9. Applicator's Method Statement.

Khalifa Bin Zayed Street


Development, Al Ain
Project Client Consultant Contractor

Project: Khalifa Bin Zayed Street Development, Al Ain

Method Statement
for
HARDSCAPE WORKS

Ref. BAS-OTK-KBZ-MS-0012-00

Revision Date Prepared by Reviewed by Endorsed by Approved by Status

Basatin Basatin Sr. Project


Consultant
QA/QC TE Manager
29-01-
00 Abdul Latheef Baker Abdullah Aiham Tayar
2024

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 1 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

Contents
1. PURPOSE .......................................................................................................................... 3
2. SCOPE .............................................................................................................................. 3
3. LEGISLATION AND CODE OF PRACTICE .............................................................................. 3
4. REFERENCES ..................................................................................................................... 4
5. DEFINITIONS .................................................................................................................... 4
6. RESOURCE ........................................................................................................................ 5
6.1 MATERIAL AND THEIR APPROVAL ........................................................................................................................... 5
6.2 SUBCONTRACTOR APPROVAL ................................................................................................................................ 5
6.3 TOOLS & EQUIPMENT ......................................................................................................................................... 5
6.4 SHOP DRAWING APPROVAL .................................................................................................................................. 5
7. RESPONSIBILITIES ............................................................................................................. 5
7.1 SR. PROJECT MANAGER ...................................................................................................................................... 5
7.2 CONSTRUCTION MANAGERS AND PROJECT ENGINEERS.............................................................................................. 6
7.3 TECHNICAL ENGINEER ......................................................................................................................................... 6
7.4 QA/QC ENGINEER............................................................................................................................................. 6
7.5 SITE ENGINEER .................................................................................................................................................. 7
7.6 QUANTITY SURVEYOR ......................................................................................................................................... 7
7.7 SAFETY OFFICERS ............................................................................................................................................... 7
7.8 SURVEYOR ........................................................................................................................................................ 8
7.9 SITE SUPERVISORS .............................................................................................................................................. 8
7.10 FOREMAN ...................................................................................................................................................... 8
7.11 DOCUMENT CONTROLLER .................................................................................................................................. 8
8. DETAILED CONSTRUCTION METHODOLOGY ...................................................................... 9
8.1 GENERAL: ......................................................................................................................................................... 9
8.2 METHOD KERBSTONE INSTALLATION.................................................................................................................... 10
8.3 METHOD FOR PAVING INSTALLATION ON 50MM THICK BLACK SAND BEDDING ((VEHICULAR & PEDESTRIAN) ................... 11
8.4 INSTALLATION OF HAZARD WARNING TACTILE-BLISTER........................................................................................... 14
8.5 METHOD FOR INSTALLATION- GRANITE PAVER ...................................................................................................... 15
8.6 CAST-IN-SITU METHODOLOGY (GENERAL)............................................................................................................ 15
8.7 METHOD OF METAL EDGE INSTALLATION ........................................................................................................... 18
8.8 RAISED CROSS WALK PAVING (PEDESTRIAN CROSSINGS TABLE) ................................................................................ 19
8.9 WHEEL STOPPER INSTALLATION .......................................................................................................................... 20
9. HSEW REQUIREMENTS: .................................................................................................. 21
9.1 HEALTH SAFETY REQUIREMENTS: ........................................................................................................................ 21
9.2 EMERGENCY PROCEDURE .................................................................................................................................. 22
9.3 ENVIRONMENTAL REQUIREMENTS: ...................................................................................................................... 23
9.4 HOUSEKEEPING ............................................................................................................................................... 23
10. INSPECTION AND TESTING PLAN (ITP) ............................................................................. 23
11. RECORDS: ....................................................................................................................... 23
12. DISTRIBUTION: - ............................................................................................................. 23
13. ATTACHMENT ................................................................................................................ 24

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 2 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

1. PURPOSE
This method statement is applicable to define the step-by-step procedures and to ensure that the
procedures for Hardscape works in the project are executed safely and in accordance with the contract
requirements, hazard and safety precautions implemented and all the Quality Assurance / Quality
Control activities are conducted in a systematic manner, work inspected and documented.

2. SCOPE
This method statement pertains to the hardscape works outlined in the project, encompassing the
following:

1. Precast concrete Kerbstone installation


2. Precast concrete paver installation (Vehicular & Pedestrian)
3. Hazard warning tactile blister tile installation
4. Granite tiles installation
5. Raised Cross Walk Paving (Pedestrian Crossings Table)
6. Precast Concrete Steps Installation
7. Metal Edging
8. Pedestrian Crossings
9. Wheel Stopper Installation

3. LEGISLATION AND CODE OF PRACTICE


1. Al Ain City Municipality (AACM) Regulations and Guidelines.
2. Standard Specification- ADM Landscape and Public Realm by Department of Municipalities and
Transport (DMT), Abu Dhabi City Municipality.
3. ADQCC: Abu Dhabi Quality and Conformity Council
4. All applicable Local Regulatory Authority requirements and regulations.
5. UAE Labor Code of Practices.
5.1. OSHAD SF - CoP - 02.0 - Personal Protective Equipment
5.2. OSHAD SF - CoP - 03.0 - Occupational Noise
5.3. OSHAD SF - CoP - 03.1 - Vibration
5.4. OSHAD SF - CoP - 04.0 - First Aid and Medical Treatment
5.5. OSHAD SF - CoP - 08.0 - General Workplace Amenities
5.6. OSHAD SF - CoP - 09.0 - Workplace Wellness
5.7. OSHAD SF - CoP - 11.0 - Safety in the Heat
5.8. OSHAD SF - CoP - 14.0 - Manual Handling and Ergonomics
5.9. OSHAD SF - CoP - 17.0 - Safety Signage and Signals
5.10. OSHAD SF - CoP - 21.0 - Permit to Work
5.11. OSHAD SF - CoP - 22.0 - Barricading of Hazards
Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.
MS for Hardscape Works 00 1 29-01-2024 Page 3 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

5.12. OSHAD SF - CoP - 25.0 – Driver Fatigue Prevention


5.13. OSHAD SF - CoP - 29.0 –Excavation
5.14. OSHAD SF - CoP - 36.0 - Plant and Equipment
5.15. OSHAD SF - CoP - 51.0 - Powered Lift Trucks
5.16. OSHAD SF - CoP - 53.0 - OSH Management During Construction Work
5.17. OSHAD SF - CoP - 54.0 - Waste Management

4. REFERENCES
1. Project Specifications
2. IFC Drawing and Shop Drawings.
3. Material Approvals / Manufacturer Recommendation
4. BOQ
5. Approved Project Quality Plan
6. Approved HSE Plan
7. No Objection Certificate
8. Permit to work.

5. DEFINITIONS
Definitions used within this document is detailed within the text shall have the meanings indicated
below unless otherwise clearly indicated by context of the use.

1. Project : Khalifa Bin Zayed Street Development, Al Ain


2. Employer : Department of Municipalities and Transport (DMT)
3. Engineer : Otak International
4. Contractor : Basatin Landscaping LLC
5. PQP : Project Quality Plan.
6. MS : Method Statement.
7. ITP : Inspection & Test Plan.
8. RA : Risk Assessment
9. ITL : Independent Testing Laboratory.
10. WIR : Work Inspection Request.
11. MIR : Material Inspection Request.
12. HSEW : Health, Safety, Environment and Welfare.
13. IFC : Issued for Construction.
14. SD : Shop Drawing.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 4 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

6. RESOURCE

6.1 Material and their approval


All materials used on site have to be approved prior to starting any work. The following list is a
summary of key materials to be used for the activities.

Material List

1. Geotextile Fabric 6. Kerbs- Flush, Heel, Drop and Transition


2. Subbase 7. Blister tiles
3. Black Sand 8. River Pebbles
4. Cement sand mortar 9. Metal edges
5. Precast Paving Tiles 10. Concrete C40, C20

6.2 Subcontractor approval


External organization, executing part works on behalf of contractor, based on a specified (sub)
contract with approved prequalification.

6.3 Tools & Equipment


1. JCB Excavator 7. Grinders
2. JCB Tele handler 8. Plate Compactor
3. Bobcat 9. Rubber Hammer
4. Mobile Roller Compactor 10. Pointed hand shovel.
5. Air Compressor 11. Wood & Steel saw
6. Drills & Drill Bits

6.4 Shop drawing approval


The shop drawings will be prepared based on the issued contract drawings, which will include all
necessary additional information and details to enable proper execution of the works. Shop
drawings submittals are to be complete with respect to dimensions, design criteria, materials,
connections, bases, foundations, anchors, etc. and will be accompanied by technical and
performance data (as necessary) to fully illustrate the information in the drawings.

7. RESPONSIBILITIES

7.1 Sr. Project Manager


 Direct all construction operations, responsible for skilled person and staff members, while
responsible for direction, leadership, and control.
 Responsible for strategic planning.
 Responsible for cost control and budget to avoid overruns.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 5 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

 Create and manage the master construction schedule for more than one project.
 All operational issues, involving, people, skills, plant, financial.
 Responsible for effectiveness, and efficiency of staff, plant, materials, logistics, Procurement,
subcontractor, management.
 Client relationship & Staff relationships, grading, training, recruitment, and terminators.
 Coordinates all facets of construction to ensure overall performance, with regards to budget,
planning, technical, and value engineering.
 Manage staff development and ensure performance standards.
 Ensure efficient use of human resources, and grading of staff, to increase or decrease current
positions.
 Mange subcontractor performance.
 Responsible for site cost implementation records and monitoring of set budget.
 Ensure QA-QC Standards are set to be implemented and met.
 Ensure HSE Standards are set, implemented, and met.
 Overall responsibility or site safety.

7.2 Construction Managers and Project Engineers


 Implement and maintain a successful completion of the work.
 Communicate this Method Statement to his subordinates.
 Provide his subordinates with the information they need to carry out their responsibilities.
 Enforce the application of this document once it is approved.
 Stop all unsafe work activities.
 Ensure the Health and Safety of the personnel on the site.
 Ensure that the requirements of the Project Specifications and relevant ITP is followed and
implemented during construction.
 He shall coordinate with Engineer / Employer authorities and arrange the necessary
arrangements and to ensure that proper control measures are enforced for performing the
activities as per Engineer / Employer expectations.

7.3 Technical Engineer


 Check tolerance, dimensions, and fabrication feasibility of designs and works with Engineers to
resolve problem.
 Adjust current drawings and recommend changes based on their understanding and knowledge
of the project.
 Follow project schedules and meet project due dates.
 Meet all project specifications and formatting within the company principles.
 Work closely to Project managers and project engineers to make sure that the design is precise,
also to ensure and that contract responsibilities are met.
 Review and interpret Client specifications.

7.4 QA/QC Engineer


 Maintain all quality records properly documented.
 Conduct inspections and monitor the required tests.
 Determining and reporting any non-conformance to the QC Manager.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 6 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

 Checking compatibility between production processes, test procedures and the applicable
documentation through review and circulation of the technical and administration document
related to the various activities.
 Ensuring all personnel are fully aware with all the quality requirements and application for all
quality documents as relevant to their discipline.
 Ensuring appropriate supervision for all work activities enabling quality related operations to be
effectively covered.
 Coordinate with the Independent Testing laboratory representative so that all test is carried out
as required by specification and records as per the Quality Control Plan.
 Stop all unsafe and substandard work activities.

7.5 Site Engineer


 The Engineers are responsible for the implementation and execution of day-to-day activities in
safe manner.
 He shall arrange the manpower, equipment and materials required for the implementation of
activities to meet the target schedule in quality and safe manner, coordination with HSE officers,
QC Engineers and progress the involved tasks in accordance with specifications, method
statement and approved Risk Assessment.
 He shall maintain project schedule by monitoring project progress; coordinating activities;
resolving problems.
 He shall raise WIRs as per approved ITPs.

7.6 Quantity Surveyor


 Price/forecast the cost of the varied materials needed for the project.
 Prepare tender documents, contracts, budget, bill of quantities and other documentation.
 Track changes to the design and/or construction work and adjusting budget projection
accordingly.
 Measure and value the work done on site.

7.7 Safety Officers


 He shall be responsible for ensuring that all involved personnel are following PPE regulations
and safe work practices.
 He shall be responsible for conducting work site inspection to ensure that all activities are
performing as per Engineer / Employer standards and procedures.
 He shall ensure that activities are performing as per Engineer / Employer work system.
 He shall maintain all relevant documents related to the activity.
 He shall lead HSE communication with workforce to encourage reporting of incidents including
incident, hazard identification, risk management and emergency preparedness.
 He shall ensure that all personnel attend HSE induction prior to the site assignment and strictly
follow HSE regulations.
 Implement the “No Smoking” rule at workplace.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 7 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

7.8 Surveyor
 The Surveyor will be responsible for all survey activities, control points, recording of survey data
as well as control and calibration of survey instruments.

7.9 Site supervisors


 Incorporate HSE instructions in routine orders and see that they are obeyed always.
 Ensure that all machinery and plant, including power and hand tools, are maintained in good
order.
 Ensure the quality and safety of the work being performed and proper housekeeping.
 Make the necessary preventive action as to minimize the noise production during working hours.
 Monitor that new employees are adequately trained and supervised always and comply with
safety precautions.
 Organize the site activities safely and systematically so that work can be carried out as per the
required standard without any impact to workforce, equipment, materials and to the
environment.
 Monitor that the Personal Protective Equipment of the work force are enough for current work
at hand.
 Conduct daily "Toolbox Talks” and in advance of any critical work and enforce proper PPEs as
per task.

7.10 Foreman
 Preparation and execution the works at site as per the approved drawings.
 Mange the required team at site.
 Ensure the quality and safety of the work being performed and proper housekeeping.
 Make the necessary preventive action to minimize the noise production during working hours.
 Monitor that new employees are adequately trained and supervised always and comply with
safety precautions.
 Organize the site activities safely and systematically so that work can be carried out as per the
required standard without any impact to workforce, equipment, materials and to the
environment.
 Monitor that the Personal Protective Equipment of the work force are enough for current work
at hand.
 Conduct daily "Toolbox Talks” and in advance of any critical work and enforce proper PPEs as
per task.

7.11 Document Controller


 Leads the Contractor’s Document Controller on proper document numbering as per procedure.
 Generates transmittal of project technical documents and maintain track of document revisions.
 Monitors and maintain Document Register for all technical documents.
 Maintain Common access server for easy access of project documents.
 Monitor and track correspondence of Client and Contractors.
 Support Consultant Engineers for formatting of documents and subsequent submission to the
client.
 Responsible on preparing Monthly Progress Report to be submitted to Client.
Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.
MS for Hardscape Works 00 1 29-01-2024 Page 8 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

 Attend weekly progress meeting and responsible for preparing Minutes of Meeting.

8. DETAILED CONSTRUCTION METHODOLOGY

8.1 General:
 Method listed in the references above shall be followed for the relevant works.
 Relevant Personal Protective Equipment shall be provided and utilized by the workforce.
 Appropriate Safety guidelines must be adhered during all stages of construction activity.
 Necessary & mandatory work permit from the Authority shall be available prior to the start of the
activities.
 Work area shall be barricaded as applicable and necessary.
 Required safety sign boards shall be placed at the area.

8.1.1 Pre-commencement Requirements:


 Ensure that the relevant permits / PTW (if applicable) are obtained from the authorities, prior to
commencement of the activity.
 Latest revision for drawings should be available at site, prior to start of activity.
 Employ fully qualified and experienced personnel who have had the previous experience on
comparable installations.
 Ensure proper coordination with other disciplines so that all relevant personnel are aware of the
requirements. Ensure that relevant permit to work is obtained from the appropriate civil
contractor, if required.
 Ensure that the work area is safe and that all constraints on operations have been identified and
necessary precautions have been taken.
 Arrange all necessary personnel, plant equipment and services as required for the works and
ensure adequate lighting, temporary power (where applicable) and access arrangements.

8.1.2 Preparatory Works and Construction Procedures


The construction will comprise the following, but not necessarily sequential, stages:
 Lay-down areas and other initial preparatory works.
 Material delivery to site
 Initial construction works.
 Reinstatement works.

8.1.3 Delivery, Storage and Handling


All records of stock materials at the storage area will be recorded and labelled stating intended
location for installation on the project. All materials will be marked and monitored by the Basatin
Landscaping Store-Keeper Materials for each task/zone will be stored separately. Adequate
ventilation will provide for storage area. Unless materials are near the intended installation area and
are in the process of installation, materials will be protected as appropriate. Protective
tapes/coverings will be made to protect the stored materials of unique nature and specification,
Materials will be stocked in groups to increase efficiency of site deliveries.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 9 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

8.1.4 Production from Suppliers


The Basatin Landscaping Purchasing department will liaise with the QS and QA/QC department and
prepare a detailed material list for each item in accordance with the approved shop drawings. The
first sample of each item will be submitted to the Basatin Landscaping Project Manager for approval
and the production process will continue as per schedule. Each product/item will be labeled with a
unique number for its identity. Supplier’s Quality control will take care of the quality issues if any of
the material once approved and passed by their QC team. The materials will then be stacked in
pallets, protection wrapped around them awaiting delivery call off from site. When materials
delivered to site Basatin Landscaping QA/QC Engineer along with the storekeeper will inspect all
goods for conformity. If a non-conformance arises Basatin Landscaping will issue the supplier with an
NCR. The storekeeper and Basatin Landscaping Logistics Team will ensure safety and soft handling of
all delivered materials.

8.1.5 Site Inspection


Prior to starting installation activities, each specified area will be inspected by the Basatin
Landscaping survey team to ensure grading and measurement is in accordance with the approved
drawing for handover. If any discrepancies occur Client’s Representative or Consultant will be
informed, and a coordinated outcome will prevail. Only approved material will be used. Delivered
material will be stored at Basatin Landscaping’s suitable lay down area and will always be subject to
Client’s Representative or Consultant inspection.

8.2 Method Kerbstone Installation

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 10 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

1. Site Preparation: Adequate stock of material, testing equipment and consumables along with
sufficient manpower shall be arranged to carry out the work. Prior to start of activity, area and
access will be inspected to ensure that the area is ready for the work to start and already
approved by the Consultant/Engineers.
2. Setting Out: All the foundation co-ordinates as per the approved shop drawings were set out
on site and approved by the consultant.
3. Mortar bed: Dry Pack Mortar shall be cement/sand mortar (1:3) composed of one-part ordinary
Portland cement to three parts of sand by volume of works above damp-proof course level and
mortars for below damp-proof course shall be one-part sulphate resisting cement to three-part
sands.
4. Concrete haunching will be provided as per shop drawings approved by Engineer to support the
kerbs.
5. Kerb blocks will be set using a string line as a guide where possible and tapped into a place with
non-marking rubber mallet. It shall be placed over a 30mm thick dry mortar bed. The final level
and locations of kerb blocks will be checked at regular intervals by the Basatin Lands site
surveyor to ensure correct placement and heights in accordance with approved shop drawing
and specifications.
6. WIR shall be submitted as per approved ITP.

8.3 Method For Paving Installation On 50mm Thick Black Sand Bedding ((Vehicular &
Pedestrian)

8.3.1 Setting out:


 The setting out of paving and related features is to be submitted in detailed contractors approved
shop drawings which shall consider actual site conditions.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 11 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

 Any loose material shall be compacted or removed. The site shall be wet down to ensure
compaction and if required compacted further with a plate compactor or vibrating roller.

8.3.2 Sub-grade:
 Upon approval of setting out from the Engineer, A task briefing and walk of work area will take
place to ensure all labor & machine operatives are aware of the task ahead.
 When all the above is complete the bobcats and excavators will then proceed to excavate/grading
pre-determined areas to design specification.
 The sub-grade shall be graded and compacted to not less than 95% of MDD as per required level
to receive sub-base. Frequency of test one test per 1000m2 or as directed by the Engineer.

8.3.3 Sub-base:
 All aggregates for use in the construction of the pavement Layer shall be obtained only from
sources approved by the Engineer.
 The sub-base material shall consist of furnishing, spreading and compacting sub-base in
accordance with the details shown on approved shop drawings and the specification.
 Each sub-base material layer shall be spread by finisher and/or grader or other approved
mechanical methods, watered shaped to a compacted thickness not exceeding 150mm and
compacted to the required grade and cross-section.
 The sub-grade and sub-Base shall be compacted to not less than 98% maximum dry density
determined in accordance with BS 1377. Field density tests shall be carried out at a frequency of
one test per 1000m2 laid or as directed by the Engineer.

8.3.4 Base coarse (Road Base):

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 12 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

 Road base shall be carried or as per SD approved by Engineer.


 All aggregates for use in the construction of the pavement Layer shall be obtained only from
sources approved by the Engineer.
 The road base material shall consist of furnishing, spreading and compacting sub-base in
accordance with the details shown on approved shop drawings and the specification.
 Each road base material layer shall be spread by finisher and/or grader or other approved
mechanical methods, watered shaped to a compacted thickness not exceeding 150mm and
compacted to the required grade and cross-section.
 The Road base shall be compacted to not less than 98% maximum dry density determined in
accordance with BS 1377. Field density tests shall be carried out at a frequency of one test per
1000m2 laid or as directed by the Engineer.

8.3.5 Laying Course- Black Sand:


 The laying course shall consist of sharp sand with a particle size of 5mm and shall be as per
material approval.
 During laying, the sand (or laying course) shall be carefully spread and screened to a smooth
surface to receive paving units. No compaction of the sand layer and no traffic, including
pedestrian is to be permitted before the paving are laid. The laying of course shall be laid to a
thickness of 50mm (unless otherwise specified plus a surcharge necessary to provide the specified
final bed after vibration of the installed unit paving. The profile of the laying course shall be like
that of the finished surface. The maximum deviation from the design levels shall be in accordance
with the Code of Practice.

8.3.6 Edge Restraint:


 The edge restraint to the paved area shall be laid in advance of the laying course and all obstacles
within the area, such as manhole covers shall be constructed to the correct finished levels.

8.3.7 Paver Units Installation:


 The concrete paving slabs/units shall be laid on the sand laying course in such a manner as not to
disturb the blocks already laid. Each block/slab shall be placed firmly against its neighbor so that
they fit closely together. The joints between slabs/setts shall not exceed to 3mm.Paver slabs do
not fit at the edge, restraints or other obstructions such as manholes or up stands the gap shall
be filled using cut slabs. Any damaged or broken slabs shall not be laid.
 In all cases cutting shall be undertaken using a diamond bladed rotary saw, no guillotine cutters
shall be used on the site. Any damage or broken slabs/setts shall not be laid. Any paving damaged
during compaction shall be replaced at the discretion of the consultant.

8.3.8 Expansion Joint:


 Only approved materials by the Engineer will be installed and comply as per contract specification
and manufacturer method statement subject by the Client Representative.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 13 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

8.3.9 Joint Filling:


 Only approved fined material and shall be apply for joint filling such as dune sand and comply to
the specification and as per manufacturer method statement subject by the Client
Representative. Plate vibrator shall be used to ensure the joints are filled properly with dune
sand.

8.4 Installation Of Hazard Warning Tactile-Blister


8.4.1 Material
1. Tactile pavers: 400x400x15mm, Buff Tactile Blister Porcelain Tile; Colour as approved by
Engineer.
2. Cement-sand mortar
3. Sub-base

8.4.2 Procedure for Installation of Tactile Paver

1. Subbase / base course shall be prepared as mentioned above.


2. Setting out of tactile tile shall be done as per approved shop drawing.
3. Cement sand mortar shall be prepared as per 1:3 ratio.
4. Tactile tile shall be installed as shown in the shop drawing approved by Engineer.
5. Joint filling to be with grey sand and tile space to be max 2mm.
6. WIR shall be submitted as per ITP for Engineer’s inspection and approval.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 14 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

8.5 Method For Installation- Granite Paver

1. Setting out of granite paver shall be done as per shop drawing approved by Engineer.
2. The section detail or the shop drawing approved by Engineer shall be followed for installation.
3. Existing soil shall be compacted to 95% in accordance as mentioned above.
4. 1 layer of 1000G polythene sheet shall be laid with overlapping 150mm at joints.
5. Side shutters shall be installed in the setout area. Ensure line, level, and rigidity of shutters.
6. A393 mesh shall be installed with 350mm lapping. Cover block shall be provided so that the
mesh lays middle of concrete section. Side cover shall be minimum 40mm.
7. Concrete mix of C40 grade shall be poured and finished properly.
8. Once concrete is cured, the preparation for granite installation shall begin.
9. Cement sand mortar shall spread and levelled as per requirements and to an average thickness
of 50mm.
10. Approved granite slabs shall be then installed as per shop drawing approved by Engineer.
11. Expansion joints shall be provided as per article as per drawings.
12. Surveyor to ensure the levels and coordinates are as per approved shop drawing.
13. WIR shall be submitted as per ITP for Engineer’s inspection and approval.

8.6 Cast-In-Situ Methodology (General)


8.6.1 Tools, Plants and Equipment:
1. Concrete mixer and pumps
2. Concrete Vibrator
3. Personnel Protective Equipment
4. Hand Tools
Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.
MS for Hardscape Works 00 1 29-01-2024 Page 15 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

5. Surveying Instruments / Tools


 GPS  Surveying Staff
 Total station  Measuring tapes.
 Auto level  Spirit level, etc

8.6.2 Materials:
All materials used on site have to be approved prior to start any work. The following list is a summary
of key materials to be used for the activities.
1. Concrete mix as per design mix 3. Warning Tapes
2. A393 mesh 4. Emergency Kits
8.6.3 Preparation Prior To Concrete Placement:
1. Mechanical vibrators with adequate capacity needles ensured must be available in working
condition for placing concrete.
2. All the debris/binding wire pieces/unwanted materials shall be removed from the pouring
location.
3. Necessary prior information shall be provided to the Engineer and Testing agency prior to
starting concrete placement.
4. Formwork, steel reinforcement and accessories shall be ensured in proper locations, clean, free
of loose scale, dirt or other foreign coatings that may reduce bond to concrete.
5. Sub-base shall moisture uniform without pools or dry areas.
6. Necessary reference mark shall be provided to maintain the required finish level.
7. Ensure the curing arrangements are ready in place to cover the concrete immediate after finish
and before final setting time starts.
8. Ensure the necessary clearance has been taken from MEP & Precast team prior to proceed for
concrete.

8.6.4 Placing of Concrete


9. Clean and prepare formwork to maintain dust free prior to placement of concrete.
10. Concrete shall start one end to progress further continuously without interruption between
predetermined construction and contraction joints.
11. Where placement consists of multiple layers, restrict the first layer of concrete pouring to
continue the succeeding layer to maintain below layer within plastic state to avoid cold joints.
12. Consolidate placed concrete by mechanical vibrating supplemented by hand-spading, rodding
or tamping.
13. Moving fresh concrete laterally inside forms through vibrator is strictly not allowed from
discharge point. Concrete shall be discharged point by point as needed to maintain uniform
level as possible without any segregation.
14. Vibrator needle shall be inserted and withdrawn vertically and uniformly in such a manner that
there should not be any visible hole and adequate compaction made without any segregation.
15. Vibrate needle shall be ensured penetrated at least 150mm in the previous layer meantime due
care shall be taken to do not insert the vibrator needle in concrete which begun set.
Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.
MS for Hardscape Works 00 1 29-01-2024 Page 16 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

16. During the vibration necessary care shall be taken while compacting at embedment of
reinforcement and other embedded items without causing segregation of mix.
17. Expansion joints if required for a area more than 12 sq.m. shall be done as per shop drawing
approved by Engineer.

8.6.5 Curing:
1. Curing activity begins as soon as free water has disappeared from concrete surface and finishing
has been completed.
2. Curing methods shall be of: Cure concrete by curing compound, by moist curing, by moisture-
retaining cover curing or by combining these methods.
3. Approved Curing compound shall be applied as per Manufacture recommendation.
4. If any surface defects observed after de-shuttering, it shall be notified to Engineer. The surface
shall be prepared for the acceptance of Engineer. Approved repair material shall be applied as
per manufacturer’s recommendation. Curing for the same shall be done accordingly.

8.6.6 Field Quality Control


1. Testing Agency: Engage a qualified independent testing and inspecting agency approved by
Engineer to sample materials, perform tests, and submit test reports during concrete
placement according to requirements specified herein.
2. Sampling Fresh Concrete for slump, concrete temperature shall be done at each delivery of
concrete as per specification.
3. Compressive Strength Tests: cast and cure one set of 7 standard cubes for each 100 m3 for
water tank and each blinding 3 specimens tested after 7 days, 3 specimens tested after 28 days,
and one specimen retained in reserve for later testing if required. Additional test specimens
may be cast for construction progress control and form stripping.
4. Testing laboratory shall report test results in writing to the Engineer, and Ready-Mix supplier
on the same day that tests are made.
5. Reports of compressive strength tests shall contain Project identification name and number,
date of concrete placement, name of Contractor, name of concrete supplier and truck number,
name of concrete testing service, concrete type and class, location of concrete batch in the
structure, design compressive strength at 28 days, concrete mix proportions and materials,
compressive breaking strength, and type of break for both 7-day tests and 28-day tests.

8.6.7 Quality Control & Inspection


1. Only approved materials shall be used to execute the works.
2. All materials shall be stored/stacked at the site shall be as manufacturer recommendations.
3. Material receiving inspection shall be done by the site engineer while receiving at the site.
4. Detailed particular testing requirements to be undertaken in relation to activities to ensure
contractual quality requirements are achieved and to identify any non-compliance.
5. WIRs shall be submitted as per the Inspection and Test Plan (ITP) enclosed.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 17 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

8.7 Method Of Metal Edge Installation

1. Ensure the underlying surface is clean, level, and free from debris.
2. Compact the base material thoroughly to provide a stable foundation for the pavers and metal
edge.
3. Mark the desired position for the metal edge between the two pavers.
4. Use chalk lines or other suitable markers to ensure accurate placement.
5. If necessary, cut the pavers to accommodate the metal edge. Use appropriate tools such as a
saw with a diamond blade.
6. Carefully place the metal edge in the marked position between the two pavers, ensuring a snug
fit.
7. Secure the metal edge further by using screws/ stakes or other fastening methods
recommended by manufacturer. Ensure the fasteners are evenly spaced and securely
tightened.
8. Apply grout around the metal edge and between the pavers to provide a clean and finished
look.
9. Smooth the grout lines for a neat appearance.
10. Wipe away any excess grout using a damp sponge or cloth. Prompt cleaning is crucial to achieve
a professional finish.
11. Allow sufficient time for the adhesive and grout to cure, following the manufacturer's
recommendations.
12. WIR shall be submitted as per approved ITP.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 18 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

8.8 Raised Cross Walk Paving (Pedestrian Crossings Table)

1. Clear the area where the crosswalk raised platform will be installed. Remove any existing
pavement or materials as needed.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 19 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

2. Excavate the area to the required depth according to the design specifications. This may include
removing existing soil or materials to make way for the base layers.
3. Install a well-compacted base coarse layer. The thickness and compaction requirements should
be in accordance with the shop drawing approved by the Engineer.
4. Install kerb stones and pavers as mentioned above.
5. Install bollards at designated locations along the crosswalk raised platform. Secure them firmly
to the pavement as per drawings / manufacturer recommendation.
6. Install tactile tiles on the sides of the crosswalk to assist visually impaired pedestrians as
mentioned above.
7. Apply crosswalk markings and install appropriate signage to indicate the presence of the
crosswalk raised platform.
8. A reflective solid triangle pavement marking in yellow shall be applied on the inclined surface
with pavers where vehicles will approach, in accordance with the approved drawing and using
materials that have been approved.
9. WIR shall be submitted as per approved ITP. Wheel Stopper Installation

8.9 Wheel Stopper Installation

1. Mark the positions for the wheel stopper on the asphalt road or pavers using chalk or spray
paint by the Surveyors.
2. Use a drill with a masonry bit to drill holes into the asphalt or pavers at the marked locations.
The hole diameter should be slightly larger than the diameter of the steel rod.
3. Remove any debris or loose material from the drilled holes using a brush or compressed air.
This ensures a better bond with the concrete.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 20 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

4. Cut the 19mm diameter steel rods to the desired length. The length will depend on the
thickness of the precast wheel stopper and the depth of the drilled holes.
5. Insert the steel rods into the drilled holes. Ensure they are securely positioned and extend to
the recommended depth.
6. Prepare the non-shrink epoxy grout according to the manufacturer's instructions. Use a mix
suitable for outdoor applications and compatible with the surrounding environment.
7. Position the precast wheel stopper over the steel rods, ensuring a snug fit.
8. Adjust the position of the wheel stopper to align with the markings on the asphalt or pavers.
9. Pour the prepared non-shrink epoxy grout mix around the base of the precast wheel stopper,
filling the drilled holes.
10. Use a level to check and adjust the alignment of the precast wheel stopper. Make sure it is level
and straight.
11. Allow the non-shrink epoxy grout to cure according to the recommended time frame provided
by the manufacturer.

9. HSEW REQUIREMENTS:

9.1 Health Safety Requirements:


1. Activities covered in this method statement shall be carried out in strict compliance with the
requirements of the approved Project HSEW Plan.
2. Job briefing / Toolbox Talk shall be conducted by concerned Charge hand/ Foreman before
starting activity.
3. For safety purpose, provide safety barrier along the perimeter of the excavated area to fall
hazards.
Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.
MS for Hardscape Works 00 1 29-01-2024 Page 21 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

4. The area of construction shall be cordoned off properly with all necessary safety measures like
signboards, warning tape, traffic cone, barriers & flashlight etc.
5. Access and egress to trench shall be done.
6. Attention will be given to ensure that safety of all devices is being used for the job.
7. Experienced worker shall be deployed for operation of all type machine and tools.
8. All the required PPEs such as helmet, safety goggles, hand gloves, overall, safety shoes and ear
plugs shall be used by involved workers.
9. Proper supervision shall be ensured to monitor the work.
10. Appropriate Safety guidelines must be adhered during all stages of construction activity.
11. Manual Handling training shall be conducted.
12. First aid facilities shall be provided with provision of First Aider/ Male Nurse
13. Accident / incidents will be reported immediately followed by a written report within 24 hours
of the occurrence as per site accident / incident reporting procedures.
14. Proper escape route in case of evacuation shall all be designated, marked, and notified to all
personnel.
15. Work area shall be barricaded as applicable and necessary.
16. Required safety sign boards shall be placed at the area.
17. AACM waste management system to be followed.
18. Access and egress to trench shall be done. Ensure proper coordination with other disciplines so
that all relevant personnel are aware of the requirements. Ensure that a relevant permit to
work is obtained from the appropriate civil contractor, if required.
19. Ensure that the work area is safe and that all constraints on operations have been identified
and necessary precautions have been taken.
20. Welfare Facilities such as drinking water, rest area/ toilets.
21. Safety requirements and precautions, please refer to the approved RA.

9.2 Emergency Procedure


To facilitate the reporting of emergency situations the safety in-charge/Engineer shall arrange for the
following emergency procedure and telephone numbers to be displayed on site and updated
regularly:

Step-1: If a person is injured/need medical assistance, remove the injured person from where
danger still exists and get first aid, do not leave the injured person until help arrives.
Step-2: For major injuries and incidents, call emergency service required and give location and
nature of emergency.
 Ali Nazir (HSE Lead) - 056 995 7731
 Ahmed (HSE Officer) - 050 752 7427
 George (CM) - 056 995 7728
 Darwin Armada Colete (HSEM) - 055 2991798

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 22 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

 Aiham Tayar (PM) - 055-2216355


 Police - 999
 Ambulance - 998
 Civil Defense (Fire) - 997
PPE requirement
The following PPEs shall be worn by workers involved:
• Helmet, safety goggles, hand gloves, overall, safety shoes and ear plugs

9.3 Environmental Requirements:


1. All applicable government requirements and regulations pertaining to environmental
protection and pollution shall be identified and adhered to.
2. Good housekeeping should be followed at all times to prevent the occurrence of accidents and
consequent injuries.

9.4 Housekeeping
Housekeeping of fabrication and installation sites will be done in accordance with the OSHAD, DMT
and project safety manual.

10. INSPECTION AND TESTING PLAN (ITP)


Details particular testing requirements to be undertaken in relation to particular activities in relation
to construction works to ensure contractual quality requirements are achieved and to identify any
non-compliance. Inspections shall be carried out as per ITP approved by the Engineer.

11. RECORDS:
1. Work inspection request approvals.
2. Material inspection request approvals
3. Test reports

12. DISTRIBUTION: -
Copies of this Method Statement shall be circulated to the following for Information & action.
1. Project Manager. 4. HSE officer.
2. Project Engineer / Site Engineer. 5. Supervisors
3. QC Engineer / Inspector. 6. Foremen.

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 23 of 24
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

13. ATTACHMENT
1. Inspection and Testing Plan (ITP)
2. Inspection Check List (ICL)
3. Risk Assessment (RA)

*****************

Document No. BAS-OTK-KBZ-MS-0012 Rev.: Issue: Issued Date: Page No.


MS for Hardscape Works 00 1 29-01-2024 Page 24 of 24
INSPECTION & TEST PLAN (ITP) FOR HARDSCAPE WORK
DEPARTMENT OF MUNICIPALITIES AND
Employer Project Khalifa Bin Zayed Street Development, Al Ain ITP Ref. No. BAS-OTK-KBZ-ITP-0012-00
TRANSPORT
Engineer Otak International Discipline HARDSCAPING WORKS Date 29-01-24
Contractor Basatin Landscaping MS Ref. No. BAS-OTK-KBZ-MS-0012-00

Responsibility
Frequency of Test Applicable Specification /
SN Inspection / Test to be carried out Acceptance Criteria Control Data / Forms Inspection Method Sub Main
/ Inspection Standard Engineer Third Party
contractor Contractor
I Pre- Construction Activities
Prior to start the Employer's/ Authority/Engineer Approved Method Document
1 Approval of Method Statement 1. Standard Specification- ADM N/A H R/A N/A
activity Approval Statement Verification
Landscape spceifications
Prior to start the Employer's/ Authority/Engineer Approved Material Document
2 Approval of Materials N/A H R/A N/A
activity Approval 2. Landscape specification: Submittal Form Verification
Prior to start the Employer's/ Authority/Engineer Division 32: Document
3 NOC's and Permits Section-321400: Paver Authority Approval N/A H R/A N/A
activity Approval Verification
Section-321600 Curbs And
Prior to start the Employer's/ Authority/Engineer Approved Shop Drawing Document
4 Approval of Shop Drawing Edgings N/A H R/A N/A
activity Approval Submittal Form Verification
II Main Activities (Installation)
Pre-examination of the site done Visual inspection of
by the contractor. Site daily excavation side
1 Safety and Cleanliness Each area HSE plans N/A P&H H&A N/A
activities have been supervised by slopes & formation;
the safety officer. Survey check on
Material sample shall meet the
1 sample every
2 Sampling and Testing 3 minimum requirements as per Test Report Document Review N/A P&H W&A P
1,000m
specification
1. Standard Specification- ADM
Hardscaping work alignment, levels
Landscape spceifications
and locations carried out by the Survey Visual Inspection
3 Setting out Each area N/A P&H W&A N/A
Surveyor to the approved drawings records/WIR/Checklist /WIR
2. Landscape specification:
and specifications.
Division 32:
As per approved shop drawing and
Excavation & Formation of Sub Section-321400: Paver
Each area 1 test approved method statement, Excavation Permit/WIR/
4 Section-321600 Curbs And Visual Inspection N/A P&H H P
grade every 500 sq. m. Subgrade 200mm thk layer min. checklist
Edgings
MDD 95% & CBR 30
Sub base shall be laid at the depth
specified in the specification and
Each area 1 test approved shop drawing. Survey records/WIR/ Visual Inspection/
5 Sub base Laying & Compaction N/A P&H W&A P
every 300 sq. m. Compacted subbase of 150mm Test Report Hold Point
thickness shall have minimum of
98% MDD

Page 1 of 2
INSPECTION & TEST PLAN (ITP) FOR HARDSCAPE WORK
DEPARTMENT OF MUNICIPALITIES AND
Employer Project Khalifa Bin Zayed Street Development, Al Ain ITP Ref. No. BAS-OTK-KBZ-ITP-0012-00
TRANSPORT
Engineer Otak International Discipline HARDSCAPING WORKS Date 29-01-24
Contractor Basatin Landscaping MS Ref. No. BAS-OTK-KBZ-MS-0012-00

Responsibility
Frequency of Test Applicable Specification /
SN Inspection / Test to be carried out Acceptance Criteria Control Data / Forms Inspection Method Sub Main
/ Inspection Standard Engineer Third Party
contractor Contractor
Formwork shall be constructed
accurately to represent the shape
6 Shuttering Each area Checklist Visual Inspection N/A P&H S N/A
of the concrete as detailed on the
kerb location/layout plan
Approved design mix for Concrete
7 Concrete Blinding Each area blinding. Concrete pouring shall Checklist Visual Inspection N/A P&H S N/A
follows the standard procedures
Approved Sand bedding shall be
laid at the depth specified in the
8 Sand Bedding Each area 1. Standard Specification- ADM Checklist Visual Inspection N/A P&H S N/A
specification and approved shop
drawing. Landscape spceifications

To be set and installed on a 50mm 2. Landscape specification:


Installation of PC Paving thick fine course aggregate Division 32: MIR/WIR/ checklist/ Test
9 Each area Visual Inspection N/A P&H W&A N/A
blocks/Kerb bedding, in accordance with the Section-321400: Paver Report
approved drawing Section-321600 Curbs And
Edgings
Sand Joint to the Paving tiles shall
10 Sand Joint Each area be match the color of tiles and checklist Visual Inspection N/A P&H S N/A
adjacent paving color
Before final inspection, all
components, systems and
Final Inspection (After completion Each area after subsystems shall be tested, to Visual inspection,
11 WIR/ checklist N/A P&H W/A N/A
of hardscape items) work completion demonstrate compliance with the Document Review
specified performance
requirements.
Note (1): H: Hold Point, W: Witness, R: Review, S: Surveillance, A: Approval, P: Perform / Execute

Issued for Review /


00 29-01-24 2 Sr.QA/QC Engineer Sr. Technical Engineer Project Manager
Approval

Rev Date Pages Description Prepared Reviewed Approved

Page 2 of 2
Check List for Hardscape Works
Project Name Khalifa Bin Zayed Street Development, Al Ain Employer DMT
Contractor Basatin Landscaping Engineer Otak International
Checklist Title: Check List for Hardscape Works Checklist No. BAS-OTK-KBZ-ICL-0012-00
Works Location: Related ITP # BAS-OTK-KBZ-ITP-0012-00
Related Drawing(s) Related MS # BAS-OTK-KBZ-MS-0012-00
Status - Acceptable
SN Description of checking to be carried out Remarks
Yes No NA
Preliminary

1 a. Proposed approved shop / Survey drawing


b. Check availability of NOC & related permits from concerned
authorities
Safety & Cleanliness
a. All are in PPE uniform
1
b. As per method statement & HSE plan
c. Safety Access
Sub base / Road Base
a. Approved materials
2
b. Embedded item securely fixed
c. Compaction 98% MDD
Bedding Sand
a. Approved materials
2
b. Thickness of 50mm
c. Level
Mortar Bed
a. Approved materials
3
b. Thickness of mortar (as per drawing)
c. Level
Installation
a. Approved materials
4
b. Level & Alignment / Position
c. Control joints
Remarks:

Accompanying document :

Quality Engineer For Supervision Consultant (Engineer)

Name
Designation
Date

Page 1 of 1
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
1- Post Work Noncompliance of • Lack of • Legal Non- 4 4 16 E • Ensure that the relevant permits / PTW (if applicable) 1 1 4 M Project
Activities. Pre awareness Compliance are obtained from the authorities, client and Manager.
commencement about Pre- could lead consultant prior to commencement of the activity. Technical
Engineer.
Requirements. commencemen loss of life • Latest revision for drawings should be available at
HSE
t Requirements and site, prior to start of activity. Manager/
and obtaining property. • Involved team must be competent to commence and Engineer
procedure. • Penalties. carry out the work.
• Unsafe Act. • Ensure proper coordination with other disciplines so
that all relevant personnel are aware of the
requirements.
• Ensure that relevant permits to work are obtained.
• Internal PTW system must be implemented if
required.
• MSRA shall be be prepared for the activity and it must
be approved from respective client and consultant.
• Approved MSRA must communicated with the site
staff and workers.

2- Personnel Unfamiliar with • Lack of • Personal 3 3 9 H • Information shall be provided to the HSED prior to 1 3 3 L Logistic
Mobilization at the work area and information injuries. Personnel Mobilization at site. Officer.
site. nature of work. about the work • Property • All legal documents of the personnel shall be Site
Engineer
procedures and Damages. available such as Passport, visa, EID and competency
HSE Officer
Illegal personnel related hazards • Legal certificate if required.
without valid legal • Unsafe act actions. • HSE officer shall check all the submitted documents
documents. and ensure its valid prior to conduct safety induction.
• Induction stickers shall be provided for identification.
• Induction log shall be maintained.

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 1 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
• Induction training shall cover site information, related
activities and its hazards and precautions, emergency
procedure, duties responsibilities etc.
• Required PPE’s PPE must be available at all times and
specific PPE should be provided as per requirement.
• Refresher induction training shall be conducted as per
requirement.

3- Plant and Non-Compliance • Lack of • Personal 3 3 9 H • Plant and equipment must have all valid documents 1 3 3 L Logistic
equipment with legal information injuries. such Mulkiya and third-party certificates. Officer.
Mobilization at requirements. • Unsafe act • Property • Plant and equipment must be inspected prior to Site
Engineer
site. Unauthorized Damages. deploy at the site by HSEO and ensure its safe to use.
HSE Officer
operator. • Legal • Inspection tag to be provided.
actions. • Operators must have valid license and third-party
training certificates.
• Safety induction to be conducted for the operators.
• Awareness training shall be carried out.
• Pre use inspection must be carried out by the
operators on daily basis and supervisor ensure it
4- Site Survey Unauthorized • Lack of • Personal 4 4 16 E • Workplace shall be isolated. 1 4 4 M Surveyor
and Marking. Entry. awareness. injuries. • Warning signs shall be displayed in the work area. Site
Unauthorized • Unsafe act. • Property • Only inducted personnel are allowed to carry out Engineer
operation. damage. survey and marking HSE
Unfamiliar • NOC/work permit and required approval and drawing Engineer/
workplace. must be available with in charge person. Officer
Un protected • Provided rebars shall be protected with rebar caps.
rebars. • Required PPE’s shall be provided to the staff and
workers.

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 2 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
5- Mobilization of Moving vehicles. Collision with • Physical 4 4 16 E • Vehicle for delivery must have valid registration 1 4 4 M Logistic
materials to Pedestrians. vehicle & Injury to certificate. Officer.
the site. persons. Workers, • Driver must have valid driving license. Site
Engineer
Faulty vehicles. Overloading, Staff and • Competent Drivers.
HSE Officer
Over-speeding, Visitor, • Time Management, driving time should be assessed
Unsecured Load Collapse. Fatality, and breaks should be given accordingly.
Materials Fractures, • Pre-use inspection of vehicle should be done and
Property verified by supervisor.
Damage, • Pre-Work briefings / Tool Box Talks ref: Manual
Road Handling, Loading / Unloading of materials.
Accidents • Supervisor should ensure that the workers are aware
about the correct manual handling techniques.
• While loading of materials from the store, supplier
location or remote location, driver along with
responsible person should ensure that all materials
are properly secured and tied.
• No over-speeding. On site speed limit for vehicle “20
km/h” must be followed
• Keep an eye always on the road and look for any
human or animals crossing.
• Only designated access must be used for vehicle
maneuvering.
• Reversing must be avoided if required banks man
must be assigned.
• Number of passengers or weight of goods shall not
exceed the carrying capacity of the vehicle.
• Unloading area must be free from unauthorized
person and should be barricaded wherever required.

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 3 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
• Before unloading the materials, it should be ensuring
that load is stable and proper procedure for
unloading materials must be adopted.
• Competent Supervision should be available all the
time during critical works, like unloading of materials,
etc.
• Supervisor should ensure that all the equipment and
materials are at their safe place while resting.
• Risk assessment must be communicated to all
associated persons.
• Workers assigned for work must worn adequate
PPE’s, safety shoe, high visibility jacket, gloves, hard
hat and face mask, etc.
6- Loading and • Manual handling • Use of • Physical 4 4 16 E • Worker should be trained on manual handling procedure 1 4 4 M Logistic
offloading of • Unauthorized use defective injuries + working gloves shall be provided to personnel activity, Site
equipment and of equipment’s equipment s • Serious adequate supervision to be provided Engineer
materials • Loading and for loading and injury • TBT shall be conducted on daily basis prior to start of the
offloading offloading • Damage to activity
• Incorrect purposes property • Only authorized licensed and 3rd party trained personnel
slinging/ragging • Unauthorized • Vehicles turn shall be allowed to operate equipment for unloading and
technique personnel over materials
• Unstable or inside lifting • Material and • Only third-party certificate equipment shall be used for
unstable ground area equipment the loading and off-loading of materials and equipment
surface • Unexpected fall off from shall be inspected before use
Pinch points moment of transport • Loading and offloading area shall be isolated, barricaded
load vehicle shall be erected to prevent unauthorized personnel from
• Equipment entering
overloading • Tag line shall be used to control load during loading and
offloading activity

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 4 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
Miscommunica • Electronic loads indicator and load chart shall be used at
tion during all times. Weight of material or equipment shall be
work established prior loading and offloading of materials and
equipment.
• Only one rigger (experienced and third party certified)
shall give signal to equipment operator to avoid
miscommunication
• Only experienced and third-party certified rigger shall
perform slinging and rigger technique for all loading and
off-loading activity
• Ground surface must be inspected to ensure sufficient
compaction to operate any lifting equipment. Plan the
travel path and ensure route is clear of obstructions.
• Personnel shall keep their hands and other body
pinch point areas; adequate supervision shall be
provided during the loading and offloading activity
7- Work with Plant • Moving and • Activity not • Personal 4 4 16 E • Vehicle movement area shall be separated if possible. 1 4 4 M Foreman
and equipment working Plant and supervised Injury • Man, and machine interface shall be avoided as much Engineer
such as Backhoe equipment • Flagman/ • Serious as possible. Operator
loader, wheel • Struck by moving signal man Injury • While movement, a certified flagman shall be Flagman
loader, skid plant and does not • Damage to available with plants and equipment.
loader crane equipment present to property • A practical training shall be conducted for the
etc. • Caught in guide operators and flagmen.
between operators / • Activity to be supervised at all times
• Collision drivers • Dily pre-use inspection of plants and equipment shall
• Turn over • Overloading be followed.
• Failure of load • Unsecured load • A hard copy of all valid documents must be available
• Area not with plants and equipment’s operators.
isolated from • While shifting, Load to be tie-in securely

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 5 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
• Area to be cordoned off.
• Awareness signages to be displayed.

8- Use of power • Cuts and • Unauthorized • Harm to 4 4 16 E • Pre-task briefing regarding the hazard risks and 1 4 4 M Foreman
tools such as abrasion user. workers/o control measures of the power tools Engineer
Jack • Lack of perators/m • Authorized Technician should inspect the power tools Operator
• Laceration
hammer/Drilli awareness. embers of to ensure that it is safe for use.
• Projectiles
ng Machine • Failure to the public • Ensure the presence of trained fire warden and
etc. • Fire inspect Damage to availability of suitable fire extinguisher
• Noise property • Electrical equipment must have earth – fault – circuit
– protection via residual current devices (RCD).
Equipment shall pass the portable appliance testing
(PAT testing).
• Only trained personnel shall operate the power tools
• The operator should ensure regular breaks are taken
from use to provide postural relief and to avoid hand-
arm vibration injury
• Wear or use personal protective equipment (PPE);
this may include items such as safety glasses or
goggles, or a face shield (with safety glasses or
goggles), hearing protection, dust mask, glove and
safety shoes
• Do not wear loose clothing or dangling jewelry as
they may get caught in the moving parts of the power
tools. If you have long hair, keep it tied back.
• Ensure the attachment selected is designed
for the purpose it will be used (e.g. only use

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 6 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
abrasive discs for grinding and cut-off discs
for cutting).
• Only use attachments designed for use on
power tools and do not use circular saw
blades on angle grinders
• Inspect all wheels and bits for cracks and
defects before mounting
• Ensure that the mounting flange surfaces are
clean and flat.
• Ensure the fixed guard is in place while
operating the grinder.
• Use the mounting blotters supplied.
• Use an appropriate ventilation exhaust
system to reduce inhalation of dusts, debris,
and coolant mists. Exhaust systems must be
designed and maintained appropriately.
• Do not use power tools near flammable
materials.
• Do not use any liquid coolants with portable
grinders.
• Do not tighten the mounting nut excessively.
• Do not put the power tools on the floor or
working surface until it has stopped.
• Do not keep any materials close to the
grinding wheel when it is not in use.
• Keep the electrical cord clear off the pathway.

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 7 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
9- Use of Hand • Misuse of tools • Improper use • Personnel 3 3 9 H • All Employees will be undertaking a TBT training 1 3 3 L Foreman
tools • Improper of the tools Injury course leading to Hazards and risks related to hand Engineer
maintenance • Lack of tools
• Sharp edges maintenance • Employees informed of requirement to provide all
• Lack of hand tools in a safe condition
knowledge • Pre-operation Hand tools inspection
• Inadequate • Damaged/defective tools to be taken out of use
resources e.g. immediately
PPE • Workers to be instructed by joining instructions to
use all necessary PPE (gloves, safety shoes, safety
helmets, safety glasses/goggles)
• Carry out periodic visual inspections throughout
competition, defective tools to be removed
immediately.
10- Working • Man-machine • Employee in Personnel 3 3 9 H 1 3 3 L Foreman
adjacent to interface vicinity to injury • Close Supervision for the work activates Engineer
vehicular • Workers hit by heavy • Banks man to be availed for equipment’s for equipment
traffic heavy equipment equipment reversing, each equipment must be fitted with reverse
During the road alarm flashing light and fire extinguisher
works • Safety training and toolbox talk to include all active safety
measures and emergency procedure.
• Equipment to be inspected before starting the job
• Labors are not allowed to stay too close to equipment’s
• Specific PPE include suitable safety Shoes and high
visibility vest must be worn
• Speed limit on site must be followed

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 8 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
11- • Vibration • Lack of • Personnel 3 3 9 H • Reduce exposure time, 1 3 3 L Foreman
Compaction • Noise inspection of Injury • Job Rotation, Engineer
work • Unguarded tools before • Proper Awareness and Trainings
• Tools use. • Proper compaction machine is recommended along with
• Personal injury • incompetent competent operator,
due to use the operator • Use the correct the tool for the job.
incorrect/unsafe • Use of • Regular inspection of tools.
Use of homemade • Protect the sharp edges of tools that are to be stored or
machineries/ tools tools carried.
• Inadequate • Renew wooden handles that are split.
training, • Keep hammer head tightly wedged on their shafts.
instruction & • Never allow any employee to prepare tool at workplace.
supervision, • All employees should be properly instructed the safe
• Bad condition work procedure of all hand tools.
of hand tools, • Adequate monitoring shall be implemented to prevent
• Operating the preparation of homemade tools.
Procedures. • Use Proper PPE.
12- installation of • Manual Handlin • Unsafe manual • Slips, trips 3 3 9 H • Manual handling must be avoided as much as 1 3 3 L Site
paver units, handling and falls possible. Engineer.
hazard technique. • Back injury • Use suitable handling aids to avoid manual handling HSEO
warning • Lack of • Cuts and as much as possible. Supervisor
tactile-blister awareness. abrasion • Portable trolleys to be used. .
and Tactile • An awareness training shall be conducted for safe
Paver manual handling.
• Required PPEs shall be provided.
• PTB shall be conducted.

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 9 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
13- Installation- • Chemical handling • Chemical • Eye, skin 3 3 9 H • SDS of chemicals shall be made available and shall be 1 3 3 L Site
Granite Slab exposure, and strictly adhered with. Engineer.
• Environmen respiratory • Ensure all chemicals handling and storage procedure HSEO
tal Hazard irritation are done as per the instructions mentioned in SDS. Supervisor
to person • Only authorized or labelled containers must be use
assigned for the chemical.
for work • Risk assessment should be communicated.
and person • Only trained and experienced personnel shall be
present at assigned for operation.
work area. • Personal hygiene must be maintained such as wash
• Physical hand with soaps before having meal.
injury, Soil • All mandatory and job specific PPE must be worn.
contamina • Hazardous waste should be stored separately and
tion disposed of through registered waste collector.
• Fire extinguisher should be available in storage and
working areas and should be in good working
condition. (if required)
• Supervisor should ensure that all personnel working
on site are familiar with the use of fire extinguisher.
14- Installation- Concrete activity. • Exposure with • Eye, skin 3 3 9 H • Fully protected cloth shall be provided. 1 3 3 L Site
Granite Slab. chemical allergy. • Required ppes shall be available with the crews. Engineer.
• Environmental • Environme • An awareness training shall be conducted for the HSEO
hazard ntal team. Supervisor
• Concrete waste must be disposed in designated area
only.
• PTB must be followed.
• Full time supervision shall be provided.

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 10 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
15- Compaction • Vibration • Lack of • Personnel 3 3 9 H • Reduce exposure time, 1 3 3 L Foreman
• Noise inspection of Injury • Job Rotation, Engineer
• Unguarded tools before • Proper Awareness and Trainings
• Tools use. • Proper compaction machine is recommended along with
• Personal injury • incompetent competent operator,
due to use the operator • Use the correct the tool for the job.
incorrect/unsafe • Use of • Regular inspection of tools.
Use of homemade • Protect the sharp edges of tools that are to be stored or
machineries/ tools tools carried.
• Inadequate • Renew wooden handles that are split.
training, • Keep hammer head tightly wedged on their shafts.
instruction & • Never allow any employee to prepare tool at workplace.
supervision, • All employees should be properly instructed the safe
• Bad condition work procedure of all hand tools.
of hand tools, • Adequate monitoring shall be implemented to prevent
• Operating the preparation of homemade tools.
Procedures. • Use Proper PPE
16- Weather • Dust, Heavy wind, • Heavy wind • Uneasiness, 3 3 9 H • Awareness training shall be given to all personnel 1 3 3 L Site
condition and sandstorms can cause breathing • Personnel to avoid working in storm and windy condition. Engineer
site • Heat Stress eruption of problem, • Sprinkle water for dust suppression.
environment dust, sand, and eye injuries, • Ensure emergency vehicle available at site.
accumulation poor • Personnel to wear dusk mask as and when required
Working under • Employees visibility, • Provided water cooler and rest shelter as required
direct sunlight exposed to lack of • Acclimatization for new personnel or personnel coming
heat stability from vacation
• Dehydration during lifting • Dress for the conditions lightweight, loose clothing is best
• Hot working and manual avoid layering clothing underneath coverall
environment handling of • Sufficient cold drinking water and other supplement for
loads dehydration will be available on job site.

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 11 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
• Personnel to have a well balance diet avoiding heavy and
fatty foods
• Personnel avoid caffeine and alcohol the night before
and during the day
• Water breaks at least every 20-30 minutes
• Intermittent breaks or rotation of personnel to be
implemented
• Shaded areas will be provided for short breaks
• Work stop during summer break time as mandated by
law
• Engineers and Forman to monitor their team for
symptoms of heat related illness.
• Personnel to stop activity and inform Foreman if he feels
something is wrong with his physical condition
• First aider available on site
• Emergency vehicle will be available on site.
17- Emergency • Inadequate • Lack of • Death / 3 3 9 H • First-aid box and trained first aider onsite. 1 3 3 L Engineer
Preparedness emergency consultation extensive • Emergency response should be in accordance with the HSEW
response and loss project emergency response plan. Officer
Constructio
arrangements. • Emergency contact number will be posted at site.
n Manager
• Poor Emergency contact numbers are available with the HSE
communication Plan.
• Communication by mobile
18- Site welfare • Inadequate • Lack of • Environment 3 3 9 H • Portable toilet and periodical cleaning. 1 3 3 L Foreman
facilities maintenance of management al pollution • Site shade, drinking water availability and sealed. Engineer
maintenance welfare facilities commitment • Health • First-aid box and trained First-aider. Admin
Constructio
towards effects
n Manager
welfare
facilities

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 12 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
CAUSE OF
SI NO ACTIVITY HAZARD/ HAZARD CONSEQUEN RISK RISK RISK RECOMMENDED CONTROL MEASURE RISK RISK RISK Responsible
ASPECT AND CE/ EVALU RATIN LEVEL EVALU RATI LEVEL
CONDITION IMPACT ATION G ATION NG
THAT DEVELOP
THE HAZARD P S P*S (H/M/ P S P*S (H/M
L) /L)
19- Waste • Unhygienic • Waste is • Environment 3 3 9 H • Bins to contain trashes, no food waste / left over onsite. 1 3 3 L Foreman
Management conditions. disposed of in al pollution. Eating only at designated approved area. Engineer
• Lack of identified un- authorized • Health • Food waste to be removed every day. Work debris. Logistic FM
Constructio
area for storage & location that effects Excess material to be removed.
n Manager
segregation can cause Outbreak of • Waste segregation and disposal practices.
• Ineffective problem epidemic • Communication on the MSDS.
clearing. Fine • Emergency response for storage of hazardous waste.
• Un-identifications • Biological waste (medical waste) are not allowed to
of hazardous litter collected and maintained in sealed container and
chemicals. disposed of properly.
• Waste • Minimization of waste generation encourages waste
minimization segregation at source, recycle reuse and/or utilize in an
program is not environmentally friendly manner.
available • Municipality licensed approved waste transporter to be
used.
20- Housekeeping • Tripping hazard • Improper • Slips and 3 3 9 H • Housekeeping on daily basis. 1 3 3 L All
• Fire hazard arrangement of trips • Fire Extinguisher to be provided on site.
materials • Personnel • Skips/ drums to be provided to dispose debris.
Injury • Food waste should be removed from site on daily
basis

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 13 of 14
Project CLIENT CONSULTANT CONTRACTOR
Khalifa Bin Zayed Street
Development, Al Ain

Project Title: Khalifa Bin Zayed Street Development, Al Ain DATE OF ISSUE 29-01-2024
ACTIVITIES: Risk Assessment – Hardscape Works REVISION NO. 00
RISK MATRIX
SEVERITY (CONSEQUENCE)
PROBABILITY
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20

Frequent (5) 5 10 15 20 25

absolutely unacceptable high


15 - 25 Extreme Risk (E) activity should not proceed in current form
unacceptable high
8 – 12 High Risk (H) activity should be modified to include remedial planning and
action and be subject to detailed HSE assessment
acceptable but must be manage at ALARP
4–6 Moderate Risk (M) activity can operate subject to management and/or modification
acceptable w/o required further action
1-3 Low Risk (L) no action required unless escalation of risk is possible

Date: Prepared by: Reviewed by: Approved by:


29-01-2024 Ali Nazir Darwin Armada Colete Aiham Tayar
HSEW Engineer HSEQ Manager Project Manager
Consultant Approval: Date: Approval: Resident Engineer:

YES NO

E= Extreme Risk, H= High Risk, M = Medium Risk, L = Low Risk, A = Acceptable Risk Page 14 of 14