You are on page 1of 3

Status as on : //2012

CONTRACT NO. Activity Total Completed Balance


VISUAL PROGRESS CHART (GOPALGANJ PART)
: PGCB/ADB/3522/400KV/TL/AG1
DATE OF CONTRACT : 12/23/2018 No. of Piles 1932 Nos. 1932 Nos. 0
COMPLETION TIME : 10/31/2021
:
AMINBAZAR-GOPALGANJ 400KV TRANSMISSION LINE Pile Cap
Erection
376 Nos.
94 Towers
376 Nos.
66
0
28
COMPLETION DATE
: Stringing 33.218 Km 0 33

Section-1 (2605m) Section-2 (2517m) Section-3 (3018m)

TT1 T38 T38/1 T38/2 T38/3 T38/4 T38/5 T39 T39/1 T39/2 T39/3 T39/4 T39/5 T39/6 T40 T40/1

1
1
1

BIBYANA S/S 4DT6 4D25 4D1 4DLT 4DLT 4DLT 4DLT 4D25 4DLT 4DLT 4DLT 4DLT 4DLT 4DLT 4D25 4DLT
Section-4 (2754m) Section-5 (2686m)
T40/2 T40/3 T40/4 T40/5 T40/6 T40/7 T40A T40A/1 T40A/2 T40A/3 T41 T41/1 T41/2 T41/3 T41A T41A/1 T41A/2

1
1
1

4DLT 4DLT 4DLT 4DLT 4DLT 4DLT 4D25 4DLT 4DLT 4DLT 4D25 4DLT 4DLT 4DLT 4D25 4DLT 4DLT
Section-6 (2826m) Section-7(2553 m)
T42 T42/1 T42/2 T43 T43/1 T43A T44 T44/1 T44/2 T44/3 T44A T44A/1 T44A/2 T45 T45/1 T45/2 T45A

4D25 4DLT 4DLT 4D25 4DLT 4D45 4D25 4D1 4D1 4D1 4D25 4DLT 4DLT 4D25 4DLT 4DLT 4D45

Section-8(2871 m) Section-9(3105 m)
T45A/1 T45A/2 T45B T45B/1 T46 T46/1 T46/2 T46A T46A/1 T46A/2 T46A/3 T47 T47/1 T47A T47A/1 T47A/2 T47A/3

4DLT 4DLT 4D25 4DLT 4DT6 4DLT 4DLT 4D45 4DLT 4DLT 4DLT 4D25 4DLT 4DT6 4DLT 4DLT 4DLT
Section-10(3200 M) Section-11(2075 m)
T47B T47B/1 T47B/2 T47B/3 T48 T48/1 T48/2 T48A T48B T48B/1 T48C T48C/1 T48C/2 T49 T49/1 T49/2 T49/2

4D25 4DLT 4DLT 4DLT 4D25 4DLT 4DLT 4D45 4D25 4DLT 4D25 4DLT 4DLT 4D45 4DLT 4DLT 4DLT

Section-12(3013 m)
T49A T49B T50 T50A T50A/1 T50A/2 T50A/3 T50B T50B/1 T51 T51/1 T52

4D25 4D45 4D25 4D25 4DLT 4DLT 4DLT 4D25 4DLT 4D25 4D1 4DAX
Pile Cap
Piling Piling Work Pile Cap Site Preparation
Total Shifting/Site Casting Erection Erection Stringing
Tower Type Completed(Locs. Running Completed (Excavation, Pile Stringing Running Markings Legend :
Quantity ) (Locs.)
Preparation (Pile)
(Locs.)
Running breaking) Completed Running Completed
(Locs.)

4DLT 58 58 0 0 0 0 0 53 1 Tower Stringing


Erection
4D1T 5 5 0 0 0 0 0 0 Pile Cap
.
4D25T 22 22 0 0 0 0 0 7 5 0 0 Pile Fdn.

4D45T 6 6 0 0 0 0 0 6 Piling Completed

4DT60T 3 3 0 0 0 0 0 0 1 Pile Cap Completed


Total 94 94 0 0 0 0 0 66 7 0 0.000 km Erection Completed
Erection Ongoing
ORGANIZATION CHART ASTER-MULTIFAB JV
Date: 17.03.2007

General Manager
Mr.S.K.Mukherjee

Deputy GM
Mr.B.K.Pal

Project Manager
Mr.Albert

Commercial Officer Safety Officer Q/C Officer Project Engineer Project Engineer Surveyor
Mr.Asim Dutta Mr.S.P.Bhattacharya Mr.Gama Mr.Asis Kar Mr.A.Mitra Mr.S.Mondal

Store Keeper Supervisor


Accountant Supervisor
Mr.H.P.Roy Mr.Ghosh Supervisor Supervisor Supervisor Supervisor
Mr.D.Singh

Asst.Store
Mechanic
Keeper