ID Task Name Duration Start Finish Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025

Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 Infrastructural 32 wks 20-09-24 01-05-25
Development Phase I –
Foundation and
Connectivity
2 Infrastructural 24 wks 02-05-25 16-10-25
Development Phase II –
Specialized Facilities and
Community Amenities
3 Marketing Campaigns, 56 wks 20-09-24 16-10-25
Global Outreach, Workforce
Development, and Training
Initiatives
4 Implementing Institutional 16 wks 17-10-25 05-02-26
Model for Zone
Management
5 Pilot Industrial Operations, 16 wks 06-02-26 28-05-26
Feedback Integration, and
Continuous Improvement

Task Summary Inactive Milestone Duration-only Start-only External Milestone Path Predecessor Summary Task Manual Progress
Project: PLAN BEFORE DEVELOP
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Path Predecessor Normal Task
Date: 05-01-24
Milestone Inactive Task Manual Task Manual Summary External Tasks Path Predecessor Milestone Task Progress