ENHANCEMENT OF WATER CATCHMENTS IN GABILEY DISTRICT, SOMALILAND

ID Task Name Duration Start Finish May 2023 June 20 23 July 2023
1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15
1 WORK SCHEDULE
2 MOBILIZATION

3 Mobilization of manpower, tools and 2 days Mon 5/1/23 Tue 5/2/23


equipments to the sites

4 CONSTRUCTION OF
CHAINLINKED FENCE

5 Excavation (diging) for the construction 2 days Wed 5/3/23 Thu 5/4/23
of concrete pillar base

6 Hardcore filling and lean concrete 4 days Fri 5/5/23 Mon 5/8/23
casting for the base of the fence post on
the prepared holes (includes 1-day for
curing)

7 Steel post fixing on the holes with a 6 days Tue 5/9/23 Sun 5/14/23
proper plan concrete mix (includes
1-day for curing)

8 Fixing the steel chainlink on the erected 8 days Mon 5/15/23 Mon 5/22/23
steel post

9 Fixing of the steel gate for the water 2 days Tue 5/23/23 Wed 5/24/23
catchment including eracting the steel
post columns for the gate

10 LANDSCAPE PREPARATION AND


WATER TROUGH
CONSTRUCTION

11 Cleaning and removing 0.3m depth of 5 days Thu 5/25/23 Mon 5/29/23
the top soil for the construction of water
troughs

12 Hardcore (broken stone) filling above 12 days Tue 5/30/23 Sat 6/10/23
where the loos soil has been removed
(including lean concrete casting of the
troughs base)

13 RCC concrete bottom base laying for 5 days Sun 6/11/23 Thu 6/15/23
both troughs (includes re-bar
preparation and laying, formwork fixing,
concrete casting and curing)

14 RCC concrete side walls and short top 7 days Fri 6/16/23 Thu 6/22/23
slab construction for the troughs
(includes re-bar preparation and laying,
formwork fixing, concrete casting and
curing)

15 INSTALLATION OF WATER
LINES AND WATERTANKS AND
WATER INLET CHAMBER
CONSTRUCTION

16 Excavation for the construction of the 7 days Fri 6/23/23 Thu 6/29/23
water tank base and water inlet chamber
including excavation for the pipe
installation

17 Hardcore filling and lean concrete 3 days Fri 6/30/23 Sun 7/2/23
casting for the bases of the water tank
(includes 1-day for curing)

18 RCC concrete water inlet chamber box 7 days Mon 7/3/23 Sun 7/9/23
construction at the edge of the water
catchment (includes re-bar preparation
and laying, formwork fixing, concrete
casting and curing)

19 Plain concrete casting on the prepared 2 days Mon 7/10/23 Tue 7/11/23
hardcore for the base of the water tank

20 Installation of the water tank, water 7 days Fri 7/7/23 Thu 7/13/23
pump and the pipe lines including all the
back filling and coviring of the pipe lines

21 INSTALLATION OF THE SOLAR


PANEL AND EXCAVATION FOR
THE WATER CATCHEMENTES

22 Installation of the steel frame to hold the 6 days Sat 6/24/23 Thu 6/29/23
water panel including the excavation,
fixing of the steel frames, and installing
the of solar panels and electric cables

23 Excavation of water catchments bottom 10 days Fri 6/30/23 Sun 7/9/23


to direct the water to the pump location

24 DEMOBILIZATION

25 Handovering and Demobilization 1 day Fri 7/14/23 Fri 7/14/23

Project: GABILAY DISTRICT WATER CATCHMEN Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: MARCH 12, 2023 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Note: starting date of the project may subjected to changes. Page 1