Sr. No Activity Description Duration Start Date Finish Date UOM 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar Week 4 UOM 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar Week 4
Quantity
21-May-21 30-Jun-24 Original Project Schedule
20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar Week 4 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar Week 4
Maternity Home ,Malad Malwani 25-Dec-22 14-Apr-23
Slab Cycle RCC Work 110 25-Dec-22 14-Apr-23
11 FOURTH Floor LEVEL slab (Pour 2) 11 25-Dec-22 05-Jan-23 - -
third Floor Slab Shuttering 25-Dec-22 28-Dec-22 378 Sqm - -
Third Floor Slab Reinfrocement 29-Dec-22 04-Jan-23 13 MT
Concreting 05-Jan-23 05-Jan-23 110 Cum
15 FOURTH Floor LEVEL slab (Pour3 ) 15 06-Jan-23 21-Jan-23
third Floor Slab Shuttering 06-Jan-23 09-Jan-23 378 Sqm
Third Floor Slab Reinfrocement 09-Jan-23 12-Jan-23 13 MT
Concreting 15-Jan-23 15-Jan-23 110 Cum
Fifth Floor level slab 60 16-Jan-23 17-Mar-23
30 FIFTH Floor LEVEL Slab(Pour1) 30 21-Jan-23 20-Feb-23
Column Reinforcement And Shuttering(16No.S) 10 21-Jan-23 31-Jan-23 4.4 MT
Column casting (16 nos) 3 31-Jan-23 03-Feb-23 22.1 Cum
Fifth Floor Slab Shuttering 10 16-Jan-23 26-Jan-23 378 Sqm
Fifth Floor Slab Reinfrocement 21 29-Jan-23 19-Feb-23 13 MT
Concreting 1 19-Feb-23 20-Feb-23 110 Cum
15 FIFTH Floor LEVEL Slab(Pour2) 15 20-Feb-23 07-Mar-23
Column Reinforcement And Shuttering(25 +passanger lift8) 11-Feb-23 19-Feb-23 10.3 MT
Column casting (25 +passanger lift ) 4 16-Feb-23 20-Feb-23 46.04 Cum
Fifth Floor Slab Shuttering 7 20-Feb-23 27-Feb-23 378 Sqm
Plan Fifth Floor Slab Reinfrocement 5 01-Mar-23 06-Mar-23 13 MT - - - - - - - - MT 0.00 0.00 0.00 0.00 0.00 - - -
Plan Concreting 1 06-Mar-23 07-Mar-23 110 Cum - - - 55 55 - - 110 Cum 0.00 0.00 0.00 0.00 0.00 - - -
16 FIFTH Floor LEVEL Slab(Pour3) 16 01-Mar-23 17-Mar-23
Plan Column Reinforcement And Shuttering(14) 6 01-Mar-23 07-Mar-23 6.37 MT - - - - - - - - MT 0.00 0.00 0.00 0.00 0.00 - - -
Plan Column casting (14) 2 06-Mar-23 08-Mar-23 19.77 Cum - - - - - - - - Cum 0.00 0.00 0.00 0.00 0.00 - - -
Plan Fifth Floor Slab Shuttering 7 07-Mar-23 14-Mar-23 378 Sqm - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Fifth Floor Slab Reinfrocement 5 10-Mar-23 15-Mar-23 13 MT - 2 2 2 2 2 3 13 MT 0.00 0.00 0.00 0.00 0.00 - - -
Plan Concreting 2 15-Mar-23 17-Mar-23 110 Cum - - - - - - - - Cum 0.00 0.00 0.00 0.00 0.00 - - -
` 28 17-Mar-23 14-Apr-23 - -
10 TERRACE Slab(Pour1) 10 17-Mar-23 27-Mar-23 - -
Plan Column Reinforcement And Shuttering(16No.S) 4 17-Mar-23 21-Mar-23 4.4 MT - 1 1 1 1.4 4.4 MT 0.00 0.00 0.00 - - -
Plan Column casting (16 nos) 2 19-Mar-23 21-Mar-23 22.1 Cum 7 7 - - - - - 15 Cum 0.00 0.00 0.00 0.00 - - -
Plan Fifth Floor Slab Shuttering 5 21-Mar-23 26-Mar-23 378 Sqm - 63 63 63 63 63 63 378 0.00 -
Plan Fifth Floor Slab Reinfrocement 4 22-Mar-23 26-Mar-23 13 MT - - 3 3 3 3 3 13 MT 0.00 0.00 -
Plan Concreting 1 26-Mar-23 27-Mar-23 110 Cum - - - - - - 55 55 Cum 0.00 0.00 0.00 0.00 0.00 - -
8 TERRACE Slab(Pour2) 8 27-Mar-23 04-Apr-23 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Column Reinforcement And Shuttering(25 +passanger lift3) 27-Mar-23 30-Mar-23 10.3 MT - - - - - - - - MT 0.00 0.00 0.00 0.00 0.00 - - -
Plan Column casting (25 +passanger lift ) 1 28-Mar-23 29-Mar-23 46.04 Cum - - - - - - - - Cum 0.00 0.00 0.00 0.00 0.00 - - -
Plan Fifth Floor Slab Shuttering 3 30-Mar-23 02-Apr-23 378 Sqm - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Fifth Floor Slab Reinfrocement 3 31-Mar-23 03-Apr-23 13 MT - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Concreting 1 03-Apr-23 04-Apr-23 110 Cum - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
10 TERRACE Slab(Pour3) 10 04-Apr-23 14-Apr-23 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Column Reinforcement And Shuttering(14) 4 04-Apr-23 08-Apr-23 6.37 MT - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Column casting (14) 2 06-Apr-23 08-Apr-23 19.77 Cum - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Fifth Floor Slab Shuttering 5 08-Apr-23 13-Apr-23 378 Sqm - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Fifth Floor Slab Reinfrocement 4 09-Apr-23 13-Apr-23 13 MT - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Concreting 1 13-Apr-23 14-Apr-23 110 Cum - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Basement 90 02-Jan-23 02-Apr-23 - -
77 Pour -1 77 02-Jan-23 20-Mar-23 - -
Plan Retaining Wall R/F and Column R/F 33 02-Jan-23 04-Feb-23 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Retaining Wall Shuttering and Column Shuttering 33 03-Jan-23 05-Feb-23 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Retaining Wall and Column Concrete 10 27-Jan-23 06-Feb-23 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Slab Shuttering 6 10-Mar-23 16-Mar-23 2667 Sqm - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Slab Reinfrocement 6 13-Mar-23 19-Mar-23 9 MT - - - - - - - - MT 0.00 0.00 0.00 0.00 0.00 - - -
Plan Concreting 1 19-Mar-23 20-Mar-23 50 Cum 25 - - - 25 - - 50 Cum 0.00 0.00 0.00 0.00 0.00 - - -
23 Pour -2 23 10-Mar-23 02-Apr-23 - -
Plan Retaining Wall R/F and Column R/F 2 10-Mar-23 12-Mar-23 completed - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Retaining Wall Shuttering and Column Shuttering 2 12-Mar-23 14-Mar-23 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Retaining Wall and Column Concrete 1 14-Mar-23 15-Mar-23 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
NOT
Plan Slab Shuttering 6 23-Mar-23 29-Mar-23 2667 - - - 381 381 381 381 1,524 NOT PAYBLE 0.00 0.00 0.00 -
PAYBLE
Plan Slab Reinfrocement 6 26-Mar-23 01-Apr-23 9 MT - - - - - - 1 1 0.00 0.00 0.00 0.00 0.00 - -
Plan Concreting 1 01-Apr-23 02-Apr-23 50 cum - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
5 Pour -3 Ramp 5 23-Mar-23 28-Mar-23 - -
Plan Retaining Wall R/F and Column R/F 2 23-Mar-23 25-Mar-23 completed - - - - - 0.00 0.00 0.00 - -
NOT
Plan Retaining Wall Shuttering and Column Shuttering 2 25-Mar-23 27-Mar-23 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
PAYBLE
Plan Retaining Wall and Column Concrete 1 27-Mar-23 28-Mar-23 68 Cum - - - - - - - - cum 0.00 0.00 0.00 0.00 0.00 - - -
62Water Proofing,
Finishing Work ( Brick Work, Internal Plastering & Painting, 06-02-2023
Plumbing Work, 09-04-2023
Flooring) - -
60 First Floor 60 06-02-2023 07-04-2023 - -
Plan Brick Masonry 23 06-02-2023 01-03-2023 258 Cum - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Electrical Work ( Cheisling) 28 08-02-2023 08-03-2023 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Door and Window Framing 15 08-03-2023 23-03-2023 254 RMT 16 16 16 16 - - - 64 RMT 0.00 0.00 - - -
Plan Internal Plaster 15 23-03-2023 07-04-2023 1224 Sqm - - - 77 77 77 77 306 Sqm 0.00 0.00 0.00 -
37 Second Floor 37 02-03-2023 08-04-2023 - -
Plan Brick Masonry 15 02-03-2023 17-03-2023 74 Cum - - - - - - - - Cum 0.00 0.00 0.00 0.00 0.00 - - -
Plan Electrical Work ( Cheisling) 20 04-03-2023 24-03-2023 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan Door and Window Framing 15 24-03-2023 08-04-2023 48 RMT - - - - 3 3 3 9 RMT 0.00 0.00 0.00 0.00 -
22 Third Floor 22 18-03-2023 09-04-2023 - -
Plan Brick Masonry 15 18-03-2023 02-04-2023 220 Cum 14 14 14 14 14 14 14 96 Cum 2 2
Plan Electrical Work ( Cheisling) 20 20-03-2023 09-04-2023 - - - - - - - - 0.00 0.00 0.00 0.00 0.00 - - -
Plan 4,83,707 3,22,547 4,33,882 12,27,319 15,42,019 5,34,979 14,33,501 59,77,955 11,744 0.00 0.00 0.00 0.00 - - 11,744