You are on page 1of 1

Doc.Ref. : MASB-ITP-ST Form No.

: MASB-C-ST-07

Contractor : Client :
MENUJU ASAS SDN BHD (496835-A)
Project :
PROJEK LEBUHRAYA PERSISIRAN PANTAI BARAT: KERJA-KERJA MENAIKTARAF
JALAN PERSEKUTUAN FT005(TELUK INTAN-KG LEKIR) PERAK DARUL RIDZUAN
(REKA DAN BINA)
Consultant :

DURING CONCRETING CHECK LIST


Specification Req. - JKR/SPJ/2008-S9, Section 9 (clause 9.5,9.8) Job ref.
Location : RFI No.

Structure stage : Date

Drawing No. :

DURING CONCRETING

INSPECTION
No. Criteria/ Standards Remarks
Contractor Consultant

1 Ready-mixed concrete/ Gred

2 Slump test

3 Concrete cube taken

4 Reinforcement inspected and approved

5 Placing of concrete - Dry condition

- Under water

6 Placement Temperature (not more 36°C)

7 Compaction

8 Construction joints

9 Formwork - rigid and tight (no loss grout or mortar)

- formwork supports in position

10 Curing and protection

* Marks : √ if comply to specificatiom /and Drawings

Х if not comply to specificatiom /and Drawings (refer to NCR form)

Comments :

Submitted by : Checked by : Verified by (Consultant)

Site Supervisor Site Engineer/ C.Manager C.O.W. A.R.E / R.E


Date : Date : Date : Date :

ST/No. 07 Form Rev 00/15.09.15 Structure

You might also like