ID Task Name Duration Start Finish May 2023 June 20 23 July 2023
1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15
1 WORK SCHEDULE
2 MOBILIZATION
4 CONSTRUCTION OF
CHAINLINKED FENCE
5 Excavation (diging) for the construction 2 days Wed 5/3/23 Thu 5/4/23
of concrete pillar base
6 Hardcore filling and lean concrete 4 days Fri 5/5/23 Mon 5/8/23
casting for the base of the fence post on
the prepared holes (includes 1-day for
curing)
7 Steel post fixing on the holes with a 6 days Tue 5/9/23 Sun 5/14/23
proper plan concrete mix (includes
1-day for curing)
8 Fixing the steel chainlink on the erected 8 days Mon 5/15/23 Mon 5/22/23
steel post
9 Fixing of the steel gate for the water 2 days Tue 5/23/23 Wed 5/24/23
catchment including eracting the steel
post columns for the gate
11 Cleaning and removing 0.3m depth of 5 days Thu 5/25/23 Mon 5/29/23
the top soil for the construction of water
troughs
12 Hardcore (broken stone) filling above 12 days Tue 5/30/23 Sat 6/10/23
where the loos soil has been removed
(including lean concrete casting of the
troughs base)
13 RCC concrete bottom base laying for 5 days Sun 6/11/23 Thu 6/15/23
both troughs (includes re-bar
preparation and laying, formwork fixing,
concrete casting and curing)
14 RCC concrete side walls and short top 7 days Fri 6/16/23 Thu 6/22/23
slab construction for the troughs
(includes re-bar preparation and laying,
formwork fixing, concrete casting and
curing)
15 INSTALLATION OF WATER
LINES AND WATERTANKS AND
WATER INLET CHAMBER
CONSTRUCTION
16 Excavation for the construction of the 7 days Fri 6/23/23 Thu 6/29/23
water tank base and water inlet chamber
including excavation for the pipe
installation
17 Hardcore filling and lean concrete 3 days Fri 6/30/23 Sun 7/2/23
casting for the bases of the water tank
(includes 1-day for curing)
18 RCC concrete water inlet chamber box 7 days Mon 7/3/23 Sun 7/9/23
construction at the edge of the water
catchment (includes re-bar preparation
and laying, formwork fixing, concrete
casting and curing)
19 Plain concrete casting on the prepared 2 days Mon 7/10/23 Tue 7/11/23
hardcore for the base of the water tank
20 Installation of the water tank, water 7 days Fri 7/7/23 Thu 7/13/23
pump and the pipe lines including all the
back filling and coviring of the pipe lines
22 Installation of the steel frame to hold the 6 days Sat 6/24/23 Thu 6/29/23
water panel including the excavation,
fixing of the steel frames, and installing
the of solar panels and electric cables
24 DEMOBILIZATION
Project: GABILAY DISTRICT WATER CATCHMEN Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: MARCH 12, 2023 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress