Professional Documents
Culture Documents
B.1 Demolition
B.1.1 Schedule and Method
The Contractor shall carry out all demolition work in accordance with
the recommendations of BS 6187, “Code of Practice for Demolition”.
The foregoing provisions shall not prevent the Engineer from requiring
the Contractor to vary his plant or methods at any time during the
execution of the works should the Engineer consider it essential so as
to ensure compliance with the Documents and Specification.
The Contractor shall not vary his plant or method of working, without
obtaining the Engineer’s written approval of such variation.
The Contractor shall be held responsible for the safety of the existing
structure and the sufficiency of all the temporary works.
The Contractor shall provide all necessary protection for the existing
works against the effects of inclement weather and make good any
damage caused to existing works which are not be demolished.
The Contractor shall protect all existing fittings and surfaces, which are
not to be demolished and any damage so caused shall be made good to
the Engineer’s approval at the Contractor’s expense.
B/1
Multipurpose Hall at Manah
B.1.3 Disposal
All materials arising from demolition shall be disposed off as directed
by the Engineer. Materials taken off the worksite shall be disposed off
in accordance with the requirements of the Local Municipality and
with the Engineer’s approval.
The Contractor shall take all necessary precautions and care to avoid
interference with and obstruction or damage, in particular through
pollution, to be environment. The Contractor shall repair at his own
expense any damage to the environment resulting from demolition or
disposal of materials.
B.1.4 Permits
Before commencing demolition work the Contractor shall obtain a
work permit from the Municipal Authorities. The Contractor shall
ensure that this permit states that all services have been disconnected.
Instructions on the permit shall be adhered to.
The Contractor shall keep the permit securely on the worksite for
inspection by the Authorities.
B/2
Multipurpose Hall at Manah
B.1.8 Explosives
Explosive and blasting will not be allowed under any circumstances.
B.2 Excavation
B.2.1 Nature of the Ground
The Contractor shall judge for himself the nature of the ground and
shall be fully responsible for ascertaining all necessary information
concerning permanent water table, period of rainfall, flooding of the
site and all matters affecting the excavation and foundation work.
(c) The Contractor shall then set out the work and outline the location
of any existing structure or utility, concealed or exposed, with
reference to the axes of the project. The Engineer will then proceed
to approve or modify the setting out or order the Contractor to
reroute any utility which he deems necessary after obtaining special
permit from the local authorities.
B/3
Multipurpose Hall at Manah
B.2.4 Method of Excavation
Excavation may be carried out by machine or any other method
approved by the Engineer. In soil, excavations shall be taken to within
200 mm of the formation or foundation level and all subsequent
excavation in any section must be carried out by hand not more than
24 hours before the commencement of construction in that section is
approved by the Engineer.
Particular care shall be taken to keep dry, rock and other surfaces
against or upon which concrete may be deposited, and proper
precautions shall be taken to prevent the leaching out of cement or
otherwise damaging unset concrete.
Rock in this context is any material met which is, in the opinion of the
Engineer, of such size or position that it can only be removed by means
of wedges, compressed air or other special plant, or explosives, or if
met in open excavation could not be loosened by bulldozing or ripping.
Boulder rock in this context is any material met with is, in the opinion
of the Engineer, or such size, position or composition that it can only
be removed by means of special equipment but which does not need
breaking up prior to removal.
B/4
Multipurpose Hall at Manah
B.3 Filling
B.3.1 Material for Filling
Material for backfilling shall be selected, graded, hard granular fill free
from clay and deleterious matter and of size not exceeding 75mm, upto
50% passing a 5mm mesh sieve and not more than 20% passing 75
micron sieve. It shall contain less than 0.2% total sulphates and total
soluble salts shall not exceed 2%. The liquid limit shall not exceed 35%
and plasticity index shall not exceed 6%. The uniformity coefficient
shall be atleast 10 and the 10% fines value atleast 100KN. Generally,
material from swamps/marshes, material susceptible to combustion,
stumps/logs and perishable materials, running silt, highly inorganic
clay or silt and slurry or mud and uniformly graded fine sand are
considered as unsuitable for backfilling. Backfilling material shall be
free of vegetable matter and roots. Organic matter content shall be less
than 6% and clay/silty material less than 5%. Quantity of Gypsum shall
be insignificant. Isolated boulders shall not exceed 0.015cum. in size.
B/5
Multipurpose Hall at Manah
B.3.4 Compaction
The equipment employed for compaction such as vibratory compactors
or power rammers or smooth wheeled/pneumatic tyred rollers shall be
of a type with compacting effort as approved by the Engineer and shall
be capable of achieving the specified Degrees of compaction.
Minimum 5 ton roller shall be used.
B/6
Multipurpose Hall at Manah
The Contractor may backfill with the excavated material provide
that such material meets with the approval of the Engineer. If there
is a deficiency of backfill material due to rejection of the excavated
material for use as backfill as e.g. when excavating in rock, the
Contractor shall furnish the required amount of approved material
at his own cost.
e. From 600 mm above the pipe to the finished ground level shown on
the drawings or specified elsewhere, the trench shall be backfilled
and consolidated by approved mechanical methods in layers with a
thickness not exceeding 200 mm for the first layer and not
exceeding 300 mm for the following, each layer to be compacted
separately. In roads the dry density of the compacted soil shall not
be less than 95% of the dry density found after laboratory test of the
soil, applying the heavy compaction test in accordance with BS
1377. If necessary to obtain the required density, and with
permission or instruction of the Engineer, the trench shall be
watered during backfilling and compaction operations. For this
purpose a safe amount of water shall be available at the trench
when backfilling.
f. All service trenches shall have a soft sand surround 150 mm all
round.
B/7
Multipurpose Hall at Manah
B.3.7 Unsuitable Material
When the specified levels or limits of excavation are reached, the
Engineer will inspect the ground exposed and if he considers that any
part of the ground is by its nature unsuitable he may direct the
Contractor to excavate further and refill to the specified levels or limits
with mass material. Such further excavation shall be held to be extra
excavation and shall be measured as such.
Should the material forming the bottom of any excavation, while
acceptable to the Engineer at the time of his inspection, subsequently
become unacceptable to him due to exposure to weather conditions or
due to flooding or have become puddled, soft or loose during the
progress of the works, the Contractor shall remove such damaged,
softened or loosened material and excavate further by hand. Such
excavation shall be held to be excess excavation and carried out at the
Contractor's own expense.
B.3.8 Disposal of Surplus Excavated Material
Surplus excavated material shall not be removed from the site unless
directed so by the Engineer. When rejected material is to be removed
from site, this shall be carted away and deposited only at locations
permitted by the Municipal authorities.
B/8
Multipurpose Hall at Manah
Application
For termite control soil application, the emulsion must be adequately
dispersed over or in the soil to provide a barrier between the structure
and the termite colonies in the soil. As a good practice, all non-
essential wood and cellulose containing materials, including scrap,
wood and form boards, should be removed from around foundation
walls, crawl spaces and porches. Soil around untreated structural
wood in contact with soil should be treated as described.
Contamination of public and private water supplies must be avoided by
following these precautions
1. Use anti-backflow equipment or procedures to prevent siphonage of
pesticides into water supplies.
2. Do not treat soil beneath structures that contain falaj or wells.
3. Do not treat soil that is water saturated. Always consult state and
local regulations for recommended distances of well/falaj.
To prepare a recommended dosage of 0.075% emulsion, mix 1 litre of
concentrate to 260 litres of water. Mixing should only be done by
professionally trained pest control operators. Hand gloves should be
worn while handling chemical concentrates. It is important that
chemical emulsion reaches the soil substrate and that even coverage is
obtained. Application to be made by low pressure spray (less than 50
p.s.i) using a coarse spray nozzle. Effective pre-construction
subterranean termite control is achieved by the establishment of
vertical and/or horizontal chemical barriers.
B/9
Multipurpose Hall at Manah
B.4.5 Treatment of Critical Areas
Soil should be treated around the drainage & plumbing lines, utility
entry points and other critical areas by flooding the area at the rate of 5
litres to 10 litres per entry point. A vertical chemical barrier of a
minimum width of 300 mm has to be created by treating the back filled
soil against walls along the expansion joints to the entire depth at the
rate of 2.5 litres per 500 mm depth by trenching and/or rodding.
B.4.7 Precautions
Precautions shall be taken not to disturb the treated areas by re-
levelling, digging or earth filling, as this will break the chemical barrier.
In case such situation arises, the area is to be treated again to restore
the chemical barrier.
B/10
Multipurpose Hall at Manah