Professional Documents
Culture Documents
PART 1 GENERAL
A. STIPULATIONS
The section “Special Requirements” forms a part of this section by this reference
thereto and shall have the same force and effect as if printed herewith in full. The
Contract Drawings and the Standard Form of Agreement apply to this Section.
B. RELATED DOCUMENTS
The Contract Drawings and the Standard Form of Agreement apply to this
Section.
C. SUMMARY
5. Each Contractor shall provide field offices and storage sheds, if required.
D. QUALITY ASSURANCE
E. EQUIPMENT
PART 3 EXECUTION
A. INSTALLATION, GENERAL
2. All contractors shall locate facilities where they will serve the Project
adequately and result in minimum interference with performance of the
Work. Relocate and modify facilities as required. Location shall be
approved by the OWNER and PROFESSIONAL.
3. All contractors shall provide each temporary facility ready for use when
needed to avoid delay. Maintain and modify as required. Do not remove
until facilities are no longer needed or are replaced by authorized use of
completed permanent facilities. Locations shall be approved by OWNER
and PROFESSIONAL.
B. Temporary facilities as outlined herein shall be installed prior to start of work and
within (30) days of Notice to Proceed.
C. TEMPORARY UTILITY INSTALLATION
1. Each contractor shall, at their own cost and expense; install, operate,
protect, and maintain the respective temporary services as hereinafter
specified, during the construction period of the entire project. These
temporary services shall include water supply, electric, light, and power,
and any other services as may be stipulated in General Conditions, Special
Requirements, and/or specification.
2. Each contractor shall pay all costs for the operation of temporary services
herein specified, except that the University will pay all fuel costs for
steam, water and power that are taken from their utility systems. Data,
phone, and all other telecommunication costs for temporary offices shall
be the responsibility of the contractor occupying the area.
The Electrical Contractor shall, at his own cost and expense; install,
operate, protect and maintain a complete temporary construction light and
power system as detailed below.
k.Contractors shall supply their own power for any welding operations
and shall not use System provided power for this operation.
The Electrical Contractor shall, at his own cost and expense; install,
operate, protect and maintain a complete TeleData system for the project
field offices as detailed below.
a. Complete installation of a temporary system shall be in strict
accordance with the latest edition of all applicable Codes.
2 Telephone lines/numbers
1 line for connection to internet services
The General Contractor shall, at his own cost and expense; install,
operate, protect and maintain a complete Temporary Heating and Cooling
System for the project as detailed below.
a. provide temporary heating units that have been tested and labeled
UL, FM, or another recognized trade association related to the type
of fuel being consumed. If liquid fuel is used, provide under-unit
containment in the event of leakage. Provide adequate ventilation
or direct vent the units to the outside.
A. SANITARY FACILITIES
1. The General Contractor shall, at their own cost and expense; provide and
maintain in a clean and sanitary condition, adequate and approved sanitary
facilities as specified below. Portable chemical toilets approved by
Pennsylvania Department of Health are acceptable. Sanitary facilities
include temporary toilets, wash facilities and drinking water fixtures.
Comply with regulations and health codes for the type, number, location,
operation and maintenance of fixtures and facilities. Install where facilities
will best serve the Project’s needs. Provide toilet tissue, paper towels,
paper cups and similar disposable materials for each facility. Provide
covered waste containers for used material. Drinking water inside site
trailers is the responsibility of each individual Contractor.
4. Portable toilet facilities that are used on University construction sites must
comply with Best Management Practices (BMP) for placement of such
toilets. Suggested practices that minimize the potential for storm water
pollution from portable toilets and therefore ensure regulatory compliance
are listed below and should be adhered to by the General Contractor.
1. Each Contractor shall collect their waste daily and deposit in the
containers provided by the General Contractor. The General Contractor
shall provide all other cleaning and waste removal services listed below.
a. Clean Project site and work areas daily, including common areas.
Coordinate progress cleaning for joint-use areas where more than
one installer has worked. Enforce requirements strictly. Dispose
of materials off-site in a legal manner.
2. The General Contractor shall install temporary fencing outside the drip
line of trees to protect vegetation from construction damage. Protect tree
root systems from damage, flooding, and erosion.
1. All contractors shall comply with standards and code requirements for
erecting structurally adequate barricades. Paint with appropriate colors,
graphics, and warning signs to inform personnel and public of possible
hazard. Provide lighting, including flashing red or amber lights.
E. TRAFFIC CONTROLS
F. TEMPORARY ENCLOSURES
1. The General Contractor shall provide temporary enclosures for protection
of construction, in progress and completed, from exposure, foul weather,
other construction operations, and similar activities. Close openings in
floor or roof decks and horizontal surfaces with load-bearing, wood-
framed construction. Provide temporary weather-tight enclosure for
building exterior. Maintain until permanent enclosure is complete.
G. TEMPORARY PARTITIONS
1. The General Contractor shall erect and maintain dustproof partitions and
temporary enclosures to limit dust and dirt migration into other areas, and
to separate areas from fumes and noise.
I. ACCESS ROADS
4. Remove mud and gravel carried from construction site to university and
public roads on a daily basis.
J. PARKING
3. Maintain the parking area throughout the project including weed control
and snow/ice removal.
5. Remove each temporary facility when need for its service has ended, when
it has been replaced by authorized use of a permanent facility, or no later
than Substantial Completion. Complete or, if necessary, restore
permanent construction that may have been delayed because of
interference with temporary facility. Repair damaged Work, clean exposed
surfaces, and replace construction that cannot be satisfactorily repaired.
10. Restore grass areas, landscaping, concrete and macadam areas to their
original condition except where shown on the Contract Documents to
provide new areas.