You are on page 1of 1

Tanggal :

FORM RITASI
Jarak :

Block :

Shift :

NO CODE UNIT DRIVER 07:00/19:00 08:00/20:00 09:00/21:00 10:00/22:00 11:00/23:00 12:00/00:00 13:00/01:00 14:00/02:00 15:00/03:00 16:00/04:00 17:00/05:00 18:00/06:00 TOTAL KETERANGAN

TOTAL

TOTAL

TOTAL

TOTAL

TOTAL

TOTAL

TOTAL

TOTAL

Jenis Material Dibuat Oleh Dicek Oleh


OB

TOP SOIL

COAL

Checker Foreman
s1 Rain s6 Safety Talk s11 Wait Operator s16 Commissioning s21 No/Wait Support s26 No Operator s31 Customer Problem
s2 Slippery s7 Over Capacity s12 Wait Truck No Operator s17 Washing Unit (Coal) s22 Wait Survey s27 No Location s32 Strike
s3 Shift Change s8 Wait Blasting s13 Front Preparation s18 Wait Mechanic s23 Moving Equipment s28 No Material
s4 Meal & Rest s9 Praying s14 Disposal Preparation s19 Mis-identification s24 Holiday & Shutdown s29 Hazard
s5 Friday Pray s10 Toilet s15 Fuel s20 Dusty s25 Wait Exa/Truck (PA) s30 Fog