You are on page 1of 15

SECTION 01 50 00

TEMPORARY FACILITIES AND CONTROLS

1. PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Contractor shall provide, erect, install, maintain, alter as necessary, and remove on
completion or when directed by the Engineer, temporary facilities and as described
in Project Documents and/or specified herein.

B. Contractor shall provide and maintain the temporary accommodation and facilities
for the Owner and the Engineer site offices requirements indicated in this section as
per categories respected to the project site area, any project site category shall be
determined as following:

1. Category C0 for project site area less than 1,500 m2.

2. Category C1 for project site area equal and more than 1,501 m2 and less than
4,000 m2.

3. Category C2 for project site area equal and more than 4,001 m2 and less than
9,000 m2.

4. Category C3 for project site area equal and more than 9,001 m2 and less than
20,000 m2.

5. Category C4 for project site equal and more than 20,001 m2 and less than 50,000
m2.

6. Category C5 for project site equal and more than 50,001 m2.

1.2 TEMPORARY ROADS

A. Contractor shall prepare and maintain such temporary roads as may be


necessary from the site to the nearest road and also within plot. Roads shall be
positioned strictly in accordance with the Engineer’s instructions and the
Contractor shall reduce or control any dust nuisance by spraying with water.

B. Contractor shall satisfy himself as to the location and nature of the proposed
access routes to site and shall be responsible for preventing any damage
whatsoever to adjacent property and vegetation and keeping the access road free
from debris at all times.

1.3 TEMPORARY SERVICES

A. General:

1. Contractor shall make his own provisions with prior approval of the
Engineer, or he shall perform necessary works required in conjunction with
Project Documents.

Ministry of Interior Headquarter 01 50 00-1 Temporary Facilities and Controls


Buildings – Jeddah
2. Contractor shall bear costs related to installation, connection, maintenance
and removal of all temporary services and consumption of water and
electricity during the entire duration of Project.

B. Temporary Water:

1. Contractor shall supply in sufficient quantity all necessary potable and other
water for construction purposes for other trades at a point within a
reasonable distance from buildings being constructed. Contractor shall
make arrangements and pay charges for water service installation,
maintenance, and removal thereof, and pay cost of water for other trades.

2. When permanent water supply and distribution system has been installed, it
may be used as the source of water for construction purposes, provided
that the Contractor obtains the written approval of the Engineer, and
assumes full responsibility for the entire water distribution system, and pays
all cost of operation and maintenance of the system.

3. Temporary pipe lines and connections from the permanent service line,
whether outside or within the building, but necessary for the use of the
Contractor and his subcontractors, shall be installed, protected and
maintained at the expense of the Contractor.

4. At completion of the work or at such time as the Contractor makes use of


the permanent water supply installation, the temporary water service
equipment and piping shall be removed by Contractor at his own expense.

C. Temporary Electricity:

1. Contractor shall make all necessary arrangements for a temporary


electrical service, pay all expenses in connection with the installation,
operation and removal thereof, and pay the costs of electricity consumed by
all trades.

2. In event that site cannot be connected to a local electricity network or where


the available power is insufficient, Contractor shall make his own temporary
provision and maintain such temporary installation until permanent supply is
available and pay for expenses related in connection with such process.

3. A temporary lighting system shall be furnished, installed and maintained by


the Contractor as required to satisfy the minimum requirements for safety
and security. Temporary lighting system shall afford adequate general
illumination to all building areas. Adequate outdoor lighting shall be
provided to illuminate staging, trenches and the like to the satisfaction of the
Engineer, and general illumination throughout adequate for watchmen and
emergency personnel.

4. Temporary equipment and wiring for power and lighting shall be in


accordance with the applicable provisions of governing codes. Temporary
wiring shall be maintained in a safe manner and utilized so as not to
constitute a hazard to persons or property.

5. When the permanent electrical power/lighting systems are in an operating


condition, they may be used for temporary power and lighting for
Ministry of Interior Headquarter 01 50 00-2 Temporary Facilities and Controls
Buildings – Jeddah
construction purposes, provided that Contractor obtains written approval of
the Engineer and shall assume full responsibility for the entire power and
lighting systems, and pays for operation and maintenance of the systems.

6. At completion of construction work, or at such time as the Contractor makes


use of permanent electrical equipment and devices, temporary electricity
services shall be removed by the Contractor at his own expense.

D. Waste Disposal:

1. Contractor shall make such temporary provisions as may be required in


order to dispose of any chemicals, fuels, oils, greases, bituminous
materials, waste and soil waste and the like without causing pollution to
either the site or the environment.

2. Disposal of any materials, wastes, effluent, garbage, oil, grease, chemicals


and the like shall be in areas specified by the concerned local authority or
municipality proposed by Contractor and subject to approval of the
Engineer.

3. If any waste material is dumped in unauthorized areas, Contractor shall


remove material and restore areas to condition of adjacent undisturbed
area. If necessary, contaminated ground shall be excavated, disposed of
as directed by the Engineer, and replaced with suitable fill material,
compacted, and finished with topsoil at the expense of the Contractor.

E. Fire Protection:

1. Contractor shall provide and maintain adequate fire protection in the form of
barrels of water with buckets, fire bucket tanks, fire extinguishers, or other
effective means of extinguishing fire, ready for instant use, distributed
around the project and in and about temporary inflammable structures
during construction of the works. Gasoline and other flammable liquids shall
be stored in and dispensed from safety containers approved by the
Engineer and storage shall not be within buildings. Torch-cutting and
welding operations performed by Contractor shall have the approval of the
Engineer before such work is started and a chemical extinguisher is to be
available at location where such work is in progress. Contractor shall follow
instructions and specifications of the Civil Defense Department.

F. Telephone and Fax:

1. Contractor shall immediately after receiving the Letter of Acceptance, install


telephone exchange at site office and one extension for each personnel of
the Owner or the Engineer and shall provide required telephone and fax
lines for Owner Representative and the Engineer’s offices. The Contractor
shall provide handsets for all telephone extensions, including executive sets
for Owner Representative Office. Provide fax lines including fax machine for
Owner Representative and the Engineer site offices.

2. Contractor shall be responsible for payment of all installation charges and


periodic accounts (invoices) for all telephone and fax lines during
construction period and up to substantial handover.
Ministry of Interior Headquarter 01 50 00-3 Temporary Facilities and Controls
Buildings – Jeddah
3. In case of no availability of telephone lines through PTT, the Contractor
shall buy direct lines for Owner Representative and the Engineer or provide
mobile lines.

4. Contractor shall provide and install the required numbers and quantities of
telephone and fax lines, handsets, fax machines and system equipments
indicated in the following table:

Table A: Site office Telephone & fax requirements:

Site Telephone System Project Category


S.N.
Requirements C0 C1 C2 C3 C4 C5
Telephone exchange (one
1 extension for each Owner and - 1 1 1 1 1
Engineer personal)
No. of direct telephone lines for
2 - 1 1 2 2 3
the Owner.
No. of direct telephone lines for
3 - 1 1 1 1 1
the Engineer .
No. of Mobile telephone for the
4 - - 1 2 2 3
Owner
No. of direct fax lines including
5 - 1 1 1 2 2
fax machine for the Owner
No. of direct fax lines including
6 - 1 1 1 2 2
fax machine for the Engineer
No. of executive sets for the
7 - - 1 1 1 1
Owner
No. of executive sets for the
8 - 1 1 1 1 1
Engineer
No. of telephone sets for Owner’s
9 - 6 7 8 12 13
site supervision team.
No. of telephone sets for
10 - 9 16 20 25 30
Engineer’s site supervision team
* Project category shall be indicated from clause 1.1-B of this section.
* All item quantities mentioned in above table by Nos., unless otherwise indicated.

1.4 TEMPORARY ACCOMMODATION AND FACILITIES

A. General:

1. Location, construction, operation, maintenance and removal of site offices,


storage facilities and other temporary buildings of all persons or parties
within perimeter of site, operating or associated as Sub-Contractors to
Contractor shall be subject to approval of Engineer. Contractor shall submit
to Engineer, prior to commencement of any temporary installations, plans
showing proposed position of site offices, storage and buildings of
temporary nature.

2. All habitable rooms shall be properly insulated, shall have dust-sealed


windows with sun protection and insect screens, and shall be equipped
with electric lights, air conditioning and/or mechanical ventilation, and the

Ministry of Interior Headquarter 01 50 00-4 Temporary Facilities and Controls


Buildings – Jeddah
supporting facilities shall provide the necessary hot and cold water, sewer
and electrical facilities, and maintenance, all to the satisfaction of the
Engineer.

B. The Engineering Site Office

1. The Contractor shall provide and maintain for the entire duration of the
project such administrative and supporting facilities as required for the sole
use of the Engineer and his staff. The building/s may be pre-fabricated or
conventionally constructed and all rooms shall be sufficiently dimensioned
to include the essential furnishings. The temporary offices shall be
available for use not later than one (1) month after the date of the site
handing over.

2. The Engineering site office shall consist of at least the required rooms
spaces, functions, and facilities which shall be provided as indicated in the
following tables B & C:

Table B: Owner site office spaces requirements

Site Office Spaces Project Category


S.N.
Requirements C0 C1 C2 C3 C4 C5
Office 48 m2 floor area,
connected to Meeting Room for
25 persons and Reception and
1 - - 1 1 1 1
Waiting Area; private toilet. Room
shall have a medium size
refrigerator
Office 32 m2 floor area,
connected to Meeting Room for
15 persons and Reception and
2 - 1 1 1 1 2
Waiting Area; private toilet. Room
shall have a medium size
refrigerator
Conference Room 60 m2 floor
area, for drawing review and
3 progress meetings, to - - 1 1 2 2
accommodate 25 persons;
equipped with furniture.
4 Room 20 m2 floor area 1 2 2 4 8 8
5 Common toilet 1 1 1 1 2 2
6 Secretary Room - - 1 1 2 2
7 Storage room 15 m2 - 1 1 2 2 2
8 Toilets for visitors & site persons 3 6 10 20 25 30
* Project category shall be indicated from clause 1.1-B of this section.
* All item quantities mentioned in above table by Nos., unless otherwise indicated.

Table C: The Engineer’s site office spaces requirements

Site Office Spaces Project Category


S.N.
Requirements C0 C1 C2 C3 C4 C5
1 Office 48 m2 floor area, - - 1 1 1 1

Ministry of Interior Headquarter 01 50 00-5 Temporary Facilities and Controls


Buildings – Jeddah
connected to Meeting Room for
25 persons and Reception and
Waiting Area; private toilet. Room
shall have a medium size
refrigerator
Office 32 m2 floor area,
connected to Meeting Room for
15 persons and Reception and
2 - 1 1 2 3 4
Waiting Area; private toilet. Room
shall have a medium size
refrigerator
Conference Room 60 m2 floor
area, for drawing review and
3 progress meetings, to - - 1 1 1 2
Accommodate 25 persons;
equipped with furniture.
4 Room 20 m2 floor area 2 4 8 12 16 20
5 Conference room for 15 persons - 1 1 2 3 4
6 Reception room, floor area - 15 m2 15 m2 15 m2 20 m2 25 m2
Telephone room, floor area 10
7 - 1 1 1 1 1
m2
8 Storage, floor area 6 m2 1 - - - - -
9 Storage, floor area 10 m2 - 1 2 3 4 4
10 Kitchen, floor area 6 m2 1 - - - - -
11 Kitchen, floor area 10 m2 - 1 2 3 3 4
12 Toilets for ( ) persons 3 10 20 40 50 60

* Project category shall be indicated from clause 1.1-B of this section.


* All item quantities mentioned in above table by Nos., unless otherwise indicated.

All rooms shall have a minimum height of 2.45 m. construction shall be approved
by the Engineer prior to erection. The Contractor shall provide water, electricity,
AC, telephone and drainage system and all such supplies shall be continuously
furnished throughout the construction period. Contractor shall be responsible to
provide adequate and sufficient services for the Engineer and his staff including
the messenger / office boy acceptable to the Engineer in full time basis and shall
keep the building in clean conditions. Contractor shall supply to the satisfaction
of the Engineer the necessary office equipment and furniture, i.e. telephone
exchange, telephone sets, fax machine, electrical typewriter English and Arabic,
desk calculators, advanced photocopy machine, chairs, desks, tables, filing
cabinets, coat hooks, etc.

3. Communications Facilities: The Contractor shall provide each room with a


telephone connection box. The telephone system shall be provided with a
medium size private telephone system, extension lines and facilities for
internal links including night answering with an operating. The whole
installation shall be maintained in good order and the contractor is
responsible for providing the necessary lines, extension lines and facilities
for internal links as mentioned in table A (Telephone and fax requirements).

4. The Contractor is responsible for employing the personnel (English / Arabic


speaking) to operate the system at full time basis and shall be responsible
of paying all the costs for running and maintain the system during the

Ministry of Interior Headquarter 01 50 00-6 Temporary Facilities and Controls


Buildings – Jeddah
project period.

5. Kitchen Equipment’s: The Contractor shall provide the kitchen equipment


as per the list indicated in the following table D:

Table D: Site office kitchen equipment

Site Office Kitchen Equipment Project Category


S.N.
List C0 C1 C2 C3 C4 C5
1 Electrical cooker with 2 hot plates 1 1 1 1 1 1
Stainless steel double sink-unit
2 with one drainer, warm and cold 1 1 1 1 1 1
water including supply of linen
3 Wooden Kitchen cabinet units 1 1 1 1 1 1
Tea and coffee service sets for
4 6 10 10 15 15 15
( ) persons
5 Refrigerator, 150 liter 1 1 1 1 1 1
6 Electrical Coffee percolator - 1 1 1 1 1
7 Water cooler - 1 1 1 1 1

* Project category shall be indicated from clause 1.1-B of this section.


* All item quantities mentioned in above table by Nos., unless otherwise indicated.

6. Office furniture and equipment : Contractor shall furnish all rooms and office
with the suitable furniture and equipment for the offices use as per the list
to be submit for the Engineer approval and as indicated in the following
table E:

Table E: Site office furniture and equipment

Site Office Furniture and Project Category


S.N.
Equipment List C0 C1 C2 C3 C4 C5
1 Metal desk 156 x 78 x 75 cm 3 16 26 39 55 67
Complete desk set of good
quality as selected by the Owner
Representative; desk size not
2 1 1 1 2 2 3
less than 200 x 100 x 75 cm,
complete with desk return, high
back chair and book shelf.
3 Good qualify Sofa set - 1 1 2 3 4
Variable height swivel-chair with
4 3 16 26 40 55 70
castors
5 Metal table 156 x 78 x 75 cm 1 4 8 16 20 24
Meeting table with chairs for 15
6 - 2 2 3 4 6
persons
7 Visitor metal chair 4 6 10 15 20 25
Combined metal desk and
8 1 1 1 2 3 3
typists, table of suitable size.
Adjustable shelving cabinet size
9 2 4 8 16 20 24
120 x 200 x 42 cm.
10 Metal Drawings racks set 1 3 5 10 15 20
11 Wardrobe for coats - 1 1 2 2 3
12 Safety helmets 10 20 30 45 60 70
Ministry of Interior Headquarter 01 50 00-7 Temporary Facilities and Controls
Buildings – Jeddah
13 Adjustable metal shelve 100 cm 2 4 8 16 20 24
14 Blackboard 1 1 2 3 3 4
15 Notice Board 1 2 2 3 4 4
16 Fiberboard fixed to wall in offices. 1 2 4 8 12 16
Dry fire-extinguishers, 4.5 kg
17 4 10 22 32 44 50
capacity

* Project category shall be indicated from clause 1.1-B of this section.


* All item quantities mentioned in above table by Nos., unless otherwise indicated.

Contractor shall furnish and supply the offices with all the necessary office
supplies of adequate quantities as directed by the Engineer during the
entire project duration.

7. Special equipment: The Contractor shall supply the Engineer in addition to


what mentioned at previous clauses with the special equipments list
indicated in the following table F:

Table F: Site Office Special Equipment

Site Office Special Equipment Project Category


S.N.
List C0 C1 C2 C3 C4 C5
Advanced photocopy machine
A3, and A4 sizes with
1 1 1 2 3 4 4
enlargement and reducing
facilities.
Advanced Automatic SLR
camera, 35 mm with
2 interchangeable lenses standard, - 1 1 1 2 2
wide & tele-photo complete with
synchronized flash.
3 Instant Camera - 1 1 1 2 2

* Project category shall be indicated from clause 1.1-B of this section.


* All item quantities mentioned in above table by Nos., unless otherwise indicated.

8. Computers and Accessories :

a. Contractor shall supply computers, printers and other related


accessories and shall be purchased in the Owner name and shall
become the Owner property and shall be handed over to Owner
anytime they request. However, Contractor shall be responsible to
maintain them in perfect order throughout the construction period up
to substantial handover.

b. Computers, printers and other related accessories shall be as


selected by Owner Representative from high-end models available at
the time of purchase.

c. Computers and Accessories shall be provided as indicated in the


following table G:

Table G : Site Office computers and accessories

Ministry of Interior Headquarter 01 50 00-8 Temporary Facilities and Controls


Buildings – Jeddah
Site Office Computers and Project Category
S.N.
Accessories List C0 C1 C2 C3 C4 C5
Server:
-2.5 GHz processor, core 2
due, RAM 4GB (or
whatever is the highest
Intel CPU available for
PC’s on the project
commencement date).
-Support for up to four (4)
symmetrical processors.
-Dual-processor installed.
-RAID Technology Support.
-1024 MB RAM.
1 - 1 1 2 4 4
-320 GB Hard Disk.
-52-Speed CD-ROM Drive.
-Ultra-SCSI Fast and Wide
Controller.
-19” Monitor LCD.
-2-100 MB Network Interface
Card with RJ-45 and BNC
Connector.
-Tape Backup Device (Tape
Capacity: 16 GB
Uncompressed).

Desktop PC’s:
-2.5 GHz, core 2 due, RAM 4
GB.
-1024 MB RAM.
-256 MB Video Card.
2 -320 GB Hard Disk Storage. 2 14 23 33 45 54
-52-speed CD-ROM.
-17”-LCD Monitor
-10/100 MB Network
Interface Card with RJ-45
and BNC Connector.
A0 Plotter :
-Res: 1200 dpi mono, 1200
dpi color.
3 - 1 1 1 2 2
-512 MB RAM
-Jet Direct Network Interface
Card.
Laser Jet A3 Printer HP or equal:
-1200 dpi, 30 ppm
-512 MB Printer Memory.
4 -Prints up to A3 paper size. - 1 2 3 3 4
-Jet Direct Network Interface
Card.
-A4 and A3 Trays.
Laser Jet A4 printer HP or equal:
5 -1200 dpi. 1 1 2 3 3 4
-512 MB Printer Memory.
Ministry of Interior Headquarter 01 50 00-9 Temporary Facilities and Controls
Buildings – Jeddah
-A4 Tray.
-Jet Direct Network Interface
Card.
A4 Flatbed Scanner :
6 -600 dpi - 1 1 2 2 2
-1 GB Printer memory.
Uninterrupted Power Supply
7 - 1 1 1 1 1
(UPS) for Server, 1.5 KVA
8 UPS for Workstations, 500 watt 2 14 23 33 45 54

* Project category shall be indicated from clause 1.1-B of this section.


* All item quantities mentioned in above table by Nos., unless otherwise indicated.

9. Software Specifications:

a. General: Software applications mentioned in this section shall be


of latest version available at the time of purchase. Where
applicable, provide both English and Arabic versions of software.
Software shall be purchased in Owner name complete with all
licenses and certification required for legal use of software
packages.
b. Computer Software shall be provided as indicated in the following
table H:

Table H: Computer Software

Project Category
S.N. Computer Software
C0 C1 C2 C3 C4 C5
Server Software
1 Windows NT4.0 Servers with - 1 1 2 4 4
Multi Processor Support
Document Management System
 Allows indexing of files /
documents / AutoCAD
drawings.
2 - 1 1 1 1 1
 Allows linking of
documents to spatial
objects.
Query and search functions.
Latest version available from
3 Windows for workstations 2 14 23 33 45 54
software.
Latest version available for
4 2 14 23 33 45 54
Microsoft Office
Latest version available for
5 2 12 21 29 40 48
autoCAD/
Latest version available for SAP
6 for Windows NT – Structural 1 1 3 4 6 7
Design & Analysis.
Latest version available for PCA
7 Col-Portland Cement Association 1 1 3 4 6 7
Program for Column Design

Ministry of Interior Headquarter 01 50 00-10 Temporary Facilities and Controls


Buildings – Jeddah
* Project category shall be indicated from clause 1.1-B of this section.
* All item quantities mentioned in above table by Nos., unless otherwise indicated.

C. Contractor’s Facilities :

1. The Contractor shall, for his own use, furnish and maintain suitable offices,
stores and auxiliary facilities on the site. The Contractor shall include for
general use the following:

a. Sanitary Facilities: Toilets shall be provided and maintained on site or


as directed by the Engineer. Toilets shall be individually partitioned
and the enclosures provided with lockable doors.

b. First Aid Facilities: The Contractor shall provide adequate first aid
facilities for the joint use of his staff and the Engineer and his
personnel. They shall be made available at no extra cost.

c. Vehicle Parking: The Contractor shall provide a suitable sized car


park shade structure for the Engineer cars and spaces for visitors
cars. The size of car park shade shall be as indicated in the following
table I :

Table I: Size of car park shade

Project Category
S.N. Size of Card Park Shade
C0 C1 C2 C3 C4 C5
Suitable sized car park shade
1 2 6 12 20 25 30
structure for ( ) cars

* Project category shall be indicated from clause 1.1-B of this section.


* All item quantities mentioned in above table by Nos., unless otherwise indicated.

d. Sample Room: The Contractor shall provide as directed by the


Engineer and near the Engineering Office a sample room with
appropriate shelving of the storage of complete set of approved
samples of the project. The Contractor shall make the necessary
modifications to the room as directed by the Engineer.

The Contractor shall provided all skilled labor required for the
installation, operation and maintenance of all laboratory equipment.
The equipment shall be periodically calibrated as directed by the
Engineer. The laboratory shall at all times be available for use by the
Engineer.

D. Labor Camps:

1. A labor camps is not permitted on the site of the works.

2. Any labor camp or accommodation shall be provided for laborers off site and
is expected to be fully in accordance with the laws of the Kingdom; and the
Contractor shall be fully accountable and responsible for ensuring all labor
laws are complied with, and security and the conduct of such men are lawful.

Ministry of Interior Headquarter 01 50 00-11 Temporary Facilities and Controls


Buildings – Jeddah
1.5 TEMPORARY HOISTS AND CHUTES

A. Contractor shall provide, install, maintain and remove materials and personnel
hoists as required for normal use by all trades, and employ only skilled operators
for them. He shall provide necessary guards, signals, protective facilities, safety
devices and the like required for safe operation, provide suitable runways from
hoists to each floor level and roof, and remove all such facilities after they have
served their purpose or when directed by the Engineer.

B. Contractor shall also provide and maintain all temporary ladders, ramps, runways,
chutes, derricks, stairs, and similar items required for the proper execution of the
work and permit the use of such facilities by other contractors, subcontractors or
trades. Hoists and chutes shall be so constructed as to prevent damage, staining
or marring of permanent work.

C. Not materials, rubbish or debris shall be permitted to drop free, but shall be
removed by use of materials hoist and/or fully enclosed rubbish chute.

D. Where required, openings in slabs, walls and partitions shall be provided for
installing large pieces of equipment. Openings shall be closed and/or made good
after the equipment is in place. Structural modification, if required, shall be subject
to prior approval by the Engineer.

1.6 STAGING AND SCAFFOLDING

A. Contractor shall provide, erect and maintain all staging and scaffolding (exterior
and interior) for all trades for their use during the construction of the building.
Staging and scaffolding shall be of approved design, erected and removed by
experienced stage builders and shall have all accident prevention devices
required by government laws.

B. Such staging and scaffolding shall be erected in sufficient time and in a proper
sequence so as not to delay the works. Subcontractors shall schedule and
commence their work so that building progress is not delayed or obstructed once
staging and scaffolding becomes available.

C. The above facilities shall be constructed and maintained in accordance with the
applicable requirements of Government Authorities and designed to comply with
the recommendations of the British Standards CP 97, Parts 1, 2 and 3, as
applicable, and be removed after they have served their purpose or when
directed by the Owner's Representative.

1. 7 TEMPORARY COVERINGS

A. Contractor shall protect finished surfaces, including jambs and soffits of openings
used as passageways or through which materials are handled, against possible
damage resulting from the conduct of work by trades.

B. Adequate protective material shall be laid under all materials stored on finished
surfaces, and shall be laid before moving materials over finished areas.
Wheelbarrows used over such areas shall have rubber type wheels.

C. Finished surfaces, including factory-finished and job-finished items shall be clean


Ministry of Interior Headquarter 01 50 00-12 Temporary Facilities and Controls
Buildings – Jeddah
and not marked upon handing over of building(s) to Owner. Contractor shall,
without extra compensation, re-finish such spaces where surfaces were proved to
have been inadequately protected, and which are damaged.

D. As soon as an area of flooring is finished, it shall be protected by the Contractor


from dirt and damage by covering as necessary with paper or by other approved
method.

E. Waterproofed and roof surfaces shall not be subjected to traffic, nor be used for
storage of material. Where some activity must take place in order to carry out the
work, adequate protection, subject to approval by the Engineer shall be provided.

1.8 TEMPORARY SAFETY MEASURES

A. Contractor shall provide and maintain during the entire contract period all
temporary safety measures necessary for the protection of people, buildings,
structures, pavings, curbs, channels, fences and the like on the site or adjacent
properties, and he shall be solely responsible for any damage to life and property
caused as a result of not having taken adequate precautions against such
damage.

1.9 TEMPORARY SIGNBOARD

A. Provide, erect and maintain on suitable supports and as directed by the engineer
one signboard of minimum size 6 x 3 m giving the names of the Project, the
Owner, the Designer, the Engineer, the Contractor and other required
information.

1.10 TEMPORARY FENCING

A. Provide temporary fencing, 2 m high with lockable gate (s) and adequate access
around the site, constructed in the conformance with the Municipality Regulations
and requirements.

1.11 OWNER TRANSPORTATION

A. The Contractor should provide new cars for the Owner site supervision team
(Employer Representatives) covered by the Contract’s value and with the
following specifications & quantity:

Total Number for


Car Category / Group
Every Category
Number of Cars,
1
Category (A)
Number of Cars,
2
Category (B)
Number of Cars,
2
Category (C)

Ministry of Interior Headquarter 01 50 00-13 Temporary Facilities and Controls


Buildings – Jeddah
Category (A): Japanese Jeep – Toyota Land Cruiser – VXR – Basic or equivalent.
Category (B): Japanese Jeep – Toyota Land Cruiser – GXR – Basic or equivalent.
Category (C): Japanese Jeep – Toyota Prado Basic or equivalent.

“Japanese Jeep, four doors, 4 driving wheels, model of the year during which the
project shall start. Then the ownership of this car will be transferred to the MOI. The
Contractor won’t be responsible for the expenses of fuels, maintenance, insurance &
traffic violations, as its responsibility is limited only for providing the car and the
expenses of transferring its ownership.

1.12 TRAINING COURSES:

The Contractor shall organize and conduct 20 No. training courses in Saudi Arabia for
the Employer’s personnel, and such courses should fulfill the needs of The Employer’s
personnel.
The Contractor shall be responsible for all costs resulted from organizing these courses,
and such costs to be incurred on its total price in the project. The cost of one course
shall be SR 50,000 (Saudi Riyals Fifty thousand)
Employer shall determine the training topics, which will be carefully selected to fulfill the
needs of MOI personnel and to realize integration and full knowledge with all modern
techniques and methods in all different engineering and projects management fields,
Including Building Information Modeling (BIM) for facilities management of the Project
The Contractor shall be responsible for organizing such courses and all related
coordination, procedures and arrangements. The contractor shall be also liable any
delay occurred in courses or non-conducting or any part thereof, and in case of the
Contractor’s failure to conduct one of these courses, the Employer shall have the right
to conduct such courses or any part thereof and then to collect their values directly from
the contractor or shall deduct them from the contractor’s due payments or from those
payments may be due to it later.

2. PART 2 - PRODUCTS

2.1 MATERIALS

A. General: Materials shall be new and approved by the Engineer, and must not
violate requirements of applicable codes and standards.

3. PART 3 - EXECUTION

3.1 GENERAL

A. Maintain systems to assure continuous service.

B. Modify and extend systems as work progress requires.

3.2 REMOVAL

A. Completely remove all temporary facilities, materials, services and equipment


when their use is no longer required.

Ministry of Interior Headquarter 01 50 00-14 Temporary Facilities and Controls


Buildings – Jeddah
B. Clean and repair damage caused by temporary installations or use of temporary
facilities.

C. Restore permanent facilities used for temporary services to specified conditions.

END OF SECTION

Ministry of Interior Headquarter 01 50 00-15 Temporary Facilities and Controls


Buildings – Jeddah

You might also like