Contract Name: Construction of a Classroom Block and 2no. VIP Latrines at Ngozi Primary school in Traditional
Authority Chadza
Contract No.: MW-LLDC-412295-CW-RFB
NGOZI CLASSROOM BLOCK SUMMARY
DESCRIPTION
PRELIMINARY AND GENERAL ITEMS- CONTRACTOR'S MOBILIZATION AND
ESTABLISHMENT ON SITE
CLASSROOM BLOCK
Subtotal
ary school in Traditional
AMOUNT (MK)
-
-
Contract Name: Construction of a Classroom Block and 2no. VIP Latrines at Ngozi Primary school in Traditional Authority
Chadza
Contract No.: MW-LLDC-412295-CW-RFB
B100 General
Bills of Quantities
These Bills of Quantities must not be used for the purpose of ordering
materials and no liability whatsoever shall be accepted by the Employer
for any loss or expense incurred in this respect.
A Provide for all plantand equipment necessary for the proper execution of
the Works comprising:-
(iv) The contractor shall allow for control of water during construction LS 1 -
Provide for all necessary watching and lighting and take general security
measures to safeguard the Works, materials and plant, including sub- LS 1 - -
contractor’s property, against damage and theft.
The Contractor shall provide, erect, paint, letter as required and maintain,
in a position approved by the Supervising Officer, a project sign board,
size 1.850 x 4.050 metres overall. The wording permitted on the sign
board shall be only that which is specifically authorized by the
Supervising Officer. No other boards or signs, other than those bearing no 1 -
warnings, shall be allowed on or adjacent to the site unless authorised by
the Supervising Officer. All signs and notice boards shall be removed and
disturbed areas made good upon completion of the works. The sign
board shall be as per the drawing provided.
D Temporary Buildings
(i) Weatherproof, dry floored storage space for materials and equipment month 4 -
-
(ii) Suitable office accommodation for site agent, foreman and other
month 4
supervisory staff
The Contractor shall make his own arrangements for any temporary living
accommodation required for his workpeople and shall abide by all
national and local regulations in connection therewith.
The contractor shall make available at his own expense as necessary all
general goods and timber on the like for approval as required by the
Supervising officer to ensure that such goods and materials comply with
their specifications and he shall pay all costs in connection with any
necessary testing thereof except testing charges only of successful tests
which shall be offset against the provisional sum included hereunder
F General Scaffolding
Provide and erect all scaffolding including all stages, trestles, planks,
guard rails, barrow runs and the like required for the execution of the
LS 1 -
Works and maintain, alter and adapt as necessary and remove when no
longer required.
The Contractor shall provide clean, fresh water, free from chemical or
organic impurities or other deleterious matter, for use on the Works,
including that required by Sub-contractors, pay all charges in connection
LS 1 -
therewith, provide all temporary storage, plumbing services, connections
and the like and clear away and make good upon completion of the
Works.
The Contractor shall be responsible for the adequate drying out of the
Works and for maintaining them at a suitable temperature and humidity
until handed over.
(I) Remove all rubbish and debris from the site both as it accumulates
from time to time and upon completion of the Works and shall not bury or LS 1 -
otherwise conceal the same upon the site.
(ii) Clean the Works internally and externally upon completion to the -
satisfaction of the Architect/ Supervising Officer including all glazing and LS 1
sanitary fittings
A Protect all trees, shrubs, etc designated for protection by the Supervising
Officer or his representative. The Contractor shall be liable for a payment
of liquidated damages of K5,000.00 for any tree and K1000.00 for any
shrub, which, as a result of the execution of the Works, sustains harmful
damage or is removed without the prior consent of the
Architect/Supervising Officer.
(i) The contractor shall replace all tress cut with permission from the No 5 -
supervisor
(ii) The contractor shall plant new trees on a place directed by the
-
'supervisor' as specified by in the ESMP No 50
(i) All quarries and borrow pits for the provision of materials necessary for
the construction of the works shall be made good upon completion of the LS 1 -
project
Provide for complying with all safety, health and welfare regulations
pertaining to all work- people (including those of all sub-contractors)
employed on the site and for duly observing in full the requirements of the
Factories Act as it relates to construction sites. Such facilities as the
Contractor is required to provide to conform with the foregoing shall be
cleared away and disturbed areas made good upon completion of the
Works.
(ii) Provision of signage to warn the general public about the construction
-
activities happening on site No 8
EXCAVATION
Disposal (provisional)
H 150 mm wide 10 m1 -
1 Sand blinding
Ant treatment
To Collection -
Sundries
E Column bases
Sawn formwork
To Collection -
Reinforcement
Movements joints
BLOCKWORK (PROVISIONAL)
PLASTERWORK (PROVISIONAL)
To Collection -
G 115mm Walls
CONCRETE WORK
Reinforced vibrated in-situ concrete
(Class 21N/mm2/ 20mm)
Sawn formwork
B Sides and soffit of beam 80 m2 -
Reinforcement
C 6mm diameter mild steel rod reinforcement links at 250mm spacing 90 kg -
Movement joints
Sundries
A 28 Gauge IBR chromadeck sheets laid with one flutes side laps and
350mm minimum end laps, fixed to timber purlins
with and inculding roofing nails (purlins generally at
1200mm centres). All fixings to be complete with 285 m2 -
flat galvanised steel washers
E Roof trusses
Framed sawn softwood timber roof trusses fabricated
at ground level and hoisted approximately 3650mm
above ground level and spaced at 1300mm centre to centre
Metal work
M On roof sheetings m2 -
To Collection
SUBTOTAL FOR ROOF TO SUMMARY -
CONCRETE WORK
A Precast vibrated concrete (Class 21N/mm2/10mm)
bedded, jointed and pointed in mortar (1:3)
100 x 190 x 970mm long window cill, splay rebated once grooved
and two edges chamfered, finished fair on all exposed
surfaces and built into blockwork 2 No -
METAL WORK
970x1320mm Purpose made metal window manufactured from pressed steel to suit 200mm
thick cement block wall complete with cill 160mm wide, the hole filled with 20x3mm flat 10 No. -
C vertical bars, 173mm diameter rings all welded together and to frame
D D7H Steel window frames with A4B burglar bars complete with handles and sliding stays 2 No -
F
970x2100mm Purpose made door fabricated from 45x5mm frame the hole field with
20x3mm flat vertical bars, 173mm diameter rings all welded together and to frame complete
with frame fabricated from 1,2mm pressed steel to suite 200mm wall 2 No. -
I Standard size steel door frame 200mm wide complete with butt hindges 2 No -
IRONMONGERY
K 75mm padlocks 2 No -
GLAZING
Clear glass sheets
O 4mm Thick clear plate glass and glazing to metal windows with and including glass putty 30 m2 -
To Collection -
C Rendered walls 92 m2 -
D Rendered walls 92 m2 -
Pinboards
A 1200X1200mm PINBOARDS including 25 x 25mm hard wood framing 2 no -
Chalkboard
C 15mm cement and sand plaster in 1:4 mix -
5000x1200mm chalkboard with 75 x 50mm grooved hard wood lipping fitted at the bottom 2 no -
of chalkboard as duster holder
SHELVING
D GENERAL JOINERY
Wrot softwood
50 x 50mm styles 36 m -
H 50 x 50mm framing 72 m -
I Divisions
20mm thick blockboard 4 m2 -
J Shelves
300mmx20mm thick blockboard; lipped all round 12 m2 -
To Collection -
C Prepare and apply one thinned coat pink primer then undercoat and , two coats 12 m2 -
high gloss paint on 20mm block board shelves 100-300mm girth
D Prepare and apply one thinned coat pink primer then undercoat and , two coats 108 m2 -
high gloss paint on 50x50 mm soft wood framings and styles
To Collection -
PIN BOARDS, CHALKBOARDS AND SHELVES TO SUMMARY -
EXTERNAL WORKS
STORMWATER DRAINAGE
Dished Drains
Sundries
2 SUPERSTRUCTURE -
3 ROOF -
5 WALL FINISHES -
6 FLOOR FINISHES -
8 EXTERNAL WORKS -
SUB Total -
Contract Name: Construction of a Classroom Block and 2no. VIP Latrines at Ngozi Primary school in Tradit
Authority Chadza
EXCAVATION
Ant treatment
CONCRETE WORK
Reinforcement
Wrot formwork
Floor
INTERNAL PLASTERWORK
ROOFING
Roof Coverings
CARPENTRY
F 50 x 150mm Rafter m1 8
G 50 x 100mm Purlins m1 9
Fascia/barge boards
To Collection
1.02
METALWORK
Door frames
DOORS
IRONMONGERY
N Timber door m2 4
To Collection
SOIL SYSTEM SHALL BE 'MARLEY RIGID
PVC'
To Collection
COLLECTION
Page Nos.
1.01
1.02
1.03
1.04
1.05
TENDER AMOUNT
(MK)
- -
- -
- -
- -
- -
-
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
-
- -
- -
- -
-
- -
- -
- -
- -
-
- -
-
-
-
-
-
-
-
-
-
-
-