PERIOD : 22 JAN 2023 ~ 26 FEB 2023 (36 Days) 1/21 1/22 1/23 1/24 1/25 1/26 1/27 1/28 1/29 1/30 1/31 2/1 2/2 2/3 2/4 2/5 2/6 2/7 2/8 2/9 2/10 2/11 2/12 2/13 2/14 2/15 2/16 2/17 2/18 2/19 2/20 2/21 2/22 2/23 2/24 2/25 2/26

Task Name Start Finish Duration Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
A Unit 3 Planned Outage Overview
1 Outage Period 22-Jan 26-Feb 36
- De-Synchronization 22-Jan 22-Jan 1
- Synchronization 26-Feb 26-Feb 1
2 PTW Period 22-Jan 21-Feb 31
3 Spare Days 27-Feb 6-Mar 8
B Shutdown 22-Jan 26-Feb 36
1 De-Synchronization 22-Jan 22-Jan 1
2 Draft System Stop 22-Jan 22-Jan 1
3 GT de-Energizing 24-Jan 13-Feb 21
4 TBN Cooling Time 22-Jan 27-Jan 6
5 CWP Stop 24-Jan 24-Jan 1
C Inspection Period
1 Standard Scope
1. Mech. Turbine 22-Jan 25-Feb 35
2. Mech. Boiler 22-Jan 23-Feb 33
3. Electrical 22-Jan 17-Feb 27
4. Control & Instrument 22-Jan 18-Feb 28
2 Additional Scope
1. Generator full inspection 22-Jan 22-Feb 32
2. GCB Ordinary inspection 30-Jan 20-Feb 22
3. Generator Online Partial Discharce Installation 6-Feb 14-Feb 9
4. MS Cation Conductivity Online Monitoring installation 16-Feb 23-Feb 8
5. FGD Duct expansion joint replacement 16-Feb 23-Feb 8
D Startup Preparation & Testing
1 Main Turbine & BFPT Valve Calibration 21-Feb 23-Feb 3
2 Protection & Interlock Test (BLR, TBN, BTG) 23-Feb 24-Feb 2
3 Air Balancing Test 24-Feb 24-Feb 1
4 Boiler Flushing & light off preparation 22-Feb 24-Feb 3
5 Condenser Vac-Up & TBN Prewarming 24-Feb 24-Feb 1
6 Boiler Light Off 24-Feb 24-Feb 1
7 TBN Rolling 25-Feb 25-Feb 1
8 TBN no load test & AVR Test 25-Feb 25-Feb 1
9 Synchronization 26-Feb 26-Feb 1