Full definition:
• a binding agreement between two or more persons
or parties; especially : one legally enforceable
• a business arrangement for the supply of goods or
services at a fixed price
PBC - Workshop CPD HPJI 5 Septermber 2016 4
Elements of Contract
• Offer
• Acceptance
• Considerations
Object
• Quality
• quantity
Terms and Conditions
CONTRACTOR
SUB- SPECIALTY-
SUPPLIERS
CONTRACTOR CONTRACTOR
• Contract types:
Based on Organization of Agreement
(conventional, design-build, CM, BOT)
Based on Method of Cost Calculation and Reimbursement of fee
(lump sum, unit price, cost plus fee)
Based on Method of Reimbursement/Payment
(monthly certificate, progress payment)
OWNER
CONTRACTOR
Lump Sum
Contract (w/ Guarantee Guarantee
Lump Sum Lump Sum many Unit Price Maximum Maximum Cost-Plus- Cost-Plus-
Contract Contract w/ Changes) Cost w/ Cost w/ Fixed Fee Percent Fee
w/o Some OR Sharing Sharing
Changes Changes Cost-Plus Clause Clause
w/ (50/50) (75/25)
Guarantee
Maximum
Cost
COST + % FEE
MAX
MAX
Cost variance only on change orders and claims Cost variance, price, quantity, efficiency
LUMP SUM Schedule variance Schedule variance
Earned value on schedule of values for determining Earned value on schedule of values for determining
payments payments
In Indonesia:
• Higher education – Performance Based Contract – World Bank
• Indonesia: Managing Higher Education for Relevance and Efficiency
• I-MHERE (2005-2012)
Development of PBC in Road Projects
• 1988 British Columbia, Canada
• 1990 Argentina (Toll Concessions)
G. Zietlow
• 1994-98 Uruguay, Chile, Argentina (PBC),
Colombia, Brazil, Peru
• 1995 Australia (Sydney), Estonia, Denmark
• 1996 USA (Virginia)
• 1998 New Zealand, Finland
• 2000/1 Chad, Zambia, England, India, Spain
• 2012 Vietnam
• 2013 Indonesia
PBC - Workshop DIREKTORAT JENDERAL BINA KONSTRUKSI
Characteristics of Performance Based Contract
• Characteristics of PBC:
Outcome oriented – long-term
Clearly defined objective
Clearly defined timeframe
NOT to specify activities to be performed
Performance monitoring
Promote innovation (efficiency – effectiveness) – performance
incentive
PBC - Workshop DIREKTORAT JENDERAL BINA KONSTRUKSI 5 Septermber 2016 18
Key issues in Performance Based Contract
• What is performance?
Must be measurable and quantifiable
It is NOT merely an (exact) output
• Assuring Performance
Provider proposed method and mechanism
Level of performance/service
• minimum, average, incremental, decrement?
Mechanism for monitoring
PBC - Workshop DIREKTORAT JENDERAL BINA KONSTRUKSI 5 Septermber 2016 20
Considerations in Applying PBC in Road Projects
• Defining performance
Who’s responsibility, at what level, are there standards?
• Contractual Arrangement
Structure and complexity of owner (agency)
Planning and budgeting
Control over condition of on-service period (trans-agencies)
System and mechanism for measuring performance, acceptance
System and mechanism for compensation
TRANSPORTATION
AUTHORITY
INSURANCE AGENCY
SURETY
AGENCIES CONTRACTOR
• Selection of provider
Selection shall not be based on lowest cost ONLY – beauty
contest
Past performance
Capacity (capital and operational)
Method/technology, program and management
……….