CONSTRUCTION OF ROAD FROM PISSAN TO HOPER NAGAR (40 KM) I/C BRIDGES AND ALLIED STRUCTURES
(CONSTRUCTION/METALLING OF ROAD FROM GORIKOTE ASTORE TO SHAGARTHAN SKARDU)
ch 1 January 1 November 1 September 1 July 1 May 1 Ma ID Task Name Duration 4/28 9/22 2/16 7/12 12/6 5/2 9/26 2/20 7/17 12/11 5/7 10/1 1 Preliminaries 21 days
2 Earth Work 245 days
3 Road Works 91 days
4 Drainage & Erosion Works 266 days
5 Structure Culverts 119 days
6 Structure Bridge 175 days
7 General & Misc Works 28 days
8 Completion & Handing Taking 24 days