Professional Documents
Culture Documents
Administration
RICS Dubai
06 November 2019
Presented by: Kieran Chauhan BSc (Hons), MSc, FRICS, FCIArb
Kieran@hepher.com
www.hepher.com
About the Speaker
Kieran Chauhan BSc (Hons), MSc, FRICS, FCIArb
Partner at Hepher Associates Limited, a Claims, Dispute Resolution and Contracts
Specialist Consultant based in Dubai.
Fellow of the RICS (FRICS), a Fellow of the CIArb (FCIArb), BSc in QS&CM and a Masters
Degree in Construction Law and Dispute Resolution.
Learning Outcomes
Understand the differences between the different types of Claims in Construction;
What is a Claim?
Delay Claims
Acceleration Claims
Disruption Claims
Federal Law No. 10 of 1992 Civil and Commercial Transactions Law concerning the
Law of Evidence
FIDIC 2017 - Sub-clause 20.1 and 20.2 – see next slides for extract
Cause and effect - the claiming party has the evidential burden to
— Show a contractual entitlement to claim
— Demonstrate that the facts trigger the contractual entitlement to claim
— Establish delay/costs incurred
Only proven losses can be recovered - speculative claims are inadmissible
Types of Claims in Construction
Basis for a Claim – Applicable to ALL
Unsuitable procurement
Unrealistic deadlines
Refusal to collaborate/cooperate
Types of Claims in Construction
Contracts
What contracts do you use?
FIDIC Conditions of Contract for Construction for Building and Engineering Works
Designed by the Employer Second Edition 2017
Baseline Programme
Extended TFC
Types of Claims in Construction
Delay Claims
Baseline Programme
It’s when the work being performed must be done at a quicker pace than planned.
However, acceleration could also become necessary if the scope of work increases
during the life of the project;
Generally, the instruction to accelerate work will come via change order.
Types of Claims in Construction
Acceleration Claims
that are made as a result of the costs associated with speeding up work;
When work must be accelerated during the life of the project, the compensation for
that acceleration leads to acceleration claims by the parties performing that work.
Types of Claims in Construction
Acceleration Claims
Types of Acceleration?
Excusable delay -> EOT requested -> EOT refused -> Constructive Acceleration
Types of Claims in Construction
Variation Claims
Variations
Variation (sometimes referred to as a variation instruction, variation order (VO) or change order);
Almost all construction projects vary from the original design, scope and definition.
Alterations to quantities.
Alterations to quality.
If disruption is caused by the employer, the contractor may have grounds to seek
compensation.
Delay relates to lateness rather than productivity, although they can often be
related. Delays can cause disruptions, and vice versa. Despite their inter-
relation, they require a different approach to assessing claims.
Types of Claims in Construction
Disruption Claims
Disruption
Which element of the works and which trades have been disrupted, why losses
occurred, and so on.
Measured mile analysis: Compares actual labour performance between two periods
– a normal measured mile period and an impacted period.
Earned value analysis: Compares the amount and cost of work that was planned to
have been done by a particular stage with the amount that has actually been done
and what it has actually cost.
Types of Claims in Construction
Prolongation Cost Claims
Definition?
the term ‘prolongation’ refers to 'the extended duration of the works during which
time-related costs are incurred as a result of a delay’;
RECAP
Excusable delays
Baseline Programme
Extended TFC
Types of Claims in Construction
Liquidated Damages Claims
Definition?
FIDIC 2017 - "Delay Damages" means the damages for which the Contractor shall be
liable under Sub-Clause 8.8 [Delay Damages] for failure to comply with Sub-Clause 8.2
[Time for Completion].
A typical clause will provide that should the contractor fail to complete by a date
stipulated in the contract, or any extended date, he shall pay or allow the employer to
deduct liquidated damages at the rate of ‘X’ per day, or week, for the period during which
the works remain uncompleted.
Under UAE law, despite what the parties may have agreed, the court (or an arbitrator)
has the ability retrospectively to change that agreement, to ensure that the damages are
equal to the loss that has been suffered. The parties are not able to contract out of this.
Cause,
Effect,
Entitlement
and Substantiation.
Demonstrating these matters in claim documents is KEY otherwise Claim may FAIL
Forms of Contracts Administration
Contract establishment
Planning
Specification development
Contract documentation
Forms of Contracts Administration
Post-award Contract Administration duties:
Payment approval
Change Management
Dispute Resolution
Contract Close-out
Methodologies
DA Methodologies
CA will also support DA methodology to support claims for time and/or costs;
There are numerous forensic schedule analysis methods that can be used to
quantify delays that occurred during a project. The most common delay
analysis methods are as follows:
Impacted As-Planned
Windows Analysis
Records,
Records and;
Records
Significance of Contracts Administration in Claims
https://issuu.com/constructionbusinessnewsme/docs/fullmag_cbnme0518_issuu
Significance of Contracts Administration in Claims
Monitoring Contractor performance
How is this done?
Programme
Site logs
Significance of Contracts Administration in Claims
Monitoring Contractor performance
Types of Programmes
The Contractor’s Programme or ‘Baseline’ Programme
• Most forms of contract require the contractor to submit a programme within a stipulated time frame
(FIDIC Red Book 28 days)
• Programme will become the baseline against which to measure delays
Revised programmes
• Should circumstances affect the programme – additional work, re-sequencing of the work, delays,
etc. – then the programme may be revised accordingly
• The programme should also be revised to take into account extensions of time
Updated programmes
• Updated programmes should be produced and submitted to the Engineer on a regular (monthly)
basis
• An updated programme, or as-built programme, will record the actual progress up to the data-date of
the update and predict the events after the data-date of the update
Significance of Contracts Administration in Claims
Correspondence / records filing
Types of Correspondence
Letters / Notices;
Reports;
Meeting minutes;
Instructions;
Submittals;
RFI’s etc.
Significance of Contracts Administration in Claims
Letters / Notices – What Constitutes an Effective Notice
Generally:
Ideally one letter per notice (do not bundle multiple notices)
Meeting Minutes can be relied upon but should not replace formal notices.
A poor notice is better than no notice at all – ideally must comply with CA
Make it timely
Significance of Contracts Administration in Claims
Timebars
Definition:
A limit in time as to when an action may be taken, such as claiming for Time and
Costs on a construction project.
Most contracts in the UAE have time bar clauses for example FIDIC 2017:
Significance of Contracts Administration in Claims
Timebars
Defence:
Freedom of contract and contracts to be interpreted in accordance with their terms
Defence:
Freedom of contract and contracts to be interpreted in accordance with their terms