You are on page 1of 5

HYDROCK WELLS, INC.

PROJECT: DRILLING OF DEEP WELL NO. 2 &


RELATED WORKS

METHOD STATEMENT

OF

WELL DEVELOPMENT
BY AIRLIFTING METHOD

Revisions Details

Contractor: Date of issue: 2-Nov.-2021 Page No. 1 of 6


HYDROCK
Identification Document Number:
WELLS, INC.

SMFI/ATI-BULK WATER/HWI PROJECT MS/002/REV.0


Document No. MS 002
Rev. 0
METHOD STATEMENT OF WELL
DEVELOPMENT BY AIRLIFTING Date of Issue 2-Nov-2021
Page No.: 2 of 6

CONTENTS

1 SCOPE:............................................................................................................................................................ 3

2 SITE PREPARATION: ...................................................................................................................................... 3

3 REFERENCES: ................................................................................................................................................ 3

4 RESOURCES: .................................................................................................................................................. 3

4.1 Personnel: .................................................................................................................................................... 3

5 DEFINITIONS & ABBREVIATIONS: ................................................................................................................. 3

6 QUALITY CONTROL:...................................................................................................................................... 3

7 SEQUENCE OF WORK: .................................................................................................................................. 4

8 SAFETY: ......................................................................................................................................................... 4
Document No. MS 002
Rev. 0
METHOD STATEMENT OF WELL
DEVELOPMENT BY AIRLIFTING Date of Issue 2-Nov-2021
Page No.: 3 of 6

1 SCOPE:

➢ This Method Statement describes the methodology that will be used for the well
development by airlifting method.

2 SITE PREPARATION:

➢ Contractor shall make site visit to ensure that site conditions is permitted to work as
per issued construction drawings and approved shop drawings.

➢ Part of area near Deep Well No. to be closed for traffic.

3 REFERENCES:

o Project Specifications.
o Construction Drawings issued for construction
o Approved Shop Drawings

4 RESOURCES:

4.1 Personnel:

• Project In-charge
• Site Foreman
• Safety Officer
• Lead Driller
• Driller
• Air compressor operator

5 DEFINITIONS & ABBREVIATIONS:


P.I.C - Project In-charge
FM - Foreman
SO - Safety Officer

6 QUALITY CONTROL:

6.1 All site activities will be in compliance with site quality plan.

6.2 Only approved material and plant will be used on site and unsuitable material will be
cart away as per the Engineer’s direction.

6.3 All required tests will be carried out as per specification and reports will be forwarded
to the Engineer for review and approval.
Document No. MS 002
Rev. 0
METHOD STATEMENT OF WELL
DEVELOPMENT BY AIRLIFTING Date of Issue 2-Nov-2021
Page No.: 4 of 6

7 SEQUENCE OF WORK:

7.1 Well Development

7.1.1 Development by airlifting method using air compressor.

7.1.2 Mobilize 750 cfm Air compressor and well site.

7.1.3 Install air line.

7.1.4 Prepare or locate existing canals for discharge water.

7.1.5 Conduct airlifting for 12 hours.

8 SAFETY:

8. 1 All works shall comply with the safety instructions of site safety manual and
all safety recommendations shall be followed.

8.2 All workers will be given safety induction training by the safety officer before
starting work & necessary personal protective equipment to be used by all
workers.

8.3 Care will be taken in handling materials during loading, unloading & shifting
to working area.

8.4 Secure access roads will be provided to the different working areas.

8.5 All personal protective equipment shall be used as appropriate according to


the nature of the different jobs involved.

8.6 Adequate lighting shall be provided during night shift work.

8.7 Good cleaning and housekeeping shall be maintained overall


Document No. MS 002
Rev. 0
METHOD STATEMENT OF WELL
DEVELOPMENT BY AIRLIFTING Date of Issue 2-Nov-2021
Page No.: 5 of 6

Site preparation layout for closure of area for traffic.