CONTRACTOR DAILY

ACTIVITY REPORT

Daily Activity Report (DAR)


RED-Familywing-Al Dyar-FORT -DAR-021 Date 10/2/2024
Weather:
Weather Sunny Cloudy Rainy Dusty
Humidity High Medium Low
Temperature C Max 19 Min 10 High temperature lunch break

EQUIPMENT Hours EQUIPMENT Hours


Type Qty Worked Idle Type Qty Worked Idle
Hammer Drill 2 2 Traffic
Cutting Grinding 1 1 Pickup
Tipper Water tanker
Drill 1 1 Leser Level 2 1
Mobile Crane Baby Steel Roller
Tower Crane Bar Bending Machine
Transit Mixers Wood/Marble Brick Cutter
Concrete Pump Framing Square 2 2
Welding Machine Electrical Tools
Generator Hose Level
Grade 6-Wheel Truck
Brick Trowel 2 2 Backhoe
Steel Roller Wheel Loader
Total Station Clamp piliers 1 1
Shovel 1 1 Wernch 2 2
Ladder 1 1 Tubing Cutter 1 1
Screeding level 6 6 Pipe and tube benders 1 1
Vibrator Plumer torch
Scraper Mortar Trowel-Rubber 2 2

MATERIALS DELIVERED TO SITE VISITORS TO SITE


Item Unit Qty Name Company

Distribution: PM (Original) Consultant QS Contractor Others


CONTRACTOR DAILY
ACTIVITY REPORT

CONTRACTOR'S MANPOWER AVAILABLE AT SITE


Staff Labor Daily Sum
Occupation Contract Actual Occupation Skilled unskilled Total Total
Project manager 1 1 Foreman
Construction Manager Carpenter
Project Coordinator Rebar Fixers
Site Administrator Masons 1 1 2
Logistics in charge Machine Operators
Design Engineer Plumber 2 2 4
ELECTRICAL Engineer Tiler 1 1
Quantity Surveyor Labors
Document Controller Tower Crane Operator
Safety Engineer Plasterer 7 3 8
Project Engineers Painter 3 3
Site Engineers 1 1 Mechanic
Surveyor Electrician 5 2 7
Supervisors Welder
Foreman Concreter
Draftsman Steel Fixer
Secretary Others (list) 5
Timekeeper Sculptor worker 1 1
Storekeeper
QA/QC
QA/QC Supervisor
Office Boy
Driver
Watchman
Safety Crews
Surveyor's Aide
QA/QC Assistants
Others (list)
SUB-TOTAL 2 2 SUB-TOTAL 25 9

Distribution: PM (Original) Consultant QS Contractor Others


CONTRACTOR DAILY
ACTIVITY REPORT

WORK IN PROGRESS / MANPOWER ALLOCATION


Activity Location Manpower Date %
Trade Description of work
Number BULD FLO Group Hours Start Finish comp.
B27 3rd Floor F
nd
Fixing of wall conduits & B27 2 Floor F
1
switch socket boxes B27 1st Floor F
B27 GF Floor 1 8.5 8 4:30 95
rd
B27 3 Floor 1 8.5 8 4:30 80
nd
Installation of Drainage B27 2 Floor 1 8.5 8 4:30 15
2
pipes B27 1st Floor 1 8.5 8 4:30 5
B27 GF Floor 1 8.5 8 4:30 5
rd
B27 3 Floor F
nd
Installation of Water B27 2 Floor 1 8.5 8 4:30 95
3
pipes B27 1st Floor 1 8.5 8 4:30 95
B27 GF Floor
B27 3rd Floor F
nd
B27 2 Floor 1 8.5 8 4:30 95
4 Brickwork
B27 1st Floor 1 8.5 8 4:30 95
B27 GF Floor 1 8.5 8 4:30 95
rd
B27 3 Floor F
nd
Starting B27 2 Floor 1 8.5 8 4:30 90
5
Plastering work B27 1st Floor 1 8.5 8 4:30 20
B27 GF Floor
Plastering 1 8.5 8 4:30 80
6 facade
Brickwork 1 8.5 8 4:30 95
B27 3rd Floor F
Paints (1st +2nd B27 2nd Floor 1 8.5 8 4:30 80
7
Kemaxit200) B27 1st Floor
B27 GF Floor
B27 3rd Floor F
Chemical insulation of B27 2nd Floor 1 8.5 8 4:30 5
8
bathrooms B27 1st Floor
B27 GF Floor
Store bricks, Sand, Cement
9 B27 1 8.5 8 4:30 40
B27 3rd Floor 1 8.5 8 4:30 95
B27 2nd Floor
10 1st GLC Dayton paint paste
B27 1st Floor
B27 GF Floor
CONTRACTOR DAILY
ACTIVITY REPORT
B27 3rd Floor 1 8.5 8 4:30 10
11 CERAMIC WORKS B27 2nd Floor
B27 1st Floor
B27 GF Floor

Issued by: Site Engineer Received by: Owner


Contractor Name / Signature / Date Engineer Name / Signature / Date

Owner comments on this report. Any issues on Quality / Program / Safety:

Received by: Contractor

Contractor Name / Signature / Date Consultant Name / Signature / Date


Distribution: PM (Original) QS Contractor Others