DAILY REPORT

SITE LEVELING WORK FOR CEMENT PLANT

CONTRACTOR CLIENT LOCATION Report # Date of Work


NAK COMPANY DCCP Dabin cement plant- Keshke 028 13-jan-23
WEATHER TEMPERATURE WIND Ground Condition Prepared by
Cloudy 10-1 4 km/h dry Shaban Abdulrahman
General Description of Work Activities
Daily Activity:
• Surveying work for the site is ongoing.
• cutting for the side slopes is ongoing.
• Cutting work for 3 zones of the site are ongoing.
• Dumping soils at designated dumping area is ongoing. About 20,000 cubic meters dumped.

Sections Events
Safety, Health & Environment No issue
Inspections Not ready for inspection
Request For Change N/A
Areas of Concern No concern

Page 1 of 2
DAILY REPORT
SITE LEVELING WORK FOR CEMENT PLANT

Equipment on Site Personnel on site

Equipment description QTY Equipment description QTY Position Quantity


Excavator 340 bucket 26 Site Offices 15 Project Manager 1
Excavator with jackhammer 3 Crane Construction Manager 1
Bulldozer 13 Drilling machine 4 Land Surveyor/assistant 2
Dump truck 55 Water tanker 2 HSE Supervisor 1
JCB 1 Diesel tanker 1 Foremen 9
Front end loader 5 Toyota HiLux 4 Equipment Operator 117
Compactor 1 Technician 4
Generator 2 Accountant 2
Vacuum truck Driver 6

Approved by

Project Manager/Mohammed Dler

Page 2 of 2