WORK SCHEDULE FOR SHUTDOWN REPAIR OF TANK 10C

ID Desc. Task Name DurationStart Finish 10 Jan '22 17 Jan '22


No. T W T F S S M T W T F S S
1 ABS NO. STRUCTURAL MEMBER DESCRIPTION 10 days Wed 12/01/22Fri 21/01/22
2 Deck An approximate deck plate area of 5000mm width and 1800mm 3 days Wed 12/01/22 Fri 14/01/22
Plate - length between frame number 20 and frame number 21 and
002A between Port side longitudinal bulkhead plate to longitudinal
stiffener number 10 counting from the port side of the tank
found wasted beyond
3 2A-1 Cropping of corroded section 1 day Wed 12/01/22 Wed 12/01/22
4 2A-2 Fit-up of replacement plate on cropped section 2 days Wed 12/01/22Thu 13/01/22
5 2A-3 Welding of fittet joints 2 days Thu 13/01/22 Fri 14/01/22
6
Deck An approximate deck plate area of 5000mm width and 1800mm 3 days Fri 14/01/22 Sun 16/01/22
Plate - length between frame number 20 and frame number 21 and
003A between Starboard Side longitudinal bulkhead plate to
longitudinal stiffener number 10 counting from the starboard
side of the tank found wast
7 3A-1 Cropping of corroded section 1 day Fri 14/01/22 Fri 14/01/22
8 3A-2 Fit-up of replacement plate on cropped section 2 days Fri 14/01/22 Sat 15/01/22
9 3A-3 Welding of fittet joints 2 days Sat 15/01/22 Sun 16/01/22
10 Deck An approximate deck plate area of 5000mm width and 1800mm 3 days Sun 16/01/22 Tue 18/01/22
Plate - length between frame number 19 and frame number 20 and
002B between Port side longitudinal bulkhead plate to longitudinal
stiffener number 10 counting from the port side of the tank
found wasted beyond
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary
Milestone Inactive Milestone Start-only
KICK-OFF DATE:
Summary Inactive Summary Finish-only
12TH JANUARY, 2022
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
WORK SCHEDULE FOR SHUTDOWN REPAIR OF TANK 10C

ID Desc. Task Name DurationStart Finish 10 Jan '22 17 Jan '22


No. T W T F S S M T W T F S S
11 2B-1 Cropping of corroded section 1 day Sun 16/01/22 Sun 16/01/22
12 2B-2 Fit-up of replacement plate on cropped section 2 days Sun 16/01/22 Mon 17/01/22
13 2B-3 Welding of fittet joints 2 days Mon 17/01/22Tue 18/01/22
14 Deck An approximate deck plate area of 5000mm width and 1800mm 3 days Tue 18/01/22 Thu 20/01/22
Plate - length between frame number 19 and frame number 20 and
003B between Starboard Side longitudinal bulkhead plate to
longitudinal stiffener number 10 counting from the starboard
side of the tank found wast
15 3B-1 Cropping of corroded section 1 day Tue 18/01/22 Tue 18/01/22
16 3B-2 Fit-up of replacement plate on cropped section 2 days Tue 18/01/22 Wed 19/01/22
17 3B-3 Welding of fittet joints 2 days Wed 19/01/22Thu 20/01/22
18 Deck An approximate deck plate area of 3500mm width and 1800mm 2 days Thu 20/01/22 Fri 21/01/22
Plate - length between frame number 18 and frame number 19 and
001 between longitudinal stiffener number 13 and longitudinal
stiffener number 20 counting from the port side of the tank
found wasted beyond allo
19 01-1 Cropping of corroded section 1 day Thu 20/01/22 Thu 20/01/22
20 01-2 Fit-up of replacement plate on cropped section 2 days Thu 20/01/22 Fri 21/01/22
21 01-3 Welding of fittet joints 2 days Thu 20/01/22 Fri 21/01/22

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Milestone Inactive Milestone Start-only
KICK-OFF DATE:
Summary Inactive Summary Finish-only
12TH JANUARY, 2022
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2