ON SITE
EQUIP. PACKAGE SHIP NO. PO ISSUE FAT FOB Quantity Unit REMARK
FORECAST ACTUAL

SIW MATERIAL
Prefabricated Vertical Drain
1 1-Jul-22 5-Jul-22 3926925 m
(PVD)
Cement for CDM 2 2-May-22 25 – Jun-2022 2079.83 Ton

Super Board Drain 3 15-Jul-22 15-Jul-22 74500 m

Main pipe D63 4 15-Jul-22 15-Jul-22 25400 m

Filter pipe D50 5 15-Jul-22 15-Jul-22 230080 m

Geotextile 6 21-Jul-22 21-Jul-22 565000 m2

GeoMembrane 7 30-Jul-22 31-Jul-22 335448 m2

Vacuum pump 8 31-Jul-22 12-Aug-22 300 Nos

PILING WORK

Test pile 1 13-Dec-22 13-Dec-22 12 Pile