Wells Dep.

Daily report
Civil team

Contractor:- AL SHALAL Well Pad:DR-(JK-29)(NW)

Location:- N-Rumelia
Date:- 2/2/2020
Degassing Station:- DS5

PTW No.:-164631
Site Supervisor:- Ehab Hussien

Work completion:-77%
Weather condition:- 14C

Man Power No. Equipment No.


Site Engineer 1 Excavator
HSE supervisor 1 Shovel
Surveyor 1 Dump truck 10
Equipment Operator 12 Water tanker
Carpenters Compactor
Steel fixer Grader
Foreman 1 Van 1
Skilled Labourers 1 Ladder
Labourers 1 Pickup 1
Masons Lorry
Cement Finishers Truck mixer
Total man power 18 Total No. Equipment 12

Item Start Finish Work Activity Activity


No. time time %
1 5:00 5:10 TBT
2 5:10 11:00 Backfill the 4th layer 20%
3 5:10 11:00 Shuttering removal 100%
4

Item Next Day Plan


No.
1 Backfill the 4th layer
2

8No. Visitor Name Company Arriving leaving Reason of visit


time time
1
2

NPT (HRS) Reason

Rev.2 Page 1
Wells Dep. Daily report
Civil team

Photos

Rev.2 Page 2