ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020

ary 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 20
1 PROPOSED CONSTRUCTION 182 days Tue 2/25/20 Tue 8/25/20
IN PRIMARYSCHOOLS - DRDIP

2 PRELIMINARIES 14 days Tue 2/25/20 Tue 3/10/20

3 MOBILIZATION 7 days Tue 2/25/20 Tue 3/3/20

4 Establishing of 7 days Tue 2/25/20 Tue 3/3/20


hoardings, stores for
materials, contractor's
site offices with
facilities, scaffolding,
erection of project
sign board Etc.

5 MATERIALS 14 days Tue 2/25/20 Tue 3/10/20


PROCUREMENT
6 FINALIZATION OF 7 days Tue 2/25/20 Tue 3/3/20
MATERIALS(LOCAL
AND IMPORTS)
7 ESTABLISHING OF 7 days Tue 2/25/20 Tue 3/3/20
BORROW PITS AND
MATERIALS APPROVAL

8 IMPORTATION OF 7 days Tue 3/3/20 Tue 3/10/20


MATERIALS
9 2 CLASSROOM BLOCK 164 days Tue 3/10/20 Fri 8/21/20
WITHOUT OFFICE
65 5 STANCE LINED VIP 77 days Fri 5/8/20 Fri 7/24/20
LATRINE (BOYS)
66 SUBSTRUCTURE 25 days Fri 5/8/20 Tue 6/2/20

67 EXCAVATIONS AND 2 days Fri 5/8/20 Sun 5/10/20


EARTHWORKS FOR
SITE PREPARATION
68 EXCAVATIONS AND 2 days Sun 5/10/20 Tue 5/12/20
EARTHWORKS FOR
FOUNDATIONS
69 PLACING HARDCORE 1 day Tue 5/12/20 Wed 5/13/20

Task Inactive Task Manual Summary Rollup External Milestone


Split Inactive Milestone Manual Summary Deadline
Project: Works program_DRDIP Milestone Inactive Summary Start-only Progress
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks

Page 1
ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 20
70 INSITU MASS 1 day Wed 5/13/20 Thu 5/14/20
CONCRETING C15
71 FIXING MESH 1 day Thu 5/14/20 Fri 5/15/20
REINFORCEMENT
72 FIXING HOT ROLLED 2 days Fri 5/15/20 Sun 5/17/20
HIGH YIELD STEEL BAR
REINFORCEMENT

73 FIXING MS BAR 2 days Sun 5/17/20 Tue 5/19/20


REINFORCEMENT
74 SAWN TREATED 1 day Tue 5/19/20 Wed 5/20/20
FORMWORK
75 SAWN FORMWORK 1 day Wed 5/20/20 Thu 5/21/20

76 INSITU REINFORCED 2 days Thu 5/21/20 Sat 5/23/20


CONCRETING C25
77 BRICKWORK 5 days Sat 5/23/20 Thu 5/28/20

78 SUNDRIES 1 day Thu 5/28/20 Fri 5/29/20

79 DPC 1 day Fri 5/29/20 Sat 5/30/20

80 PLINTH WALL AND 2 days Sat 5/30/20 Mon 6/1/20


SPLASH APRON
WORKS
81 PLACING HARDCORE 1 day Mon 6/1/20 Tue 6/2/20

82 ROOF 5 days Tue 6/2/20 Sun 6/7/20

83 ROOF CONSTRUCTION 2 days Tue 6/2/20 Thu 6/4/20

84 ROOF COVERING 1 day Thu 6/4/20 Fri 6/5/20

85 EAVES 1 day Fri 6/5/20 Sat 6/6/20

86 PAINTING 1 day Sat 6/6/20 Sun 6/7/20

Task Inactive Task Manual Summary Rollup External Milestone


Split Inactive Milestone Manual Summary Deadline
Project: Works program_DRDIP Milestone Inactive Summary Start-only Progress
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks

Page 2
ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 20
87 WALLS 10 days Sun 6/7/20 Wed 6/17/20

88 BRICKWORK 7 days Sun 6/7/20 Sun 6/14/20

89 VENTS 1 day Sun 6/14/20 Mon 6/15/20

90 PRECAST CONCRETE 1 day Mon 6/15/20 Tue 6/16/20


UNITS
91 SUPPORT HANDLES 1 day Tue 6/16/20 Wed 6/17/20

92 DOORS 13 days Wed 6/17/20 Tue 6/30/20

93 CONCRETE WORK 1 day Wed 6/17/20 Thu 6/18/20

94 FIXING HOT ROLLED 2 days Thu 6/18/20 Sat 6/20/20


HIGH YIELD STEEL BAR
REINFORCEMENT

95 FIXING MS BAR 2 days Sat 6/20/20 Mon 6/22/20


REINFORCEMENT
96 SAWN TREATED 1 day Mon 6/22/20 Tue 6/23/20
FORMWORK
97 RC INSITU 2 days Tue 6/23/20 Thu 6/25/20
CONCRETING
98 FIXING STEEL DOORS 2 days Thu 6/25/20 Sat 6/27/20

99 IRON MONGERY 1 day Sat 6/27/20 Sun 6/28/20

100 PAINTING STEEL 2 days Sun 6/28/20 Tue 6/30/20


DOORS
101 FLOOR FINISHES 1 day Tue 6/30/20 Wed 7/1/20

102 WALL FINISHES 19 days Wed 7/1/20 Mon 7/20/20

103 INTERNAL WALL 16 days Wed 7/1/20 Fri 7/17/20


FINISHES
Task Inactive Task Manual Summary Rollup External Milestone
Split Inactive Milestone Manual Summary Deadline
Project: Works program_DRDIP Milestone Inactive Summary Start-only Progress
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks

Page 3
ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 20
104 INTERNAL CEMEND 14 days Wed 7/1/20 Wed 7/15/20
AND SAND
PLASTERING

105 PAINTING 2 days Wed 7/15/20 Fri 7/17/20

106 EXTERNAL WALL 3 days Fri 7/17/20 Mon 7/20/20


FINISHES
107 CEMENT AND SAND 1 day Fri 7/17/20 Sat 7/18/20
PLASTERING

108 TYLORENE 1 day Sat 7/18/20 Sun 7/19/20


RENDERING
109 PAINTING 1 day Sun 7/19/20 Mon 7/20/20

110 MECHANICAL 4 days Mon 7/20/20 Fri 7/24/20


INSTALLATIONS
111 DRAINAGE WORKS 2 days Mon 7/20/20 Wed 7/22/20

112 SOIL AND VENT PIPES 2 days Wed 7/22/20 Fri 7/24/20

113 5 STANCE LINED VIP 77 days Fri 5/8/20 Fri 7/24/20


LATRINE (GIRLS)
114 SUBSTRUCTURE 25 days Fri 5/8/20 Tue 6/2/20

115 EXCAVATIONS AND 2 days Fri 5/8/20 Sun 5/10/20


EARTHWORKS FOR
SITE PREPARATION
116 EXCAVATIONS AND 2 days Sun 5/10/20 Tue 5/12/20
EARTHWORKS FOR
FOUNDATIONS
117 PLACING HARDCORE 1 day Tue 5/12/20 Wed 5/13/20

118 INSITU MASS 1 day Wed 5/13/20 Thu 5/14/20


CONCRETING C15
119 FIXING MESH 1 day Thu 5/14/20 Fri 5/15/20
REINFORCEMENT
120 FIXING HOT ROLLED 2 days Fri 5/15/20 Sun 5/17/20
HIGH YIELD STEEL BAR
REINFORCEMENT

Task Inactive Task Manual Summary Rollup External Milestone


Split Inactive Milestone Manual Summary Deadline
Project: Works program_DRDIP Milestone Inactive Summary Start-only Progress
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks

Page 4
ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 20
121 FIXING MS BAR 2 days Sun 5/17/20 Tue 5/19/20
REINFORCEMENT
122 SAWN TREATED 1 day Tue 5/19/20 Wed 5/20/20
FORMWORK
123 SAWN FORMWORK 1 day Wed 5/20/20 Thu 5/21/20

124 INSITU REINFORCED 2 days Thu 5/21/20 Sat 5/23/20


CONCRETING C25
125 BRICKWORK 5 days Sat 5/23/20 Thu 5/28/20

126 SUNDRIES 1 day Thu 5/28/20 Fri 5/29/20

127 DPC 1 day Fri 5/29/20 Sat 5/30/20

128 PLINTH WALL AND 2 days Sat 5/30/20 Mon 6/1/20


SPLASH APRON
WORKS
129 PLACING HARDCORE 1 day Mon 6/1/20 Tue 6/2/20

130 ROOF 5 days Tue 6/2/20 Sun 6/7/20

131 ROOF CONSTRUCTION 2 days Tue 6/2/20 Thu 6/4/20

132 ROOF COVERING 1 day Thu 6/4/20 Fri 6/5/20

133 EAVES 1 day Fri 6/5/20 Sat 6/6/20

134 PAINTING 1 day Sat 6/6/20 Sun 6/7/20

135 WALLS 10 days Sun 6/7/20 Wed 6/17/20

136 BRICKWORK 7 days Sun 6/7/20 Sun 6/14/20

Task Inactive Task Manual Summary Rollup External Milestone


Split Inactive Milestone Manual Summary Deadline
Project: Works program_DRDIP Milestone Inactive Summary Start-only Progress
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks

Page 5
ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 20
137 VENTS 1 day Sun 6/14/20 Mon 6/15/20

138 PRECAST CONCRETE 1 day Mon 6/15/20 Tue 6/16/20


UNITS
139 SUPPORT HANDLES 1 day Tue 6/16/20 Wed 6/17/20

140 DOORS 13 days Wed 6/17/20 Tue 6/30/20

141 CONCRETE WORK 1 day Wed 6/17/20 Thu 6/18/20

142 FIXING HOT ROLLED 2 days Thu 6/18/20 Sat 6/20/20


HIGH YIELD STEEL BAR
REINFORCEMENT

143 FIXING MS BAR 2 days Sat 6/20/20 Mon 6/22/20


REINFORCEMENT
144 SAWN TREATED 1 day Mon 6/22/20 Tue 6/23/20
FORMWORK
145 RC INSITU 2 days Tue 6/23/20 Thu 6/25/20
CONCRETING
146 FIXING STEEL DOORS 2 days Thu 6/25/20 Sat 6/27/20

147 IRON MONGERY 1 day Sat 6/27/20 Sun 6/28/20

148 PAINTING STEEL 2 days Sun 6/28/20 Tue 6/30/20


DOORS
149 FLOOR FINISHES 1 day Tue 6/30/20 Wed 7/1/20

150 WALL FINISHES 19 days Wed 7/1/20 Mon 7/20/20

151 INTERNAL WALL 16 days Wed 7/1/20 Fri 7/17/20


FINISHES
152 INTERNAL CEMEND 14 days Wed 7/1/20 Wed 7/15/20
AND SAND
PLASTERING

Task Inactive Task Manual Summary Rollup External Milestone


Split Inactive Milestone Manual Summary Deadline
Project: Works program_DRDIP Milestone Inactive Summary Start-only Progress
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks

Page 6
ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 20
153 PAINTING 2 days Wed 7/15/20 Fri 7/17/20

154 EXTERNAL WALL 3 days Fri 7/17/20 Mon 7/20/20


FINISHES
155 CEMENT AND SAND 1 day Fri 7/17/20 Sat 7/18/20
PLASTERING

156 TYLORENE 1 day Sat 7/18/20 Sun 7/19/20


RENDERING
157 PAINTING 1 day Sun 7/19/20 Mon 7/20/20

158 MECHANICAL 4 days Mon 7/20/20 Fri 7/24/20


INSTALLATIONS
159 DRAINAGE WORKS 2 days Mon 7/20/20 Wed 7/22/20

160 SOIL AND VENT PIPES 2 days Wed 7/22/20 Fri 7/24/20

161 10,000L WATER TANK 14 days Fri 7/24/20 Fri 8/7/20

162 TANK BASE WORKS 3 days Fri 7/24/20 Mon 7/27/20

163 FIXING MS BAR 2 days Mon 7/27/20 Wed 7/29/20


REINFORCEMENT
164 FIXING MS STEEL 2 days Wed 7/29/20 Fri 7/31/20
REINFORCEMENT
165 FORM WORK 1 day Fri 7/31/20 Sat 8/1/20

166 RC INSITU CONCRETING 3 days Sat 8/1/20 Tue 8/4/20

167 WALLING 1 day Tue 8/4/20 Wed 8/5/20

168 FINISHES 1 day Wed 8/5/20 Thu 8/6/20

169 TANK INSTALLATION 1 day Thu 8/6/20 Fri 8/7/20

Task Inactive Task Manual Summary Rollup External Milestone


Split Inactive Milestone Manual Summary Deadline
Project: Works program_DRDIP Milestone Inactive Summary Start-only Progress
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks

Page 7
ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 20
170 EXTERNAL WORKS 14 days Fri 8/7/20 Fri 8/21/20

171 LANDSCAPING 10 days Fri 8/7/20 Mon 8/17/20

172 STORM WATER 4 days Mon 8/17/20 Fri 8/21/20


DRAINAGE
173 COMMISSIONING/FINAL 4 days Fri 8/21/20 Tue 8/25/20
HANDING OVER
174 INSPECTION OF WORKS 3 days Fri 8/21/20 Mon 8/24/20

175 FINAL HANDING OVER 1 day Mon 8/24/20 Tue 8/25/20

Task Inactive Task Manual Summary Rollup External Milestone


Split Inactive Milestone Manual Summary Deadline
Project: Works program_DRDIP Milestone Inactive Summary Start-only Progress
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks

Page 8

You might also like