You are on page 1of 2

Wells Dep.

Daily report
Civil team

Contractor:- :- OROK GLOBAL CO. Well Pad:- Ru-94

Location:- S-Rumaila
Date:- 29-Mar-19
Degassing Station:- MARKAZIA

PTW No.:- 150914


Site Supervisor:- Mustafa maan

Weather condition:- 28 C Work completion:-100%

Man Power No. Equipment No.


Site supervisor 1 Excavator
HSE supervisor 1 Shovel 1
Surveyor 1 Dump truck
Equipment Operator 4 Water tanker 1
Carpenters Compactor 1
Steel fixer Grader 1
Foreman 1 Van
Skilled Labourers Ladder
Labourers 4 Pickup
Masons Lorry
Cement Finishers Truck Mixer
Total man power 12 Total No. Equipment 4

Item Start Finish Work Activity Activity


No. time time %
1 6:15 6:25 TBT

2 6:30 12:30 Compaction the existing pad %100

3 6:30 12:30 Cellar works %100


4

Item No. Next Day Plan


1 All items is completed
2
3

Rev.2 Page 1
Wells Dep. Daily report
Civil team

No. Visitor Name Company Arriving time leaving time Reason of visit
1 No visit
2

NPT (HRS) Reason

Photos

Rev.2 Page 2

You might also like