CONSTRUCTION AND INSTALLATION OF A SKID MACHINE BASE

ID Task Task Name Duration Start Finish August 2022


Mode 13 16 19 22 25 28 31 3 6 9 12 15 18
1 PROJECT 19 days Mon 7/18/22 Mon 8/8/22 PROJECT
2 MOBILISATION 1 day Mon 7/18/22 Mon 7/18/22 MOBILISATION
3 DEMOLITION 2 days Tue 7/19/22 Wed 7/20/22 DEMOLITION
4 EXCAVATION 4 days Thu 7/21/22 Mon 7/25/22 EXCAVATION
5 CONCRETE WORKS 3 days Tue 7/26/22 Thu 7/28/22 CONCRETE WORKS
6 INSTALLATION OF DRAIN 3 days Fri 7/29/22 Mon 8/1/22 INSTALLATION OF DRAIN PIPE
PIPE
7 CONSTRUCTION OF SUMP 1 day Tue 8/2/22 Tue 8/2/22 CONSTRUCTION OF SUMP
8 REINSTATING 3 days Tue 8/2/22 Thu 8/4/22 REINSTATING
9 TILING 2 days Wed 8/3/22 Thu 8/4/22 TILING
10 INSTALLATION OF MACHINE 2 days Fri 8/5/22 Sat 8/6/22 INSTALLATION OF MACHINE

11 DEMOBILISATION 1 day Mon 8/8/22 Mon 8/8/22 DEMOBILISATION

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Critical
Date: Wed 8/3/22
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1

You might also like