SP SINGLA CONSTRUCTIONS PVT LTD

MANPOWER
Sl. No. ACTIVITY DURATION START DATE END DATE MACHINERY OTHERS REMARKS
SKILLED UNSKILLED
R03-P2

BOX WALL 1ST LIFT


OUTER WALL STAGE 1
SHUTTERING 4/26/2019 3 5 CRANE

CONCRETING 4/26/2019 4/26/2019 2 4

OUTER WALL STAGE 2


TMT FIXING 4 4/26/2019 4/29/2019 2 4

SHUTTERING 4 4/30/2019 5/3/2019 3 5 CRANE

CONCRETING 1 5/4/2019 5/4/2019 2 4

OUTER WALL STAGE 3


TMT FIXING 3 4/27/2019 4/29/2019 2 4

SHUTTERING 3 4/30/2019 5/2/2019 3 5 CRANE

CONCRETING 1 5/3/2019 5/3/2019 2 4

OUTER WALL STAGE 4


TMT FIXING 3 5/5/2019 5/7/2019 2 4

SHUTTERING 3 5/8/2019 5/10/2019 3 5 CRANE

CONCRETING 1 5/11/2019 5/11/2019 2 4

LOWER PYLON
RIGHT SIDE
TMT FIXING 8 5/3/2019 5/10/2019 4 8 CRANE 100 MS PIPE

SHUTTERING 4 5/11/2019 5/14/2019 3 5 CRANE

CONCRETING 1 5/15/2019 5/15/2019 2 4

DESHUTTERING 1 5/18/2019 5/18/2019 2 4

LEFT SIDE
TMT FIXING 7 5/16/2019 5/22/2019 4 8 CRANE 100 MS PIPE

SHUTTERING 3 5/23/2019 5/25/2019 3 5 CRANE

CONCRETING 1 5/26/2019 5/26/2019 2 4

DESHUTTERING 1 5/29/2019 5/29/2019 2 4

BOX WALL 1ST LIFT


INNER WALL STAGE 1
TMT FIXING 3 5/12/2019 5/14/2019 2 4

SHUTTERING 5 5/15/2019 5/19/2019 3 5 CRANE

CONCRETING 1 5/20/2019 5/20/2019 2 4

INNER WALL STAGE 2


TMT FIXING 3 5/21/2019 5/23/2019 2 4

SHUTTERING 5 5/24/2019 5/28/2019 3 5 CRANE

CONCRETING 1 5/29/2019 5/29/2019 2 4

INNER WALL STAGE 3


TMT FIXING 3 5/30/2019 6/1/2019 2 4

SHUTTERING 3 6/2/2019 6/4/2019 3 5 CRANE

CONCRETING 1 6/5/2019 6/5/2019 2 4

DIAPHRAGM BEAM
STAGGING 3 5/30/2019 6/1/2019 3 5 CRANE 100 MS PIPE

BOTTOM SHUTTERING 2 6/2/2019 6/3/2019 4 4 CRANE

TMT FIXING 9 6/4/2019 6/12/2019 4 10 CRANE

SIDE SHUTTERING 3 6/13/2019 6/15/2019 3 5 CRANE

CONCRETING 1 6/16/2019 6/16/2019 3 5

DESHUTTERING 1 6/19/2019 6/19/2019 2 6

Page 1 of 8
SP SINGLA CONSTRUCTIONS PVT LTD
MANPOWER
Sl. No. ACTIVITY DURATION START DATE END DATE MACHINERY OTHERS REMARKS
SKILLED UNSKILLED

BOX WALL 2ND LIFT


OUTER WALL STAGE 1
STAGGING 2 6/6/2019 6/7/2019 1 3

TMT FIXING 3 6/8/2019 6/10/2019 2 4 100 MS PIPE

SHUTTERING 4 6/11/2019 6/14/2019 3 5 CRANE

CONCRETING 1 6/15/2019 6/15/2019 2 4

OUTER WALL STAGE 2


STAGGING 2 6/15/2019 6/16/2019

TMT FIXING 3 6/17/2019 6/19/2019 1 3 100 MS PIPE

SHUTTERING 4 6/20/2019 6/23/2019 3 5 CRANE

CONCRETING 1 6/24/2019 6/24/2019 2 4

OUTER WALL STAGE 3


TMT FIXING 3 6/16/2019 6/18/2019 2 4

SHUTTERING 3 6/19/2019 6/21/2019 3 5 CRANE

CONCRETING 1 6/22/2019 6/22/2019 2 4

OUTER WALL STAGE 4


TMT FIXING 3 6/25/2019 6/27/2019 2 4

SHUTTERING 3 6/28/2019 6/30/2019 3 5 CRANE

CONCRETING 1 7/1/2019 7/1/2019 2 4

INNER WALL STAGE 1


STAGGING 3 7/2/2019 7/4/2019 1 3

TMT FIXING 3 7/5/2019 7/7/2019 2 4

SHUTTERING 4 7/8/2019 7/11/2019 3 5 CRANE

CONCRETING 1 7/12/2019 7/12/2019 2 4

INNER WALL STAGE 2


STAGGING 3 7/13/2019 7/15/2019 1 3

TMT FIXING 3 7/16/2019 7/18/2019 2 4

SHUTTERING 4 7/19/2019 7/22/2019 3 5 CRANE

CONCRETING 1 7/23/2019 7/23/2019 2 4

INNER WALL STAGE 3


TMT FIXING 3 7/24/2019 7/26/2019 2 4

SHUTTERING 3 7/27/2019 7/29/2019 3 5 CRANE

CONCRETING 1 7/30/2019 7/30/2019 2 4


TOP SLAB

TMT FIXING 15 7/20/2019 8/3/2019 2 2 CRANE

CONCRETING & PLACING 15 7/21/2019 8/4/2019 1 2

Page 2 of 8
SP SINGLA CONSTRUCTIONS PVT LTD
MANPOWER
Sl. No. ACTIVITY DURATION START DATE END DATE MACHINERY OTHERS REMARKS
SKILLED UNSKILLED
R01 DECK SLAB
EXPANSION JOINT

SHUTTERING 4 5/5/2019 5/8/2019 2 2

FIXING & LEVELING 5 5/9/2019 5/13/2019 2 2

CONCRETING 1 5/14/2019 5/14/2019 1 2


LA1 RETAINING WALL (BALANCE PORTION)

FOUNDATION
EXCAVATION 3 5/10/2019 5/12/2019 EX 70, TIPPER R07 DRAWING REQUIRED
PCC 3 5/13/2019 5/15/2019 2 5

TMT FIXING 4 5/16/2019 5/19/2019 2 4

SHUTTERING 2 5/20/2019 5/21/2019 2 4 HYDRA


CONCRETING 1 5/22/2019 5/22/2019 2 2

WALL
TMT FIXING 5 5/24/2019 5/28/2019 2 4

SHUTTERING 5 5/29/2019 6/2/2019 2 4 HYDRA


CONCRETING 1 6/3/2019 6/3/2019 2 2
CRASH BARRIER

DECK PORTION
TMT FIXING 3 5/3/2019 5/5/2019 3 3

SHUTTERING 8 5/6/2019 5/13/2019 3 3 HYDRA


CONCRETING 5/9/2019 5/14/2019 1 2

DESHUTTERING 1 5/17/2019 5/17/2019 1 3 HYDRA


LA1 PORTION
TMT FIXING 2 5/15/2019 5/16/2019 3 3

SHUTTERING 4 5/17/2019 5/20/2019 3 3 HYDRA


CONCRETING 1 5/21/2019 5/21/2019 1 2

DESHUTTERING 1 5/24/2019 5/24/2019 1 3 HYDRA


LA2 PORTION
TMT FIXING 2 5/22/2019 5/23/2019 3 3

SHUTTERING 4 5/24/2019 5/27/2019 3 3 HYDRA


CONCRETING 1 5/28/2019 5/28/2019 1 2

DESHUTTERING 1 5/31/2019 5/31/2019 1 3 HYDRA


END KERB

DECK PORTION
TMT FIXING 1 5/18/2019 5/18/2019 2 2

SHUTTERING 2 5/19/2019 5/20/2019 2 2 HYDRA


CONCRETING 1 5/21/2019 5/21/2019 1 2

DESHUTTERING 1 5/24/2019 5/24/2019 1 3 HYDRA


INTERMEDIATE KERB

TMT FIXING 1 5/22/2019 5/22/2019 2 2

SHUTTERING 2 5/23/2019 5/24/2019 2 2 HYDRA


CONCRETING 1 5/25/2019 5/25/2019 1 2

DESHUTTERING 1 5/28/2019 5/28/2019 1 3 HYDRA

Page 3 of 8
SP SINGLA CONSTRUCTIONS PVT LTD
MANPOWER
Sl. No. ACTIVITY DURATION START DATE END DATE MACHINERY OTHERS REMARKS
SKILLED UNSKILLED
APPROACH FILLING

LA1 PORTION
FILTER MEDIA 3 5/1/2019 5/3/2019 2 2

SAND FILLING 3 5/15/2019 5/17/2019 2 2 ROLLER


GSB 3 5/18/2019 5/20/2019 1 1 ROLLER
DLC 5 5/21/2019 5/25/2019 2 6

PQC 8 5/28/2019 6/4/2019 2 6

LA2 PORTION
FILTER MEDIA 3 5/4/2019 5/6/2019 2 2

SAND FILLING 3 5/18/2019 5/20/2019 2 2

GSB 3 5/21/2019 5/23/2019 1 1

DLC 5 5/26/2019 5/30/2019 2 6

PQC 8 6/5/2019 6/12/2019 2 6


ELECTRICAL LIGHTING

INSERT PLATE FIXING 2 5/31/2019 6/1/2019 2

POLE FIXING 4 6/13/2019 6/16/2019 4

WIRING 3 6/17/2019 6/19/2019 4

LIGHT INSTALLATION 1 6/20/2019 6/20/2019 2


WEARING COURSE

MASTIC ASPHALT 4 6/19/2019 6/22/2019 4 4

ASPHALTIC CONCRETE 4 6/23/2019 6/26/2019 4 4


OPENING TO TRAFFIC

OPENING TO TRAFFIC 1 6/27/2019 6/27/2019

Page 4 of 8
SP SINGLA CONSTRUCTIONS PVT LTD
MANPOWER
Sl. No. ACTIVITY DURATION START DATE END DATE MACHINERY OTHERS REMARKS
SKILLED UNSKILLED
R02 DECK SLAB
EXPANSION JOINT

SHUTTERING 4 5/5/2019 5/8/2019 2 2

FIXING & LEVELING 5 5/9/2019 5/13/2019 2 2

CONCRETING 1 5/14/2019 5/14/2019 1 2


RA2 RETAINING WALL

FOUNDATION-STAGE 1
EXCAVATION 5 5/5/2019 5/9/2019 EX 70, TIPPER
PCC 6 5/10/2019 5/15/2019 2 5

TMT FIXING 6 5/16/2019 5/21/2019 2 4

SHUTTERING 2 5/22/2019 5/23/2019 2 4 HYDRA


CONCRETING 1 5/24/2019 5/24/2019 2 2

FOUNDATION-STAGE 2
EXCAVATION 5 5/25/2019 5/29/2019 EX 70, TIPPER
PCC 6 5/30/2019 6/4/2019 2 5

TMT FIXING 6 6/5/2019 6/10/2019 2 4

SHUTTERING 2 6/11/2019 6/12/2019 2 4 HYDRA


CONCRETING 1 6/13/2019 6/13/2019 2 2

WALL 1ST LIFT STAGE 1


TMT FIXING 3 5/26/2019 5/28/2019 2 4

SHUTTERING 5 5/29/2019 6/2/2019 2 4 HYDRA


CONCRETING 1 6/3/2019 6/3/2019 2 2

WALL 1ST LIFT STAGE 2


TMT FIXING 3 6/4/2019 6/6/2019 2 4

SHUTTERING 5 6/7/2019 6/11/2019 2 4 HYDRA


CONCRETING 1 6/12/2019 6/12/2019 2 2

WALL 2ND LIFT STAGE 1


TMT FIXING 3 6/13/2019 6/15/2019 2 4

SHUTTERING 5 6/16/2019 6/20/2019 2 4 HYDRA


CONCRETING 1 6/21/2019 6/21/2019 2 2

WALL 2ND LIFT STAGE 1


TMT FIXING 3 6/22/2019 6/24/2019 2 4

SHUTTERING 5 6/25/2019 6/29/2019 2 4 HYDRA


CONCRETING 1 6/30/2019 6/30/2019 2 2
CRASH BARRIER

DECK PORTION
TMT FIXING 3 5/29/2019 5/31/2019 3 3

SHUTTERING 8 6/1/2019 6/8/2019 3 3 HYDRA


CONCRETING 6/4/2019 6/9/2019 1 2

DESHUTTERING 1 6/12/2019 6/12/2019 1 3 HYDRA


RA1 PORTION
TMT FIXING 2 6/10/2019 6/11/2019 3 3

SHUTTERING 4 6/12/2019 6/15/2019 3 3 HYDRA


CONCRETING 1 6/16/2019 6/16/2019 1 2

DESHUTTERING 1 6/19/2019 6/19/2019 1 3 HYDRA


RA2 PORTION
TMT FIXING 2 6/17/2019 6/18/2019 3 3

SHUTTERING 4 6/19/2019 6/22/2019 3 3 HYDRA


CONCRETING 1 6/23/2019 6/23/2019 1 2

DESHUTTERING 1 6/26/2019 6/26/2019 1 3 HYDRA

Page 5 of 8
SP SINGLA CONSTRUCTIONS PVT LTD
MANPOWER
Sl. No. ACTIVITY DURATION START DATE END DATE MACHINERY OTHERS REMARKS
SKILLED UNSKILLED
END KERB

DECK PORTION
TMT FIXING 1 6/13/2019 6/13/2019 2 2

SHUTTERING 2 6/14/2019 6/15/2019 2 2 HYDRA


CONCRETING 1 6/16/2019 6/16/2019 1 2

DESHUTTERING 1 6/19/2019 6/19/2019 1 3 HYDRA


INTERMEDIATE KERB

TMT FIXING 1 6/17/2019 6/17/2019 2 2

SHUTTERING 2 6/18/2019 6/19/2019 2 2 HYDRA


CONCRETING 1 6/20/2019 6/20/2019 1 2

DESHUTTERING 1 6/23/2019 6/23/2019 1 3 HYDRA


APPROACH FILLING

RA1 PORTION
FILTER MEDIA 3 7/1/2019 7/3/2019 2 2

SAND FILLING 5 6/10/2019 6/14/2019 2 2 ROLLER


GSB 4 6/15/2019 6/18/2019 1 1 ROLLER
DLC 7 6/19/2019 6/25/2019 2 6

PQC 8 6/28/2019 7/5/2019 2 6

RA2 PORTION
FILTER MEDIA 3 7/4/2019 7/6/2019 2 2

SAND FILLING 4 6/15/2019 6/18/2019 2 2

GSB 3 6/19/2019 6/21/2019 1 1

DLC 7 6/26/2019 7/2/2019 2 6

PQC 8 7/6/2019 7/13/2019 2 6


ELECTRICAL LIGHTING

INSERT PLATE FIXING 2 7/3/2019 7/4/2019 2

POLE FIXING 4 7/14/2019 7/17/2019 4

WIRING 3 7/18/2019 7/20/2019 4

LIGHT INSTALLATION 1 7/21/2019 7/21/2019 2


WEARING COURSE

MASTIC ASPHALT 4 7/20/2019 7/23/2019 4 4

ASPHALTIC CONCRETE 4 7/24/2019 7/27/2019 4 4


OPENING TO TRAFFIC

OPENING TO TRAFFIC 1 7/28/2019 7/28/2019

Page 6 of 8
SP SINGLA CONSTRUCTIONS PVT LTD
MANPOWER
Sl. No. ACTIVITY DURATION START DATE END DATE MACHINERY OTHERS REMARKS
SKILLED UNSKILLED
R18-P2
PILE CAP

EXCAVATION 4/29/2019

PCC & BED PREPRATION 4 4/30/2019 5/3/2019 3 15 CRANE

PILE TRIMMING 10 5/4/2019 5/13/2019 8 8 CRANE

TMT FIXING 10 5/14/2019 5/23/2019 5 15 CRANE

SHUTTERING 3 5/24/2019 5/26/2019 3 7 CRANE

CONCRETING 1 5/27/2019 5/27/2019 4 8

DESHUTTERING 2 5/29/2019 5/30/2019 3 3 CRANE

BACKFILLING UPTO PC TOP 4 5/31/2019 6/3/2019


BOX WALL 1ST LIFT-LHS

OUTER WALL
TMT FIXING 3 6/4/2019 6/6/2019 2 4

SHUTTERING 3 6/7/2019 6/9/2019 3 5 CRANE

CONCRETING 1 6/10/2019 6/10/2019 2 4

UNDERPASS WALL
TMT FIXING 3 6/11/2019 6/13/2019 2 4

SHUTTERING 3 6/14/2019 6/16/2019 3 5 CRANE

CONCRETING 1 6/17/2019 6/17/2019 2 4

INNER WALL
TMT FIXING 1 6/18/2019 6/18/2019 2 4

SHUTTERING 3 6/19/2019 6/21/2019 3 5 CRANE

CONCRETING 1 6/22/2019 6/22/2019 2 4


BOX WALL 1ST LIFT-RHS

OUTER WALL
TMT FIXING 3 6/23/2019 6/25/2019 2 4

SHUTTERING 3 6/26/2019 6/28/2019 3 5 CRANE

CONCRETING 1 6/29/2019 6/29/2019 2 4

UNDERPASS WALL
TMT FIXING 3 6/30/2019 7/2/2019 2 4

SHUTTERING 3 7/3/2019 7/5/2019 3 5 CRANE

CONCRETING 1 7/6/2019 7/6/2019 2 4

INNER WALL
TMT FIXING 1 7/7/2019 7/7/2019 2 4

SHUTTERING 3 7/8/2019 7/10/2019 3 5 CRANE

CONCRETING 1 7/11/2019 7/11/2019 2 4


LOWER PYLON
LEFT SIDE

TMT FIXING 4 5/29/2019 6/1/2019 4 8 CRANE

SHUTTERING 3 6/2/2019 6/4/2019 3 5 CRANE

CONCRETING 1 6/5/2019 6/5/2019 2 4

DESHUTTERING 1 6/8/2019 6/8/2019 2 4


RIGHT SIDE

TMT FIXING 4 6/6/2019 6/9/2019 4 8 CRANE

SHUTTERING 3 6/10/2019 6/12/2019 3 5 CRANE

CONCRETING 1 6/13/2019 6/13/2019 2 4

DESHUTTERING 1 6/16/2019 6/16/2019 2 4

Page 7 of 8
SP SINGLA CONSTRUCTIONS PVT LTD
MANPOWER
Sl. No. ACTIVITY DURATION START DATE END DATE MACHINERY OTHERS REMARKS
SKILLED UNSKILLED
DIAPHRAGM BEAM

STAGGING 3 6/17/2019 6/19/2019 3 5 CRANE 100 MS PIPE

BOTTOM SHUTTERING 2 6/20/2019 6/21/2019 4 4 CRANE

TMT FIXING 8 6/22/2019 6/29/2019 4 10 CRANE

SIDE SHUTTERING 3 6/30/2019 7/2/2019 3 5 CRANE

CONCRETING 1 7/3/2019 7/3/2019 3 5

DESHUTTERING 1 7/6/2019 7/6/2019 2 6


BOX WALL 2ND LIFT LHS

OUTER WALL
TMT FIXING 3 7/7/2019 7/9/2019 2 4

SHUTTERING 5 7/10/2019 7/14/2019 3 5 CRANE

CONCRETING 1 7/15/2019 7/15/2019 2 4

UNDERPASS WALL
TMT FIXING 3 7/16/2019 7/18/2019 2 4

SHUTTERING 5 7/19/2019 7/23/2019 3 5 CRANE

CONCRETING 1 7/24/2019 7/24/2019 2 4

INNER WALL
TMT FIXING 3 7/24/2019 7/26/2019 2 4

SHUTTERING 3 7/27/2019 7/29/2019 3 5 CRANE

CONCRETING 1 7/30/2019 7/30/2019 2 4


BOX WALL 2ND LIFT RHS

OUTER WALL
TMT FIXING 3 7/16/2019 7/18/2019 2 4

SHUTTERING 5 7/19/2019 7/23/2019 3 5 CRANE

CONCRETING 1 7/24/2019 7/24/2019 2 4

UNDERPASS WALL
TMT FIXING 3 7/25/2019 7/27/2019 2 4

SHUTTERING 5 7/28/2019 8/1/2019 3 5 CRANE

CONCRETING 1 8/2/2019 8/2/2019 2 4

INNER WALL
TMT FIXING 3 8/3/2019 8/5/2019 2 4

SHUTTERING 3 8/6/2019 8/8/2019 3 5 CRANE

CONCRETING 1 8/9/2019 8/9/2019 2 4


TOP SLAB

TMT FIXING 10 8/10/2019 8/19/2019 2 2 CRANE

CONCRETING & PLACING 10 8/11/2019 8/20/2019 1 2