CLIENT: CONSULTANT: CONTRACTOR:

DAILY REPORT
Report No. J220/RC/DR/287

Project: Samana Miami-1 Date: 16-May-24

Client SAMANA DEVELOPERS Weather : Sunny Cloudy Rainy


Consultant AREC ENGINEERING Temperature: Max: 29° Min: 20°
Main Contractor Reliant Contracting LLC Humidity: High Medium Low

Manpower Equipment
Office Staff No. Production Workers No. Type Qty Manpower Hours Worked
GENERAL Manager 1 Carpenter 32 Small Generators 2
PROJECT Manager 1 Steel Fixer 19 Bobcat 1
Site Engineer 2 Mason 3 Welding Machine 1
Asst. Const. Manager - Labor/Helper 2 Tower Crane 1
Planning Engineer 1 Electrician 3 Bar bending Machine 1
MEP Coordinator 1 Painter 4 Vibrator 1
QA/QC Engineer 1 Boom Loader Operator 1 Compactor 1
Safety Officer. 1 Plumber 1 Boom Loader 1
Civil Forman 2 Crane Operator 1 Bar Cutting Machine 1
Electrical Forman 1 Rigger 1 Plaster Machine 2
Plumb. Forman -
Driver 4 Excavator
Sub-Contractors:
Office Boy/Cleaner 1 Shovel
Security/Watchman 1 Al Yasmeen Plaster & Tiles 0
Store/Time Keeper 1 Najam Al Simal 4
Almamr Alnader Technical Works
HR/Document Controller 1 L.L.C 30
Safety Officer.Asst.. AK Building Contracting 31
Surveyor 1 Swad Allail General Contracting 2
Surveyor Asst. 1 Jehanzeb Technical Service 0
Trade Foreman - DP Plaster 1

Total 21 135 12 156 Total= 1404

Work Target for Today:


1. Ground Floor Backwash Tank Work G- Floor
2. Fire Fighting System work G- Floor
3. LV Room Work G- Floor
4. Podium Plaster Preparation Podium
5. 3rd Floor Sub-frame for Doors 3rd Floor
6. 1st Floor MEP 1st Fix in Walls Completed 1st Floor
7. 1st Floor Plaster Work 1st Floor
8. 2nd Floor MEP 1st Fix in Walls 2nd Floor
9. 4th Floor Cutting & Chasing 3rd Floor
10. 5th Floor Cutting & Chasing 4th Floor
11. 3rd & 4th Floor MEP 1st Fix in Walls 3rd & 4th Floor
13. 4th Floor Plaster Guide Point 4th Floor
14. 5th Floor Block Work Fixing & Curing 5th Floor
15. 6th Floor Block work Fixing & Curing 6th Floor
16. Lift Upper Roof Slab Curing Casting Date: 14 May 2024 Upper Roof
17. Safety & Site Cleaning work in progress
Work Target for Next day:
1. Backwash Tank Steel & Shutter Fixing G- Floor
2. Plaster Work 1st Floor 1st Floor
3. 4th Floor Plaster Guide Point 4th Floor
4. 3rd Floor Sub-frame for Door Openings 3rd Floor
5. Podium Plaster Preparation Podium
6. 2nd Floor MEP 1st Fix 2nd Floor
7. 3rd Floor MEP 1st Fix 3rd Floor
9. 4th Floor Cutting & Chasing 4th Floor
10. 4th Floor MEP 1st Fix 4th Floor
11. 5th Floor Cutting & Chasing 5th Floor
12. 5th Floor Block Work Fixing & Curing 5th Floor
13. 6th Floor Block work & Lintel Fixing & Curing 6th Floor
14. Roof Floor Cleaning Roof
15. Lift Upper Roof Slab Curing Casting Date: 14 May 2024 Upper Roof
16. Safety & Site Cleaning work in progress
Material at Site
2. Plaster Materials
3. Cement & Sand
4. Scaffolding
5. Sikanjas.
6. MEP Materials
7. Reinforcement Steel
8. Flush Tank
9. 3"x3" Timber & Plywood
9. Ceramic Tiles
Note:
Consultant Eng.: Cont. Engineer: Eng. Sameer Alzebdeh