SAN MIGUEL FOODS DAVAO

8-Oct-21 rev_7.8
M1 > M11

SCOPE

M0
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
DownPayment = > 1 Jul 2020 ###

Equipments delivery by NLINE


SHIPMENT#1 ; end Mar 2021 ; done
B3-B10 Belt conveyor frame | parts
SHIPMENT#2 ; end June 2021 ; done
Roller|bracket
Belt cov.
Frame (70%)
B1-B2
Rail for portable receiver
B3-B10 Top cover casing
B3-B12 Take-up frame
CT Control Tank
E1-E8 Intermediat trunking
Aspiration system for cleaning tower
Aspiration system for tower 0|1|2|3
SHIPMENT#3 ; end Aug 2021 ; done
Belt cov.
Remaining Frame (30%)
B1-B2
B11-B12 U-Frame
Roller|bracket
Bucket elev. Head casing
E1-2-5-6-7 Remaining trunking
Chain conv. All Trunking
NCC500F Chain link with flight
Chain conv. All Trunking
NCC300F Chain link with flight
BM1-BM2 Belt magnet
WG3|WG4 Top and bottom hopper
SHIPMENT#4 ; etd End Oct 2021 ;
WG1|WG2 Top and bottom hopper
Belt cov. Head|Tail frame
B1-B2 Pulley
B3-B10 Head|Tail frame
All pulley
B11-B12 Head|Tail frame
All Pulley
accessories putty
SHIPMENT#5 ; etd Jan2022 - Aug2022
B1-B2 Zipper car|cover
B11-B12 Tripper car
Drum sieve = 6
Warehouse intake hopper
Warehouse grating
DSH support
Valves and spouting
Spot filters
Air Compressor
Compressed air materials
Instruments
Automation system (MCP|PLC cabinet)
Shipped Rubber Belting
directly to BE Cups
Davao DSH hopper
SHIPMENT#6 (wait for VO)
NCC1200F=4 Head|Tail casing wait for VO
All Trunking wait for VO
Chain link with flight wait for VO
FABRICAT
NCC300F=4 Head|Tail casing wait for VO
WORK
All Trunking wait for VO
Chain link with flight wait for VO
PSV 1100x525 = 1 wait for VO
SILO SHIPMENT
Prado silo #1-5

All necessary civil foundation works by SMF


Foundation for conveyor along jetty|causeway
Foundation for Transfer tower No.0|1|2|3|A-frame
Foundation for 5 units steel silo & A-frame
Cleaning tower foundation|structure installation
Foundation for Bulk load-out bins
Flat storage warehouse

Local works by Fabwerx


Permit, Seminars, Insurances
Site preparation
Structural work erection
Transfer tower0|Aframe
Transfer tower1|Aframe

Archen approve
Transfer tower2|Aframe

drawing
Transfer tower3|Aframe
Box truss above SILO|AFrame
Bulk loading bins
Warehouse Conveyor Supports
Machine erection
Jetty Receiving Belt conveyor x 2
Causeway Transfer Belt conveyor x 8
Aspiration system
Cleaning Bucket elevator x 8
tower Chain Conveyor x 4
Drum sieve x 6
Hopper scale x4
Aspiration system
Bulk bin Transfer Chain Conveyor to Bulk Loadout x4
Warehouse Tripper belt conveyor x 2
Chain conveyor underneath warehouse x 3
Silo Roof | Wall | Stair | Auger | Side hopper
Chain Conv. underneath SILO x 4
Chain Conv. above SILO x 4
Compressed air system
Electrical Works
LVSG | MCC
Power Cables | CableTray | Conduit installation
Instruments
MCP | PLC
Control cable installation
Testing | commissioning
DS DAVAO Project _ Master Erection Schedule
CIVIL WORK FW Structural Fabrication FW Customs C
N-Line supply FW Shipment FW Installatio
M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31

May-22
Nov-21

Aug-22

Nov-22
Dec-21

Dec-22
Mar-22

Sep-22
Feb-22

Jun-22
Oct-21

Apr-22

Oct-22
Jan-22

Jan-23
Jul-22
FABRICATION
WORK
2 site office | meeting room | electricity | toilet.. etc
months

S1 S2 S3 S4 S5
wait for VO
wait for VO

FABWERX SUPPLY
FABWERX SUPPLY

NLINE SUPPLY
NLINE SUPPLY
FABWERX SUPPLY
hedule
FW Customs Clearance & Delivery
FW Installation
M31 M32 M33 M34
Mar-23
Feb-23

Apr-23
Jan-23