ID Task Task Name Duration Start Finish 18/12 19/12 20/12 21/12 22/12 23/12 24/12 25/12 26/12

18/12 19/12 20/12 21/12 22/12 23/12 24/12 25/12 26/12 27/12 28/12 29/12 30/12 31/12 01/01 02/01 03/01
1 PERBAIKAN ACP SISI CYBER 42 days 20/12/2021 30/01/2022
2 PERKUATAN BAJA 14 days 20/12/2021 02/01/2022
3 PERKUATAN ACP 7 days 03/01/2022 09/01/2022
4 PEMASANGAN ACP 14 days 10/01/2022 23/01/2022
5 REPOSISI ARM 2 days 24/01/2022 25/01/2022
6 PEMASANGAN CAPPING ACP 2 days 26/01/2022 27/01/2022
7 PEMBONGKARAN GONDOLA 3 days 28/01/2022 30/01/2022
8 PERBAIKAN ACP SISI MTEN 23 days 20/12/2021 11/01/2022
9 INSTALLASI DUDUKAN GONDOLA 5 days 20/12/2021 24/12/2021
10 MOBILISASI DAN PEMASANGAN 3 days 25/12/2021 27/12/2021
GONDOLA
11 PEMBONGKARAN ACP RUSAK 5 days 28/12/2021 01/01/2022
12 PRODUKSI ACP 2 days 02/01/2022 03/01/2022
13 PEMASANGAN ACP 3 days 04/01/2022 06/01/2022
14 PEMBONGKARAN GONDOLA 2 days 07/01/2022 08/01/2022
15 PEMBONGKARAN DUDUKAN 3 days 09/01/2022 11/01/2022
GONDOLA

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: 20/12/2021 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
03/01 04/01 05/01 06/01 07/01 08/01 09/01 10/01 11/01 12/01 13/01 14/01 15/01 16/01 17/01 18/01 19/01 20/01 21/01 22/01 23/01 24/01 25/01 26/01 27/01 28/01 29/01 30/01 31/01 01/02

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: 20/12/2021 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2

You might also like