Location Total Area Done Remaining Target Remarks
4 Guardrail installation D-ring area 23-Jan-23 3/9 completed - N224 pending due to delay of Sentat material delivery (bolt and nut)
5 Earthing for AGV shelter 20-Dec-22 hacking and installation completed, 12 Dec going to start concrete casting
6 Pump room rectification 30-Nov-22 Pending PSA approval for Method Statement
8 Fire extinguisher servicing completed 1year 1 time next batch servicing: April 2023
10 Groove N210 - Waiting for rectification schedule from PSA Operations team
11 Fire engine access painting SS206W and SS207W SS206W and SS207W depends on PTW approval
C3-C8 Remaining works(Wharf)
S/N Description
1
2
3
4
5
Location
Target date Remarks
C3-C8 Remaining works(Substation, Reefer platform)
S/N Description
SS 203 W Completed
SS 204 W Completed
SS 205 W Completed
4-Nov-22
SS 206 W Completed
SS 207 W Completed
SS 208 W Completed
205 Y Completed
22-Nov-22
207 Y Completed
208 Y Completed
N 225 /Reefer Platform
Completed 4-Nov-22
N 226 /Reefer Platform
Completed 18-Nov-22
N 231 /Reefer Platform
22-Dec-22
N 232 /Reefer Platform
Completed 8-Dec-22
N 238 /Reefer Platform
15-Dec-22
N 239 /Reefer Platform
22-Dec-22
1year 1time
All Substations
1month 1time
All Substations
Remarks
C3-C8 Remaining works(Yard)