Cube ref. Date 7 Days Cube Strength (N/mm2) 28 Days Cube Strength (N/mm2)
No Location Grade Supplier Pass /
no. Casted Schedule Actual Cube Schedule Actual Cube
AVG AVG Fail
Test test Test test
No.1 No.2 No.3 (Mpa) No.1 No.2 No.3 (Mpa)
Date date Date date
Pad Footing unit no
20-Mar- 27-Mar- 27-Mar- 17-Apr- 17-Apr-
1 01,03 G30 Hanson 657429 23.5 22.9 23.5 23.30 32.6 33.1 32.0 32.57 Pass
23 23 23 23 23
Zone 1 / A1
10-Jun- 17-Jun-
29243 08-Jul-23
23 23
Pad footing unit no 1,3 Great
31 G30
Zone 1 / B1 Concrete
10-Jun- 17-Jun-
29248 08-Jul-23
23 23
14-Jun- 21-Jun-
31154838 12-Jul-23
23 23
Pad footing unit 05,07
35 G30 Hanson
Zone 1 / B1
14-Jun- 21-Jun-
31154845 12-Jul-23
23 23
Cube Date 7 Days Cube Strength (N/mm2) 28 Days Cube Strength (N/mm2)
No Location Grade Supplier Pass /
ref. no. Casted Schedule Actual Cube Schedule Actual Cube
AVG AVG Fail
Test test Test test
No.1 No.2 No.3 (Mpa) No.1 No.2 No.3 (Mpa)
Date date Date date