00
1,125,000.00
415,500.00
843,000.00
100,000.00
7,685,500.00
K t
61,672,500.00
5,505,000.00
12,437,500.00
3,020,000.00
7,685,500.00
90,320,500.00
PREPARATION
A Clear site of all rubbish ,concrete materials ,rubbles 2,100 M² 600.00 1,260,000.00
stones and any unwanted material in all planting areas -
-
Levelling -
B Break all soil and clods and rake it out to 1,100 M² 600.00 660,000.00
make fine levels. -
C Trimming sides of excavations to slope 50 M² 600.00 30,000.00
-
Top Soil -
-
D Supply fertile top soil to all cultivated grounds using -
using a 7 tonne lorry / tipper 4 Trip 150,000.00 600,000.00
-
E Thoroughly apply and mix top soil average 100mm deep -
to all cultivated grounds then level back the soil. 4 Trip 100,000.00 400,000.00
-
Manure (Provisional) -
-
F Provide well decomposed composite or dung manure
average 50mm deep using a 7 tonne lorry 4 Trips 100,000.00 400,000.00
to all cultivated areas.
G Thoroughly apply and mix to all planting areas including areas 4 Trip 100,000.00 400,000.00
for lawn,shrubs and trees
6.115
ITEM GRASS (LAWN) QTY UNIT RATE AMOUNT
LAWN (Provisional)
-
SUNDRIES -
-
D Lawn Maintenance until it is fully established by replanting 6 Month 300,000.00 1,800,000.00
dead grass, watering,weeding,fertilizer application and mowing. -
-
WATER BILLS (Provisional) -
E Provide for monthly water bills used for 6 Month 300,000.00 1,800,000.00
Lawn irrigation. -
6.116
ITEM TREES QTY UNIT RATE AMOUNT
A EXCAVATION (Provisional)
Excavate holes of not less than 10000mm² and 112 No 6,000.00 672,000.00
not less than 1000mm deep for tree planting
DISPOSAL (Provisional)
TREES (Provisional)
SUNDRIES
6.117
ITEM PASTURE PLOTS QTY UNIT RATE AMOUNT
EXCAVATION
PASTURE PLANTS
E SUNDRIES
Pasture plants maintenance, as per 6 Month 300,000.00 1,800,000.00
Scope of Works and Technical Specifications
4,620,000.00
Total carried to Collection Page
6.118
ITEM SHRUBS AND HERBACEOUS PLANTS QTY UNIT RATE AMOUNT
EXCAVATION
D SHRUBS
Provide and plant shrubs according
to specifications
E SUNDRIES
Shrubs and Herbaceous plants maintenance, as per 6 Month 300,000.00 1,800,000.00
Scope of Works and Technical Specifications
2,325,000.00
Total carried to Summary Page
6.119
ITEM SUMMARY PAGE NO.
6.120
SUMMARY 20,066,000.00
6.121
Item PRIME COST SUMS AND PROVISIONAL SUMS Unit Qty Rate K t
PROVISIONAL SUMS
7.1
BILL NO.1 - ENVIRONMENTAL, SOCIAL, HEALTH AND SAFETY MANAGEMENT (ESHS)
Induction Training
Firefighting training
ESHS12 Allowance for the one carrying the talk Lump sum 500000
CARRIED TO COLLECTION
4,000,000.00
8.2
COLLECTION
Page No.
8.1 4,000,000.00
8.2 4,000,000.00
8.3 10,000,000.00
8.4
TB-ISOLATION WARD
Page
No.
SUB-TOTAL K
MAIN SUMMARY
TB-ISOLATION WARD
K t
5,500,000.00
190,104,300.00
34,856,426.00
90,320,500.00
20,066,000.00
2,000,000.00
18,000,000.00
360,847,226.00
54,127,083.90
414,974,309.90
68,470,761.13
4,149,743.10
487,594,814.13
MAIN SUMMARY