INTERNAL SAFETY AUDIT - 2020

Cogen
Sl.No R No Observation

GTs RLNG / DM
1 181 Operating manual available , but not updated. DGM( P&U) job in progress 10.01.22 plants updation
in progress

Job Completed : 6 Out of 7


Job not completed even target date over : 1
INTERNAL SAFETY AUDIT - 2020

SRU/UTI
Sl.No R No Observation FPR CRAFT NOTIFICATION Status Target date
Check list taken sent M
1 SRU/UTI – Pre monsoon checks of tanks area records not available with mfg. DGM(Ref-III)
&I and civil
job in progress 31/7/22
96
2 100 Ref-III OWS Fire of Nov’17 - Accident investigation report recommendations to be expedited. " job in progress 31.01.2022
partially
3 CCTV is not working since one month. " INST
completed
31.01.2022
102

4 212D1/2 and 214D1/2 manifold areas HC gas detectors shall be provided. " INST 521215 job in progress 31.01.2022
106
5 107 BS IV tanks OWS chock. " CIVIL 529217 job in progress 31.01.2022
6 108 BS IV OWS vent mesh (Flame Arrestor) nil. " FIELD M/C 529218 Completed 31.01.2022
7 110 Euro – IV tanks pipeline PSV testing dates not mentioned, 3 Nos found isolated. " FIELD M/C 529219 Completed 31.01.2022
8 111 PSV block valves not locked. " Mfg 529240 job in progress 31.01.2022
9 112 Plant inside MCP numbers stenciling, canopy, etc. not provided. MCPs are difficult to notice. " INST job in progress 31.01.2022

10 115 208/209 condensate leak on pipe rack. " FIELD M/C 529242 Completed 31.01.2022

As continuous supply of drinking water is not available, reliability of safety shower is not " CIVIL job in progress 31.01.2022
11 165 consistent.(Safety shower near Sub station)

Job Completed : 16 Out of 25


Job not completed even target date over : 9

Plant-213 (New sour water system)


Sl.No R No Observation FPR CRAFT NOTIFICATION Status Target date
1 151 213D1 A&B LG drain valves kept closed and blinded. DGM(Ref-III) Completed

Job Completed : 1 Out of 2


Job not completed even target date over : 1
INTERNAL SAFETY AUDIT - 2020
OHCU
Sl.No R No Observation FPR CRAFT Remarks NOTIFICATION

1 132 Interlocks 207BS4201 to 4208 are bypassed – Spares awaited. " M&I
2 136 C15/C17 structure fire proofing damaged. " Job being done Job is in progress

Job Completed : 8 Out of 10


Job not completed even target date over : 2
Target
Status date
forced on condition
b is in progress 31.01.2022
CHENNAI PETROLEUM CORPORATION LIMITED
WEEKLY MAINTENANCE COORDINATION MEETING - Ref-III, Cogen and CPP
Meeting minutes updated through ZOOM meeting Date : 03.03.2022
Members Present: Sri: A.ARUNAVIVEKANANDAN,

Maint:S.RAJENDRAN, S.ARVINDKUMAR, VIVEK RAJ, P.RANGARAJ, K.INDIRAN, T.MURUGESAN, , MOHAMED YUSUF, SOHAILAHMED, S E J BABU

Actual Time : 11:00AM to 11:57 PM


P&U /DESAL : S.RAJENDRAN, M.VELUSAMY
PE : RAJA
GE : SANJEEV KUMAR INSPN : ABSENT
MATLS & CONTS : A.MANIVANNAN,
F&S : SACHIN VISWANATHAN EP & S: ABSENT
Meeting schedule:11.00 AM to 12.20 PM - Every Thursday Venue: Through ZOOM app
Actual Time : 11:00AM to 12:00 PM
Sl Item Date Action by STATUS Immediate Action / Target of completion
No Remarks
SIGNIFICANT JOBS STATUS MONITORING
Area/ Craft/ NMI's Raised Completed Pending Pending HiPO NMIs Pending Critical NMIs
Field 478 296 182 8 39
Rotary 29 27 2 1 0
Pending NMI's - 01.04.2021 to 17.02.2022 Civil 231 148 83 2 18
1
(Ref-III)
Elect 125 102 23 0 7
Inst 86 73 13 0 2

Total 949 646 303 11 66


Area/ Craft/ NMI's Raised Completed Pending Pending HiPO NMIs Pending Critical NMIs
Field 172 135 37 0 0
Rotary 11 4 7 0 0
Pending NMI's - 01.04.2021 to 17.02.2022 Civil 112 65 47 0 3
2
(P&U-II & III)
Elect 70 65 5 0 0
Inst 22 19 3 0 0
Total 387 288 99 0 3
Area Total Completed Part.Completed Inprogress Pending
Ref-3 onsite 55 29 3 3 20
5 IWL 's (Except Shutdown)- upto 30.06.2021
Ref-3 Offsite 22 10 0 2 10
Cogen/Desal 37 15 3 6 13
No of
ISA 2020 Points points Completed Points

Ref III – (OHCU, 211 ,206, 212)


22 20 2 2 No Target Date not Met
6 INTERNAL SAFETY AUDIT - 2020

Ref III (SRU,CDU-III, 213,214)


39 31 8 8 No Target Date not Met

P&U II &III 14 13 1 1 No Target Date not Met


FIRE & SAFETY
Leaks in Fire water lines / Field Job I/P (Internal Coating -
1 FW Leaks: Ref-III: 3, Cogen: 0 Field
Repairs in Fire fighting equipments Agency M/s Clean Coats)
207 Fin fan cooler - Flange leaks in 9 lines. 75% Choke; 207
Pump WSS - 1 leak, choke in 6 lines.
201 Fin fan cooler - 8 out of 10 lines choked; 201 Pump WSS -
2 Fire water WSS as on 04.07.2019 Field 15 out of 31 lines choked. Field / Mfg. Job I/P
206 Pump WSS - 2 lines fully choked and 7 lines partially
choked out of a total of 25 lines.
211 Pump WSS - 2 lines fully chocked out of a total of 6 lines.
211 Fin fan cooler - 70% choke in all lines.

52 NMIs in total. (Rotary - 1, Field - 33, Inst - 3, Civil - 12,


3 Closing of NMI's (Before March 2021) 11.02.2021 All craft/Mfg Projects -3) Mfg 31.12.2021

Ref-III : Work permit closure for FY 21-22 (Till Nov'21) is


28.89% (Out of 12494 permits).
Permits closed at Requester and Issuer end - 3600
Permits closed by Requester, but pending at Issuer end -
1486 31.12.2021,
Permits short closed - 10 Rotary have completed
4 Closure of Work Permits need to be Improved 08.07.2021 All craft/Mfg P&U II & III : Work permit closure for FY 21-22 (Till Nov'21) All craft/Mfg
is 63.04% of 2159 permits). all the Permits
Permits closed at Requester and Issuer end - 1361
Permits closed by Requester, but pending at Issuer end - Nil
All Permits issued till Dec'21 to be closed in co -ordination
with ITS

Contractor Participation in Generating NMI needs


5 08.07.2021 All craft/Mfg Nil All craft 3 No by Field Raised
to be Improved
31 Nos of Container and Temporary Shed to be 2 Contractor containers remaining , 1 will remain and
6 25.11.2021 Maint Maint 01.03.2022
removed (Used for Ref 3 M&I) retained by Insp, Another 1 - M/S Shilpi

IFR Suit compliance for hot works to be OISD Guide line received , stating that all person entrying F&S Observed non compliance
7 improved. For contract 09.12.2021 inside plant should wear IFR Suit. To be complied All crafts of IFR Suit by Contractor

COGEN & CPP

Based on P&U-I BS CT renewal,


GE provided the foundation drawing. Assembly drwg requied
CPP Black start up cooling tower to be made Tendering Awarded, OPH -
1 05.12.2019 P&U/Civil/GE from OEM. Agency is to be lined up- to be made ready P&U/Civil /GE
ready. Target Mar 2022 (Agency
before Ref-III M&I as GT's planned to run with Black start CT /Materail Mobilized)

CPP Control room, Rack room & turbine hall roof CPP/Rack Room side temporary arrangement 100 % GE has to study and give report
2 07.01.2021 Civil /GE Civil/GE on healthiness of roof, Agency
leak to be attended. Completed, Turbine side GE to revert to be lined up,

GE has to study and give report


3 Cogen Control room roof leak to be attended. 07.01.2021 Civil Yet to start , Agency to be Lined Up Civil /GE on healthiness of roof, Agency
to be lined up,

GE has to study and give report


4 Concrete pieces falling from Turbine hall roof 25.11.2021 Civil Hipo NMI (Safety Net Received, Target:03.02.2022), TG 1 and Civil /GE on healthiness of roof, Agency
frequently, to be repaired TG 2 Temporary arrangement Completed
to be lined up,
Desal

1 Desal - Servicing of Ball Valves 28-Mar-18 Field/P&U/PE Servicing of Ball valves by M/s IEL. 2/12 valves servicing in Maint (Field) Comp by: 31.03.2022
progress. New agency lining up I/P
Screen Filter- DATA sheet Provided, Drg Provided, Availabe.
Budgetory Quote awaited 05.02.2022 (Inputs from GE for
2 Desal - Travelling Screen filter 21-Jan-20 P&U/PE/GE Data Sheet for associated equipment provided by GE Maint (Field) associated equipment)
Vendor called for Discussion - Expected 05.03.2022

Procurement of Catridge Feed Pump S/C & D/C Data Provided by GE on 29.07.2021,
3 22.07.2021 GE / Field PR Raised (PR No:7066588, 06.03.2021) for BF valves, Matls 1-May-22
Valve (Butter fly valve and NRV) - 700 G 104A/E
NRV - PR Raised (PR No.: 7369832, 28.12.2021)

1) False celing / flooring- Tender to be refloated. Estimation is


in progress.
Tender Inputs by 05.03.2022 .
4 Civil repair works in DESAL 6-Jun-18 Civil / 2) Repairs in Civil Structure - Joint survey done, Estimation is Civil Tentative Job completion by
Contract Cell in progress.
3) Damaged strom water canal repair work. Estimation is in 31.12.2022
progress

1) 2 Nos. Available and 2 Nos. not available. New Pump PR


5 Chlorinator water booster pumps 8-Jul-20 Rotary /Field No: 7348973. Matls / Rotary /Field CDD Apr'2022
2) Alternate Scheme Issued, Agency Lined-up- Completed

CDU III / VBU

on hold for M&I , (to be reviewed), Elec - Completed


Plant to be made ready for Operation, Inspection Survey
1 Plant-204-Equipments mothbolling as per IWL. 21.11.2019 Field / PE/Mfg/Insp. Mfg. Inst - Control room Inst
completed & Recommendation provided. Rotary , Electrical
identified (Spares available)
and Inst also to give report by 31.01.2022

14/17 completed (Balance 3 lines not able to identify - New


2 Pl-203 CRWS line blockage 07.01.2021 Civil/GE line is required). Pit Opened. Joint visit planned today Civil GE study I/P

Job planned, (Drg shared to concern),Temprorary


201G44A, Bearing cooling water sump to be
3 made ready 30.12.2021 Civil measurement will be explored. Foundation heght increased, Civil Job I/P, Compl by 03.03.2022
Concreting completed. Bolt and Grouting to be carried out

HGU/CRU

Scheme issued on 16.12.2021 and drawing issued on


Combined feed filter facility for CCR NHT 12.07.2021, Process datasheet given for filter, PSV, Inst on Agency available. , Awating for
1 25.11.2021 Field/Inst/Matls 16.12.2020 by PE, MR issued for new filter on 30.1.2021 by Field/Inst/Matls
( Scheme) GE, PR Rasied PR No 7332164, Dtd.; 30.11.2021. Spud taken Filter, Filter EDD: Aug 2022
during M&I, Piping pending

Recommendation given by PE  on 6.9.2021, Spares for 206-T-


2 Catalyst fines filter element replacement 25.11.2021 GE/Field/Matls 201A & 206-T-202A available at Stores and PR Raised for 2 Field/Matls Filter EDD: Aug 2022
sets of Filter Elements (PR No 7369831)

scheme for Replacing CCR Recontacting drum Drawing issued on 14.5.2020, spud taken during Aug 21 M&I,
3 trim cooler 206E-17 with new cooler 206E-117 to 25.11.2021 Field/Matls/Civil New cooler EDD Mar 2022, Foundation Job I/P, Piping job Field/Matls/Civil
improve the LPG yield pending. PO No:26956416, EDD End Mar'22
4 PCE chemical injection nozzle(206M203 Regen 25.11.2021 Field/Matls Recommendation given by PE on 9-10-2021. Matls PR No:7435603
section) replacement- Corroded

Recommendation given by PE on 23.9.2021 as per spare list.


5 Procurement of spare catalyst transfer special gas 25.11.2021 Field/Matls Budgetary Quote requested from OEM Seagault S.A. BQ - Field/Matls PR By:…..
tight valves -IGST
Recived, Requested to revise

Plant 206 reformate control valve replacement-


6 02.12.2021 PE/Inst/Matls PR No:7370161 Inst / Mtls EDD: June 2022
206LIC2602 to higher capacity

Fire proofing is damaged condition in many Job will be taken after award of
7 locations in plant 205 & 206 area to be rectified 09.12.2021 Civil Tender Floated, TE - Completed (CC No:023121) Civil contract - 3 months completion
at the earliest period

8 Cooling Water line leak to be attended 03.02.2022 Field Agency Lined up, Job I/P Comp by 11.03.2022

OHCU

21.02.2019 /
1 F-102 pilot burner flame indication not working. Inst/Mfg MOC circulated to all concern for comments
11.04.2019

Civil sructure damaged condtion at many


locations (Fire proofing damaged condition, End March 2022,
Tender Floated (CC No 23121 ) - Critical Locations completed, Critical One (11 Places
2 beams dislodged condition (covered in NMI)). 29.07.2021 Civil Civil /Mtls (CC)
Others being attended. TE 2 Completed, Price bid to be open Completed). Alternate Material
OHCU Structural Assessment & Strengthening job
has to be taken up on priority. to be explored to imporve life

Most of the places high temperature pipelines


are not insulated / cladding not done, Insulation
3 damaged condition. Reboilers are uninsulated 1-Nov-21 Civil Job I/P, Comp by: 31.03.2022
condition.

End March 2022,


Tender Floated (CC No 23121) (TE - Completed on Critical One (11 Places
4 C-15/C-17 Fire proofing to be done (ISA Point) 25.11.2021 Civil Civil / Mtls (CC)
22.02.2022) Completed). Alternate Material
to be explored to imporve life

Pump performance trial run to be taken up by PE & rotary.


207 G-5 A developing less flow (<145 m3/hr) and
5 207 G-5 B could not develop flow > 150 m3/h 25.11.2021 PE Planned in 21.01.2022. Pressure survey is planned on PE C/V CV to be revised as per PE
03.03.2022
Licensor- provided
7 207 F-102 Pass-2 and 5 issue 25.11.2021 PE taken up with development, Reply awaited PE communication. Under
discussion
Insulation of Reactor Bottom and Connected Pipe Lines to be
8 Reactor Depresurzing system Bypassed at HWC 10.02.2022 Inst/Civil Civil Comp by 07.03.2022
completed on Priority
C/V needs to be attended on Priority. (Only 30% is opening).
9 207 C 04 LCV A 10.02.2022 Inst Old Valve Servicing I/P (Taken from B C/V) Inst 2 Weeks

10 Gas Detectors /Analyzers 17.02.2022 Analyser 7 Number not working - Job I/P Analyser

SRU / UTILITIES
1) Oil removal Job started. Tender Floated. TE in progress
Civil/ 2) PE scheme for oil catcher issued. Constn drg re-issued by Tender Floated, (2000 KL
1 Storm water pond oil removal 2-Jun-17 EP&S/Mfg./PE/GE GE. GE/Mfg/Civil Remvoed, 6000 KL Tender I/P)
Agency: Price bid to be opened

Sulphur SILO Barrication to be provided (East & Mfg with GE shall meet to solve the sulphur dust problem. North Side Completed.,
2 20-Sep-18 GE/PE/MFG/ CIVIL GE/Mfg/Civil Between Silo and Plant to be
south) Meeting to be scheduled by 04.03.2022
covered

Steam coil IWL Received 28.12.2020


Mfg/Field/Insp/ Drawings released by Engg services on 31.01.2022 Steam Coil pipe Received,
3 Sulphur Pit-A water ingressing is heavy 26.12.2019 Civil/Engg Serv Civil - Dewatering Completed, Tender Floated, Price to be Field/Civil Civil - Price bid to be opened
opened

4 210-K-102B shed damaged to be replaced 16.01.2020 Civil/Insp/Field Material mobilization in progress, Completion By mar'2022 Civil 1-Mar-22

5 Plant-222, Cooling water line leak, 30.12.2021 Field/Civil Completed. Back Filling to be done Civil

Civil visited the site. Gratings ordered. Slabs replacement Job


6 Flooring and trench gratings in Sulphur area 14-Mar-19 Civil / Mfg. I/P - 8 Nos Replaced. Grating l;aying completed, North side Mfg
damaged
Florring completed . Mfg to confirm

Medical Oxygen Line (to R&D and Cylinder Filling Analyzer checked and found OK, UV operation to be checked
7 shed) Checklist to be prepared inorder to 06.01.2022 Mfg /Field Mfg
commission by Mfg

R&D - Hospital Building in and around to be Job I/P (Grass Cutting Completed, Cut grass to be removed,
8 06.01.2022 Civil Civil 25.02.2022
made ready Plumbing Fixture replaced)

9 Medical Oxygen Compressor associated piping to 06.01.2022 Field Drg preparation I/P by Agency, job in progress Field Copper tubing Material PR I/P
enable commissioning to be completed

Dewatering completed. Day lighting also completed. Insp to


10 Down stream Industrial line submerged with 06.01.2022 Civil Civil To be cheked with Inspection
confirm
water. Dewatering and Day ligting to improved

11 Plant 208/209/210 Plant entry restriction thru 03.03.2022 Field/Civil/GE EIL standard to be shared by GE GEField/Civil
barrication/fencing to be made ready
ISOM / DHDT
DHDT/NEW- HGU (211/214)
1 Pl-214 Devegitation 11.03.2021 Civil Completed (Mfg to Confirm) Civil 15.02.2022

Spud taken during M&I, control valve and piping jobs


2 VHPS interconnection scheme 25.11.2021 Field pending. Matls received and consumed during SD. Alternate Field/Matls
Matl available, Except 8" 600 G/V (PR No 7379698 - EDD June
2022)

3 211 K 1 C 1st Stage Cylinder Abnormal Sound 27.01.2022 Rotary 1st Stage Cylinder recevied. Installation I/P Rotary 30.03.2022

ISOM (212)
Plant 212 heavy isomerate FCV replacement to
1 02.12.2021 PE / Inst /Mtls Data Sheet Provide by PE on 08.10.2021, PR :7370161 Inst /Mtls EDD:June 2022
higher capacity -212FIC5902
Plant 212 NHDT separator bottom FCV
2 02.12.2021 PE / Inst /Mtls Data Sheet Provide by PE on 08.10.2021, PR :7370161 Inst /Mtls EDD:June 2022
replacement- to higher capacity 212FIC0803
01.06.2022
3 Fire Proofing work is in 212-K-3B 07.01.2021 Civil Tender Floated (CC 24721 - Agency lining up Mar End 2022 Civil

4 Debris/Vegitation in Rd-43 North side of ISOM 07.01.2021 Civil/Mfg Job I/P Civil 28.02.2022
GENERAL
1) EURO IV, ISOM area 2/15 is not working
1 CCTV in REF-3 Area / EURO IV, ISOM area 20.08.2020 Inst AMC to be renewed.
2) For Ref-3 CCTV: 6/8 working. Bal Vendor expected.
Usage of PPE to be adhered. DGM (Maint-Onsite) instructed H2S meter to be ensured even
2 Safety compliance Maint
all concerned to ensure safety first during job execution. by Maint.

All Safety showers continuous water flow to be PE issued scheme on 30.08.2021, Drg Issued on
02.01.20
3 ensured / Drinking Water Overhead tank PE/GE/Civil 20.12.2021.Temp arrangements for cabins done (Parts Civil Overhead Tank to be restored
Overflow /12.12.19 replaced). Tender inputs sent on:

4 All non functioning Neumann to be rectified on 25.11.2021 Electrical Awaiting for Spares (Expected in Apr 2022) Matls/Electrical Spares EDD: April 2022
priority in all units
Pipe line requiring insulation need to be
5 25.11.2021 Civil Job in progress (Additional Agency being lined up) Civil
completed on Priority
All Insulation debris to be removed from plant
6 25.11.2021 Civil Job in progress (Additional Agency being lined up) Civil
after M&I
Electrical Equipment Reliabiliy in all units to be As per Reliability, Now the rate of Failure is Nil . Motor
7 improved 25.11.2021 Elect/Reliability Conditions being monitored. Elect/Reliability

Damaged Canal Inside and Outside all Units to be


8 25.11.2021 Civil Job in progress (200 No Slabs casted and Curing I/P) Civil
closed on Priority
Vendor Service engineer expected within 2 weeks, Spares
Neumann communication system in plant-205,. procurement in progress.PR. 2901103 Dt.09.06.2020 (Under
9 5.11.2020 MFG/ Elect/Matls Matls Spares EDD: April 2022
not working. TCP, CDD Apr 2022 & PR.7117009 Dt. 05.05.2021. Bid
Opening 22.07.2021, CDD: Apr 2022
10 Faulty Neumann 2Nos.in ISOM 23.07.2020 Elect/Matls/Mfg 2nos working with low volume, Spare cord indented Mfg Spares EDD: April 2022
Pl-211 & 214 entire plant uninsulated line
11 26.12.2019 Field Job in progress (Additional Agency being lined up) Field
painting to be done
12 Operator Cabin tile replacement/painting 25.11.2021 Civil Material Received, Job will be completed by 28.02.2022 Civil Pt - 207 Completed, Others I/P

13 Neumann to be attended (List already circulated) 25.11.2021 Electrical Awaiting for Spares (Expected in Apr 2022) Electrical Spares EDD: April 2022

HGU field Operator cabin perapet wall, roof &


14 floor damaged. Safety hazard 3.12.2020 Civil Parapet wall, roof completed Civil 1-Mar-22
Vendor Service engineer expected within 2 weeks, Spares
15 Neumann communication system in plant-205,. 5.11.2020 MFG/ Elect/Matls procurement in progress.PR. 2901103 Dt.09.06.2020 (Under Matls Spares EDD: April 2022
not working. TCP, CDD Apr 2022 & PR.7117009 Dt. 05.05.2021. Bid
Opening 22.07.2021, CDD: Apr 2022
Along Road 3A Debris(Belonging to all crafts) are
16 10.02.2021 Maint
dumped. To be cleared
17 FG C/V Choking Issue (Plant 206/207) 17.02.2022 PE /Mfg PE Under Study PE /Mfg
Shutdown
Attended. CardJob
changed during short/long shutdown. Still
1 214-PV-4205 B Pressure control valve passing 02.07.2020 Inst/Mfg passing problem persist (214 C 08) - Bypass B/V to be Inst /Mfg
checked- Next Oppurtunity SD
2 207 F-102 TXI 4282 Skin temperature not working 25.11.2021 Inst. Sensor Faulty, SD Job Inst.

3 Automatic Blow back system Pressure swithches 01.07.21 Inst/Rotary Alternate is being explored. (Switch over to Electronic type) Inst.
not working by 31.01.2022. If OK will be extended to other switches
NEXT MEETING will be conducted through Zoom App on 10.03.2022 (Thursday)
Sl No. sysid NMIDate NMITime Circle SubCircle
1 21863 19/01/2022 10 REFINERY3 SRU/UTI

2 21928 23/01/2022 16 REFINERY3 SRU/UTI

3 22013 28/01/2022 11 REFINERY3 SRU/UTI


4 22053 28/01/2022 13 REFINERY3 SRU/UTI
5 22095 31/01/2022 11 REFINERY3 SRU/UTI

6 20810 06/12/2021 10 REFINERY3 SRU/UTI

7 21061 16/12/2021 08 REFINERY3 SRU/UTI

8 22070 31/01/2022 02 REFINERY3 SRU/UTI

9 22501 16/02/2022 09 REFINERY3 DHDT/NEW HGU

REF-III MAINT
WORKSHOP AND
YARDS
10 22615 22/02/2022 11 OTHERS

11 22730 25/02/2022 01 REFINERY3 SRU/UTI


UnSafeAct
Manholes / drain kept open

Weak / corroded structure

H2S / Cl2 / Ammonia / hazordous leaks


Unsafe platform / ladder / railing
No Approach / Damaged Approach Pathway

Unsafe platform / ladder / railing

Electrical Defect

Unsafe platform / ladder / railing

H2S / Cl2 / Ammonia / hazordous leaks

Damage to Civil Structures

Unsafe platform / ladder / railing


EIL
213GIB

222 PLANT AIR

Plant 213 New SWS


Plant 213
PLANT 210 SILO PLANT-Staircase

In Road 3L, opposite of Silos area

251MG101G
209 C4 2nd/3rd/4th platform hand rail corroded condition to be
attended-Notification 20000575404

C-16 Rich Amine Sampling Location

Ref-III Workshop

Plant-213 1st floor staircase


DOI
213GIB OWS PIT UNCOVERED CONDITION

222XIA/B TOP ROOF ASBESTOS DAMAGED AND OPENED UP


TO ATMOSPHERE WITH PIECES OF ASBESTOS FALLING
FREELY FROM TOP NOW AND THEN. TO BE ATTENDED TO
AVOID ANY ASBESTOS FALLING ON THE OPERATING
PERSONS.
213 D1A Sour water tank Breather vent passing resulting in H2S
leak in the tank roof area
Staircase ladder Step got broken creating unsafe condition.
Gratings are in Damaged condition
Approach platform of Silo area from 3L road is not proper.
concrete Slabs are missing and unsafe during vehicle entry.
251MG101G motor fan gaurd mesh has broken and came out
from its position. motor is running . please stop and rectify to avoid
further damage

platform hand rail corroded condition -it unsafe for work

While Taking Rich Amine Sample The H2S Reading in the H2S
meter went upto 100ppm. So i had to hold my breath to take
sample and to avoid any hazard to myself. But Also i felt slight
dizziness because of the exposure

The fall ceiling in room no.6 in the workshop is damaged and


hanging condition. Two pieces of them already fallen down.Others
are in a condition to fall on our heads who may be in that room at
any time. It should be rectified immediately.
Plant-213 1st floor staircase steps were fully damaged and
corroded condition.
Craft
Field Onsite

Civil

Field Onsite
Field Onsite
Field Onsite

Field Onsite

Rotary

Field Onsite

Field Onsite

Civil

Field Onsite
EntryDate
1/19/2022 11:17

1/23/2022 18:59

1/29/2022 11:18
1/29/2022 21:09
1/31/2022 16:17

12/6/2021 12:34

12/16/2021 9:50

1/31/2022 1:39

2/16/2022 9:32

2/22/2022 12:37

2/25/2022 15:54
SN. Unique No. Observations

In plant 214 : 214-F01 the radiation of


1 ASC-II 08/2017/12
furnace is very high
2 ASC-II 02/2018/06 Plant 207 structures near cooling tower are g
VR feed tank D1 & D2 old pump valve
ASC-II 03/2018/02 Seepage leak and accumulation in dyke.
3 (SRU Area)
SRU Ref 3 Pelletiser unit, conveyor, silo &
incinerator fine deposits of sulphur dust –
ASC-II 03/2018/03
Scrapper blade system removed – Dust
4 Control system to be brought in line.
Sweep gas system in SRU to be taken
ASC-II/ 08/2018/01
5 Online.
Ref-III Sulphur pit area only one access.
ASC-II/ 08/2018/03
6 Additional access ladder to be Provided.
201-F-2 platform to be provided for
7 ASC-II/ 08/2018/04
Sampling Purpose.
Plant 206 area reactor & regenerator area
8 ASC-II/ 08/2018/05
Radiation survey to be carried out.
CT-6 structure to be painted by special
9 ASC-II/ 04/2019/02
Paint to avoid corrosion.
10 ASC-II/ 06/2019/01 CBD leak in plant 212(ISOM).
ISOM plant 212 , E 20 and E12 platform
11 ASC-II/ 06/2019/02 and handrails are damaged. Civil Floor
having small holes.
12 ASC-II/ 11/2019/01 Flue gas leak near 201 cabin.
Spent catalyst to be removed from plant
13 ASC-II/ 10/2020/01
205
Responsibility

GM (Ref-III) / DGM (GE)/ GM(Ref-III)


GM (Ref-III) / DGM (Field Maint-Onsite)

GM (Ref-III) / DGM (Field Maint-Onsite)

GM (Ref-III) / DGM (PE)/DGM(Onsite)

GM (Ref-III) / DGM (Maint onsite)/instru

GM (Ref-III) / DGM (Maint-Onsite)/ DGM-G

GM (Ref-III) / DGM (Maint-Onsite)/ DGM-G

GM (Ref-III) / RSO

GM (Ref-III) / DGM (Maint-Onsite)


GM (Ref-III) / DGM (Maint-Onsite Field)

GM (Ref-III) / DGM (Maint-Onsite Field)

GM (Ref-III) / DGM (Maint-Onsite Field)

GM (Ref-III) / DGM (Maint-Onsite Field)


ATR

Completed
Completed

Leak arrested & Cleaning to be done by Civil

Scrapper blade fixed,

UV/ FT to be attended. Maint to attend.

Alternate ladder to be provided. Construction Drg issued Mar


20.Drg No 210 C 42276.

Completed

To be checked.

Job to be taken up.


Completed

IWL Issued, to be taken up during S/D. (PF replaced)

Completed

To be removed.