NJBPRP PROCUREMENT STATUS

Original
SN Description Type Start Finish RFQ TBE PO 601 602 Delivery 603 Remarks
Duration
PROCUREMENT PHASE 1 201 17-Apr-22 6-Dec-22
CLASS 2: NON ENGINEERED EQUIPMENTS) 132 17-Apr-22 17-Sep-22
CIVIL 17 4-May-22 23-May-22
1 CIVIL CONSUMABLE ITEMS (Paint, Epoxy, Rebar grout, B Non-Engineered 17 4-May-22 23-May-22 Done Done Done n/a n/a Done Done
2 ROOFING MATERIALS Non-Engineered 11 4-May-22 16-May-22 Done Done Done n/a n/a Done Done
MECHANICAL AND PIPING 51 28-May-22 25-Jul-22
3 PROCESS PIPES AND FITTINGS Non-Engineered 51 28-May-22 25-Jul-22 Done Done Done n/a n/a Done Done
4 FIRE WATER PIPES AND FITTINGS Non-Engineered 51 28-May-22 25-Jul-22 Done Done Done n/a n/a Done Done
ELECTRICAL 125 17-Apr-22 8-Sep-22
5 MEDIUM VOLTAGE CABLES MV Non-Engineered 30 17-Apr-22 21-May-22 Done Done Done n/a n/a Done Done
6 LOW VOLTAGE CABLES LV Non-Engineered 96 17-Apr-22 6-Aug-22 Done Done Done n/a n/a Done Done
7 GROUNDING CABLES Non-Engineered 98 17-Apr-22 8-Aug-22 Done Done Done n/a n/a Done Done
8 ELECTRICAL CONDUITS AND FITTINGS Non-Engineered 45 17-Apr-22 7-Jun-22 Done Done Done n/a n/a Done Done
9 ELECTRICAL ACCESORIES (Swithces, sockets and etc) Non-Engineered 44 17-Apr-22 6-Jun-22 Done Done Done n/a n/a Done Done
10 JUNCTION BOX JB Non-Engineered 86 4-May-22 11-Aug-22 Done Done Done n/a n/a Done Done
11 LIGHTING POLE Non-Engineered 78 4-May-22 2-Aug-22 Done Done Done n/a n/a Done Done
12 HIGH MAST Non-Engineered 110 4-May-22 8-Sep-22 Done Done Done n/a n/a Done Done
13 LIGHTING FIXTURES Non-Engineered 108 17-Apr-22 20-Aug-22 Done Done Done n/a n/a Done Done
INSTRUMENTATION 132 17-Apr-22 17-Sep-22
15 INSTRUMENTATION CABLES Non-Engineered 132 17-Apr-22 17-Sep-22 Done Done Done n/a n/a Done Done
16 INSTRUMENTATION CABLE TRAY AND FITTINGS Non-Engineered 102 17-Apr-22 13-Aug-22 Done Done Done n/a n/a 95% Done
17 INSTRUMENTATION JUNCTION BOXES Non-Engineered 102 17-Apr-22 13-Aug-22 Done Done Done n/a n/a Done Done
CLASS 1: ENGINEERED EQUIPMENT 201 17-Apr-22 6-Dec-22
MECHANICAL 69 28-May-22 15-Aug-22
19 FIRE HYDRANT VALVES AND ACCESSORIES Engineered 69 28-May-22 15-Aug-22 Done Done Done Done Done Done Done
ELECTRICAL 163 4-May-22 9-Nov-22
20 TRANSFORMER CATHODIC PROTECTION RECTIFIERS Engineered 163 4-May-22 9-Nov-22 Done Done Done Done Done
21 LIGHTING PANEL BOARDS LPB Engineered 118 4-May-22 18-Sep-22 Done Done Done Done Done Done Done
22 INSTRUMENTATION 201 17-Apr-22 6-Dec-22
23 MOV ACTUATORS Engineered 186 4-May-22 6-Dec-22 Done Done Done Done 90% 60% 50%
24 PRESSURE RELEIF VALVES Engineered 138 17-Apr-22 24-Sep-22 Done Done Done Done Done
25 CONDUCTIVITY ANALYZER Engineered 185 4-May-22 5-Dec-22 Done Done Done Done Done Done
26 FLAME DETECTORS Engineered 177 4-May-22 26-Nov-22 Done Done Done Done Done
27 LEVEL TRANSMITTER Engineered 169 4-May-22 16-Nov-22 Done Done Done Done Done
28 CONTROL VALVE Engineered 182 4-May-22 1-Dec-22 Done Done Done Done Done
29 LEVEL GAUGE Engineered 176 4-May-22 24-Nov-22 Done Done Done Done Done
30 PRESSURE GAUGE Engineered 128 17-Apr-22 12-Sep-22 Done Done Done Done Done Done
31 DP PRESSURE GAUGE Engineered 191 17-Apr-22 24-Nov-22 Done Done Done Done Done Done
32 DIFFERENTIAL PRESSURE TRANSMITTER Engineered 138 17-Apr-22 24-Sep-22 Done Done Done Done Done Done
33 PRESSURE TRANSMITTER Engineered 136 2-Jul-22 6-Dec-22 Done Done Done Done Done Done
ADDITIONAL SCOPE PROCUREMENT 109 21-Jul-22 24-Nov-22
Non-Engineered equipments 80 21-Jul-22 22-Oct-22
34 FW line valves and flanges(16") Non-Engineered 30 18-Sep-22 22-Oct-22 Done Done Done n/a n/a Done Done
35 FW valves and fittings( Drain and Vent replacement) Non-Engineered 4 18-Sep-22 21-Sep-22 Done Done Done n/a n/a Done Done
36 Filter small bore pipes, valves and fittings Non-Engineered 27 7-Sep-22 9-Oct-22 Done Done n/a n/a
37 Fire proofing materials Non-Engineered 13 21-Jul-22 6-Aug-22 Done Done Done Done Done Done Done
38 Electrical cables Non-Engineered 34 14-Aug-22 22-Sep-22 Done Done Done Done Done Done Done
39 Instrument cables Non-Engineered 34 7-Sep-22 17-Oct-22 Done Done Done Done Done Done Done
Original
SN Description Type Start Finish RFQ TBE PO 601 602 Delivery 603 Remarks
Duration
Engineered equipments 89 14-Aug-22 24-Nov-22
40 ESD push button Non-Engineered 89 14-Aug-22 24-Nov-22 Done Done Done Done Done Done Done
Original
SN Description Type Start Finish RFQ TBE PO 601 602 Delivery 603 Remarks
Duration
PROCUREMENT PHASE 2 206 27-Apr-22 8-Feb-23
CLASS 2: NON-ENGINEERED EQUIPMENT 186 8-May-22 23-Jan-23
T-103 AND T-109 Non-Engineered 155 16-May-22 16-Dec-22
41 Main Plates Non-Engineered 104 16-May-22 6-Oct-22 Done Done Done n/a n/a Done Done
42 Structural Non-Engineered 72 18-Aug-22 25-Nov-22 Done Done Done n/a n/a 80%
43 Nozzles, Pipes & Fittings Non-Engineered 80 29-Aug-22 16-Dec-22 Done Done Done n/a n/a 50%
44 Welding Consumables Non-Engineered 40 1-Aug-22 25-Sep-22 Done Done Done n/a n/a Done
45 Paint Non-Engineered 38 8-Jun-22 31-Jul-22 Done Done Done n/a n/a Done Done
T-102 PROCUREMENT 224 8-May-22 23-Jan-23
CIVIL 174 8-May-22 26-Nov-22
47 STRUCTURAL PLATFORM Non-Engineered 174 8-May-22 26-Nov-22
MECHANICAL 62 13-Nov-22 23-Jan-23
48 CARBON STEEL PIPE Non-Engineered 52 13-Nov-22 11-Jan-23 Done Done n/a n/a Done
49 PIPE FITTINGS Non-Engineered 62 13-Nov-22 23-Jan-23 Done Done n/a n/a Done
50 PIPE PAINTING MATERIALS Non-Engineered 52 13-Nov-22 11-Jan-23 Done Done n/a n/a Done
CLASS1: ENGINEERED EQUIPMENTS 206 27-Apr-22 8-Feb-23
51 Foam Chambers Engineered 113 5-Sep-22 8-Feb-23 Done Done Done Done Done 50%
52 Cathodic Protection Engineered 75 27-Apr-22 9-Aug-22 Done Done Done Done Done
53 Free Vent/Guage hatch Engineered 100 19-Sep-22 5-Feb-23 Done Done Done Done Done 40%
54 Floating Roof Seal Engineered 150 27-Apr-22 22-Nov-22 Done Done Done Done Done
55 RADAR TANK GAUGE Engineered 70 14-Aug-22 2-Nov-22 Done Done Done Done Done Done
ITEM DESCRIPTION UoM QTY TAGS LOCATION

BALL VALVE WITH MOTORISED X07-MOV-


EA 1 LAUNCHING STATION
ACTUATOR 177
BALL VALVE WITH MOTORISED EA 1 X07-MOV- LAUNCHING STATION
ACTUATOR 176

ACTUATOR (ROTORK) EA 1 X07-MOV- SHIPPING FACILITY


154 SEPARATOR/KEROSENE FILTER SKID

X07-MOV- SHIPPING FACILITY


ACTUATOR (ROTORK) EA 1
1009 SEPARATOR/KEROSENE FILTER SKID

X07-MOV- SHIPPING FACILITY


ACTUATOR (ROTORK) EA 1 153 SEPARATOR/KEROSENE FILTER SKID

X07-MOV- SHIPPING FACILITY


ACTUATOR (ROTORK) EA 1
1008 SEPARATOR/KEROSENE FILTER SKID

ACTUATOR (ROTORK) EA 1 X07-MOV- SHIPPING FACILITY


152 SEPARATOR/KEROSENE FILTER SKID

X07-MOV- SHIPPING FACILITY


ACTUATOR (ROTORK) EA 1
1007 SEPARATOR/KEROSENE FILTER SKID

X07-MOV-
ACTUATOR (ROTORK) EA 1 SHIPPING AREA PIPE WAY
1519
X07-MOV-
ACTUATOR (ROTORK) EA 1 MAIN PIPE WAY
164

ACTUATOR (ROTORK) EA 1 X07-MOV- MAIN PIPE WAY


162

ACTUATOR (ROTORK) EA 1 X07-MOV- MAIN PIPE WAY


163

ACTUATOR (ROTORK) EA 1 X07-MOV- MAIN PIPE WAY


165
X07-MOV-
ACTUATOR (ROTORK) EA 1 122 Kerosene Tank X07-T-109

X07-ZV-
ACTUATOR (ROTORK) EA 1 0221 MAIN PIPE WAY

FLOWSERVER ACTUATOR EA 1 5Z02-MOV- MAIN PIPE WAY


049

FLOWSERVER ACTUATOR EA 1 5Z02-MOV- MAIN PIPE WAY


050

FLOWSERVER ACTUATOR EA 1 5Z02-MOV- MAIN PIPE WAY


051