You are on page 1of 3

Date: July 10, 2023

CONCRETE POURING REQUEST


NO. 007

NSDR AND PARTNERS


26 Courtyard Bldg. Sgt. Esguerra, Quezon City

Originator :
Project : GO-DAVID RESIDENCE
20 Illinois St. Northeast Greenhills, San Juan City

DATE REQUESTED: July 10, 2023


TIME REQUESTED: 10:00 AM
Cistern Wall, Isolated Footings/C1F1, Rear J thru K, Right Side 1 thru
STRUCTURE/MEMBER:
2, C2 Footing
LOCATION OF
Along Grid Line
MEMBER:
REFERENCE
See Attached Drawings
DRAWINGS:

DATE OF POURING: July 11, 2023 TIME OF POURING: 10:00 AM


CONCRETE SUPPLIER: Topstar ACTUAL SLUMP: 6” to 8”
NUMBER OF
AGGREGATES SIZE: 3/8” & ¾” 8
SAMPLES:
CONC. COMP. 3000psi G-3/4 PCD
TYPE OF MIXTURE Ready Mix
STRENGTH 28 days
PLACEMENT
Direct Pouring CURING METHOD: 28 days
METHOD:
ESTIMATED VOLUME: 15.0 cu. m ADMIXTURE: PPCI R2

INSPECTION CHECKLIST
Checked & REMARKS
ITEM FOR INSPECTION YES NO N/A Verified by: (Approved
MBDC NSDR /Disapproved)
APP. DIS.
1. Line and Grade √
2. Excavation / substructure

preparation
3. Lean concrete / Gravel bedding √
4. Thermal protection / vapor

barrier
5. Rebar works √
6. Formworks √
7. Embedded Items/roughing-ins:
- Electrical √
- Mechanical √
- Plumbing / Sanitary √
3rd floor Courtyard Building #26 Sgt. Esguerra Street South Triangle, Quezon City
Tel. Nos. (632) 410-1542, (632) 416-9206 Email add: admin@nsdrandpartners.com
www.nsdrandpartners.com
- Fire Protection √
- Others
8. Construction joints, waterstop,

etc.
9. Concreting equipment √
10. Others :
10.a: Spacer √
10.b: Lighting Equipment √
10.c: Soil Poisoning √
10.d: Safety/Warning Sign √
NOTE / COMMENTS:

Inspected by: Requested by:


______________________ ____________________

Assisted by: Approved by:


______________________ ____________________

Prepared by : ____________________________
Project Manager

3rd floor Courtyard Building #26 Sgt. Esguerra Street South Triangle, Quezon City
Tel. Nos. (632) 410-1542, (632) 416-9206 Email add: admin@nsdrandpartners.com
www.nsdrandpartners.com
A B C D E F G H I J K

PPPPPPPP

CPR
007

1 C2 C2
1

RETAINING WALL FOOTING-(RETW-02)


RETAINING WALL FOOTING-(RETW-01)

2 2

2' 2'
3 3

4 4

5 5

6 6

A B C D E F G H I J K

FOUNDATION PLAN
SCALE: 1:50 MTS