Professional Documents
Culture Documents
• Disadvantages
– Problems with unbalanced bids / unit
rates
– Risk of quantity variations
– Need for precise measurement of work
performed which requires more
supervision efforts
Uses
Open-ended emergency situations
(earthquakes, floods)
High risk and uncertainty
(war, tunnelling)
Ill-defined, high return projects
(private sector)
Most construction projects
• Disadvantages
– Inappropriate (in basic form) for competitive
bidding (see target cost)
– With fixed fee, no incentive for quality or timely
work
– With % fee, no incentive to limit costs
– Additional employer staff needed to monitor costs
Value Certainty
for Money of Time
Functional
Reliability
Clear
Accountability
Status of design
Standard documents
Most suitable
Inappropriate or less suitable
By Specification
Project Manager
By Specification
Engineer
Suppliers
Consultant’s
Team Contractor Nominated
Subcontractors
Site Engineer
Domestic Subcontractors
NEW ROLE
PROJECT DESIGNER
MANAGER
SUPERVISION
OF ADJUDICATOR PROJECT
CONSTRUCTION MANAGER DESIGNER
SUPERVISION
OF
CONSTRUCTION ADJUDICATOR
Turnkey Contract
Similar to Design + Build but can include total fitting-out ready for
occupation
BOO/BOT/BOOT/Concession Contract
Using investor funds or partnership agreements to construct
operating project handed to PE after stipulated period
Advantages:
Early mobilisation Disadvantages:
Rapid start Difficult to have competitive tendering
Easy Variation Fee system can reduce incentive
Basis and system for payment Contractor avoids risks
agreed High quality PE’s Staff essential to
Direct Control
ensure quality and expenditure control
TURNKEY
2-stage tendering normal
Contractor’s responsible up to taking over
BOT/CONCESSIONARY
Contractor is responsible for successful outcome
low
Procurement Management Training-
20/8/2014 24
MRB/MRB- South Sudan/ H. Labadi
FLOWCHART OF ADJUCATION/
ARBITRATION
Dispute
Dispute or
or Difference
Difference Under
Under the
the
Contract
Contract
Referral
Referral to
to Adjudicator
Adjudicator (within
(within 14
14
days
days of
of PM’s
PM’s decision)
decision)
Notice
Notice ofof Adjudication
Adjudication //
Recommendation
Recommendation (within
(within 28
28 days
days of
of
receipt
receipt of
of aa notification
notification of
of above
above
difference)
difference)
N Dispute
Dispute to
to be
be referred
referred
Adjudicator’s
Adjudicator’s o to
to Arbitration
Arbitration
Decision
Decision
agreed Yes 28
agreed within
within 28 Arbitral
Arbitral award
award executed
executed
Adjudicator’s
Adjudicator’s
days Decision
days Decision by
by National
National Court
Court
Final
Final &
& Binding
Binding
20/8/2014 Procurement Management Training- 25
MRB/MRB- South Sudan/ H. Labadi
COMPLETION OF CONTRACT
Intended
Issue of Defects Correction
Start Date Completion DateCompletion Date
Submission of final Certificate and Certificate of
(1.1) (1.1) (1.1)
account (57.1) Final Payment (57.1)
56 days