You are on page 1of 2

ID Task Name Baseline StartBaseline Finish Baseline 03 Jul '23 24 Jul '23 14 Aug '23 04 Sep '23 25 Sep

'23 14 Aug '23 04 Sep '23 25 Sep '23 16 Oct '23 06 Nov '23 27 Nov '23
Duration S S M T W T F S S M T W T F S S M T W
1 Commencement Work Mon 17-07-23 Thu 27-07-23 10 days
2 Laying of cables of different voltage grade Tue 18-07-23 Thu 31-08-23 39 days
3 Supply of nickel-plated, flame proof IIA/IIB Mon 07-08-23 Mon 21-08-23 13 days
double compression type brass cable glands
4 Supply of nickel plated brass single Mon 07-08-23 Mon 21-08-23 13 days
compression cable glands
5 Termination of XLPE insulated armoured Fri 01-09-23 Wed 20-09-23 17 days
power cables
6 Installation of prefabricated hot dip Tue 26-09-23 Wed 25-10-23 26 days
galvanised steel cable trays
7 Installation, connection, testing and Tue 17-10-23 Tue 31-10-23 13 days
commissioning of flame proof weather proof
lighting/power panels
8 Installation of Junction Box Tue 17-10-23 Mon 23-10-23 6 days
9 Installation of Platform Lighting pole Thu 26-10-23 Sat 11-11-23 15 days
10 Installation, connection, testing and Mon 30-10-23 Mon 13-11-23 13 days
commissioning of flame proof/Div.2 lighting
fixtures
11 Supply, installation and connection of lightning Tue 17-10-23 Sat 21-10-23 5 days
arrestors
12 Installation and connection of GI earthing strip Mon 16-10-23 Tue 31-10-23 14 days
13 Connecting individual equipment to the earth Mon 23-10-23 Sat 04-11-23 12 days
strip
14 Site Handover Mon 13-11-23 Mon 20-11-23 7 days

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: Instrumentation Schedul
Summary Manual Task Baseline
Date: Wed 11-10-23
Project Summary Duration-only Baseline Milestone
External Tasks Manual Summary Rollup Baseline Summary
External Milestone Manual Summary Progress

Page 1
27 Nov '23 18 Dec '23 08 Jan '24 29 Jan '24 19 Feb '24 11 Mar '24 01 Apr '24 22 Apr '24 13 May '24 03 Jun '24 24 Jun '24 15 Jul '24 05 Aug '24 26 Aug '24 16 Sep '24
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: Instrumentation Schedul
Summary Manual Task Baseline
Date: Wed 11-10-23
Project Summary Duration-only Baseline Milestone
External Tasks Manual Summary Rollup Baseline Summary
External Milestone Manual Summary Progress

Page 2

You might also like