Manhattan Lift Installation

ID Task Task Name Duration Start Finish August 2023 September 2023
Mode 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19
1 Manhattan Lift A Installation 27 days Tue 8/8/23 Wed 13/9/23 0%
2 Erection of Scaffolding 1 day Tue 8/8/23 Tue 8/8/23 0%
3 Counterweight Guide Rails 3 days Wed 9/8/23 Fri 11/8/23 0%
4 Car Guide Rails 3 days Wed 9/8/23 Fri 11/8/23 0%
5 Platform Installation 2 days Mon 14/8/23Tue 15/8/23 0%
6 Traction Machine Installation 2 days Wed 16/8/23Thu 17/8/23 0%
7 Controller Installation 2 days Wed 16/8/23Thu 17/8/23 0%
8 Counter Weight Installation 2 days Fri 18/8/23 Mon 21/8/23 0%
9 Roping 2 days Tue 22/8/23 Wed 23/8/23 0%
10 Machine Auto Tune 1 day Thu 24/8/23 Thu 24/8/23 0%
11 Demolitions 2 days Fri 25/8/23 Mon 28/8/23 0%
12 Landing Doors Installation 5 days Fri 25/8/23 Thu 31/8/23 0%
13 Builders Work 2 days Fri 1/9/23 Mon 4/9/23 0%
14 Car Door Installation 1 day Tue 5/9/23 Tue 5/9/23 0%
15 Doors Auto Tuning 1 day Wed 6/9/23 Wed 6/9/23 0%
16 Wiring 2 days Wed 6/9/23 Thu 7/9/23 0%
17 Speed Run and Testing 2 days Fri 8/9/23 Mon 11/9/23 0%
18 Inspection & Commissioning 2 days Tue 12/9/23 Wed 13/9/23 0%

Critical Manual Task Baseline Milestone External Tasks

Critical Split Start-only Milestone External Milestone

Critical Progress Finish-only Summary Progress Inactive Task

Task Duration-only Summary Inactive Milestone

Split Baseline Manual Summary Inactive Summary

Task Progress Baseline Split Project Summary Deadline

Page 1

You might also like