SCHEDULE WORKS KRAKATAU DAYA LISTRIK (KDL)

PROYEK JAWA 9 & 10 ( 2X1,000 MW )

0 153 day 30-Jun 30-Nov


Total SCHEDULE September 2022
No. Description Single Equipment Weight Total Weight
Unit
Duration Remaks
Start Finish 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

I WATER TREATMENT PLANT AREA 154 days 30-Jun-22 30-Nov-22 Dedicated equipment for
Delivery WTP Package (Mech & Piping) 1 day 21-Aug-22 21-Aug-22 1 Bulldozer
Delivery WTP Package (Elect, I&C) 1 day 21-Aug-22 21-Aug-22
Delivery WTP Package (MCC) 1 day 30-Nov-22 30-Nov-22 2 Vibro Roller
Delivery WTP Package (DCS) 1 day 30-Nov-22 30-Nov-22
Delivery of Interconnection Pipe 1 day 30-Sep-22 30-Sep-22 1 Motor Grader
H/O Fdn Inside WTP 1 day 30-Jun-22 30-Jun-22 2 DT 10M3
H/O Fdn Outside WTP 1 day 31-Jul-22 31-Jul-22 Dedicated equipment for
H/O Fdn SWRO & BWRO Storage Tank 1 day 12-Aug-22 12-Aug-22
H/O Settlement Basin 40 days 10-Aug-22 18-Sep-22
H/O S/S 1 day 20-Aug-22 20-Aug-22
H/O Outside P/R Fdn 30 days 30-Aug-22 28-Sep-22 2 Vibro Roller
H/O WTP Elec. Room 1 day 26-Sep-22 26-Sep-22 1 Motor Grader
1 Erection Mechanical Equipment (Indoor) 40 days 01-Sep-22 10-Oct-22 2 DT 10M3
Filtration Water System 10 days 01-Sep-22 10-Sep-22 Dedicated equipment for
UF UNIT A 476m3/hr 27,000kg 5 Pcs 5 days 01-Sep-22 05-Sep-22
UF UNIT B 476m3/hr 27,000kg 5 Pcs 5 days 06-Sep-22 10-Sep-22
Chemical Injection System 19,5 days 10-Sep-22 29-Sep-22
H2SO4 DOSING TANK Ø1000x1300H 2,760kg 0,5 days 24-Sep-22 24-Sep-22
NaOH DOSING TANK Ø1000x1300H 1,790kg 0,5 days 24-Sep-22 24-Sep-22
FeCI3 DOSING TANK A Ø1000x1300H 1,650kg 0,5 days 25-Sep-22 25-Sep-22
FeCI3 DOSING TANK B Ø1000x1300H 1,650kg 0,5 days 25-Sep-22 25-Sep-22
NaOCI DOSINH TANK Ø1000x1300H 1,470kg 0,5 days 26-Sep-22 26-Sep-22 2 Vibro Roller
SBS DOSING TANK Ø1000x1300H 1,520kg 0,5 days 26-Sep-22 26-Sep-22 2 Vibro Roller
ANTICALANT DOSING TANK Ø1000x1300H 1,910kg 0,5 days 27-Sep-22 27-Sep-22 1 Motor Grader
SODIUM BACARBONATE INJECTION TANK Ø1200x1600H 2,470kg 0,5 days 27-Sep-22 27-Sep-22 2 DT 10M3
CaCI2 DISSOLVING TANK FOR POTABLE WATER Ø1200x1600H 2,690kg 0,5 days 28-Sep-22 28-Sep-22 Dedicated equipment for
R0 CIP TANK Ø2400x2600H 13,300kg 2 days 20-Sep-22 21-Sep-22
UF CIP TANK Ø2400x2600H 13,380kg 2 days 22-Sep-22 23-Sep-22
R0 CIP CATRIGDE FILTER Ø1012x1270H 1,050kg 0,5 days 28-Sep-22 28-Sep-22
UF CIP CATRIGDE FILTER Ø1012x1270H 1,050kg 0,5 days 29-Sep-22 29-Sep-22 2 Vibro Roller
H2SO4 DOSING PUMP A 10L/hr x 5bar.g 18kg 0,5 days 10-Sep-22 10-Sep-22 1 Motor Grader
H2SO4 DOSING PUMP B 10L/hr x 5bar.g 18kg 0,5 days 10-Sep-22 10-Sep-22 2 DT 10M3
NaOH DOSING PUMP A FOR BWRO 10L/hr x 5bar.g 22kg 0,5 days 11-Sep-22 11-Sep-22 Dedicated equipment for
NaOH DOSING PUMP B FOR BWRO 10L/hr x 5bar.g 22kg 0,5 days 11-Sep-22 11-Sep-22
NaOH DOSING PUMP A FOR MMF 15L/hr x 5bar.g 45kg 0,5 days 12-Sep-22 12-Sep-22
NaOH DOSING PUMP B FOR MMF 15L/hr x 5bar.g 45kg 0,5 days 12-Sep-22 12-Sep-22
FeCI3 DOSING PUMP A FOR MMF 20L/hr x 5bar.g 40kg 0,5 days 13-Sep-22 13-Sep-22
FeCI3 DOSING PUMP B FOR MMF 20L/hr x 5bar.g 40kg 0,5 days 13-Sep-22 13-Sep-22
NaOCI DOSINH PUMP A FOR POTABLE WATER 1L/hr x 5bar.g 40kg 0,5 days 14-Sep-22 14-Sep-22
NaOCI DOSINH PUMP B FOR POTABLE WATER 1L/hr x 5bar.g 40kg 0,5 days 14-Sep-22 14-Sep-22
NaOCI DOSING PUMP A FOR UF TMC 1400L/hr x 5bar.g 110kg 0,5 days 15-Sep-22 15-Sep-22
NaOCI DOSING PUMP B FOR UF TMC 1400L/hr x 5bar.g 110kg 0,5 days 15-Sep-22 15-Sep-22
SBS DOSING PUMP A FOR SWRO 25L/hr x 5bar.g 22kg 0,5 days 16-Sep-22 16-Sep-22
SBS DOSING PUMP B FOR SWRO 25L/hr x 5bar.g 22kg 0,5 days 16-Sep-22 16-Sep-22

Page 1 of 2
Total SCHEDULE September 2022
No. Description Single Equipment Weight Total Weight
Unit
Duration Remaks
Start Finish 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

ANTISCALANT DOSING PUMP A FOR SWRO 30L/hr x 5bar.g 45kg 0,5 days 17-Sep-22 17-Sep-22
ANTISCALANT DOSING PUMP B FOR SWRO 30L/hr x 5bar.g 45kg 0,5 days 17-Sep-22 17-Sep-22
ANTISCALANT DOSING PUMP A FOR BWRO 7L/hr x 5bar.g 45kg 0,5 days 18-Sep-22 18-Sep-22
ANTISCALANT DOSING PUMP B FOR BWRO 7L/hr x 5bar.g 45kg 0,5 days 18-Sep-22 18-Sep-22
R0 CIP PUMP A 300m3/hr x 3bar.g 1,150kg 0,5 days 19-Sep-22 19-Sep-22
R0 CIP PUMP B 300m3/hr x 3bar.g 1,150kg 0,5 days 19-Sep-22 19-Sep-22
UF CIP PUM A 302m3/hr x 3bar.g 1,150kg 0,5 days 20-Sep-22 20-Sep-22
UF CIP PUM B 302m3/hr x 3bar.g 1,150kg 0,5 days 20-Sep-22 20-Sep-22
Demineralization water system 4 days 11-Sep-22 14-Sep-22
EDI UNIT A 95m3/hr 7,700kg 2 days 11-Sep-22 12-Sep-22
EDI UNIT B 95m3/hr 7,700kg 2 days 13-Sep-22 14-Sep-22
Desalination Water System 33 days 01-Sep-22 03-Oct-22
MICRON CARTRIDGE FILTER A FOR SWRO ø1152x1435H 2,100kg 1 day 13-Sep-22 13-Sep-22
MICRON CARTRIDGE FILTER B FOR SWRO ø1152x1435H 2,100kg 1 day 14-Sep-22 14-Sep-22
SWRO UNIT A 200m3/hr 39,600kg 2 Pcs 3 days 10-Sep-22 12-Sep-22
SWRO UNIT B 200m3/hr 39,600kg 2 Pcs 3 days 13-Sep-22 15-Sep-22
MICRON CARTRIDGE FILTER A FOR BWRO Ø660x1170H 1,050kg 1 day 18-Sep-22 18-Sep-22
MICRON CARTRIDGE FILTER B FOR BWRO Ø660x1170H 1,050kg 1 day 19-Sep-22 19-Sep-22
BWRO UNIT A 100m3/hr 10,500kg 1 Pc 2 days 16-Sep-22 17-Sep-22
BWRO UNIT B 100m3/hr 10,500kg 1 Pc 2 days 18-Sep-22 19-Sep-22
INSTRUMENT AIR RECEIVER TANK Ø1600x2500H 1,950kg 1 day 29-Sep-22 30-Sep-22
SERVICE AIR RECEIVER TANK Ø1600x2500H 770kg 1 day 30-Sep-22 01-Oct-22
SWRO HIGHPRESSURE PUMP A 476m3/hr x 30bar.g 15,000kg 3 days 01-Sep-22 03-Sep-22
SWRO HIGHPRESSURE PUMP B 476m3/hr x 30bar.g 15,000kg 3 days 04-Sep-22 06-Sep-22
SWRO HIGHPRESSURE PUMP C 476m3/hr x 30bar.g 15,000kg 3 days 07-Sep-22 09-Sep-22
2 Erection Mechanical Equipment (Outdoor) 23 days 29-Sep-22 21-Oct-22
Filtration Water System 12 days 29-Sep-22 10-Oct-22
MULTI MEDIA FILTER A ø3600x9500L 26,500kg 3 days 29-Sep-22 01-Oct-22
3 Piping Work WTP 85 days 22-Aug-22 14-Nov-22
Fabrication piping spool 11,528DI 11,528 51 days 22-Aug-22 11-Oct-22
Piping Work Inside WTP 8,845DI 8,845 20 days 21-Sep-22 10-Oct-22

II WWTP AREA
Steel Structure Installation 15 days 06-Sep-22 20-Sep-22

III FIRE FIGHTING


Zone 4 AIS
F/F Main Ring Pipe Support (Sleeper) 45 08-Aug-22 21-Sep-22