Professional Documents
Culture Documents
Mode Complete 7/27 8/24 9/21 10/19 11/16 12/14 1/11 2/8 3/8
0 CKD Mon 8/10/20 Wed 3/31/21 41%
1 1 Engineering Mon 8/10/20 Fri 12/18/20 75%
2 2 Procurement Fri 8/28/20 Thu 1/21/21 50%
3 3 Construction Thu 12/10/20 Wed 3/17/21 2%
4 3.1 Civil /Concrete Thu 12/10/20 Thu 1/7/21 10%
5 3.2 Silo Installation Mon 12/21/20 Fri 1/1/21 0%
6 3.3 Mechanical Installation Mon 1/11/21 Wed 3/17/21 0%
7 3.4 Electrical Installation Tue 2/9/21 Mon 3/8/21 0%
8 4 Start Up Thu 3/18/21 Wed 3/31/21 0%
Page 1