Professional Documents
Culture Documents
CONTRACT
MANAGEMENT
Once defined, the project scope will need to be packaged into “contract packages”. These contract packages
must be structured with at least the following in mind:
• The capability of contractors in the market to tender and manage the structured packages within a
competitive environment and with reasonable levels of risk exposure;
• The ability of the employer to manage the number of contracts as well as the necessary interfaces between
the packages;
• The identification of work packages for targeted sub-vendor groups;
• The dependencies, timing and management of access for the provision of works and services as well as the
allocation and management of risks to parties best placed to manage mitigations;
Three basic contracting arrangements for
engineering and construction projects
Traditional LMC
(Limited Multiple Contracts)
• The owner directly engages different contractors for designing the scope of work and for construction of the
work in accordance with the design.
EPC
Typically when to use
(Engineer, Procure, Construct)
• The owner directly engages a single contractor for • Scope is well defined
designing the works and for construction of the works • Schedule is not top priority
in accordance with the design.
• Cost control is high priority
• The contractor usually performs all or most of the • Strong owner team is not available
work, but could also subcontract parts of it. • Owner wishes to utilise EPC financing support for
the project
Contracting arrangements depends on circumstances and environment (socio-economic, funding, programs etc.).
Organisations and even projects may have a hybrid of LMC, EPC and EPCM contracting arrangements.
From Packaging Strategy to Contracting Options
EPCM EPC
(Engineering, Procurement & Construction Management) (Engineer, Procure, Construct/’Turnkey’)
Cost Reimbursable Contracts (or Cost Plus) Time and Material (T&M) Contracts (Unit Price Contracts) Fixed Price Contracts
Cost Plus Costs Plus Fixed Price - Economic
Percentage of Costs Plus Fixed Costs Plus Award Incentive Fee Fixed Price Incentive Price Adjustment Firm Fixed Price
Costs (CPPC) Fee (CPFF) Fee (CPAF) (CPIF) Cost Contract (CR) Cost-sharing Contract (CS) Firm (FPI) (FPEPA) (FFP)
Cost Plus --- Cost --- Rates & Target Cost --- Bill of Quantities --- Lump Sum
Verbal (or poorly drafted contracts) + high risk events = the need for deep pockets
Verbal or a poorly drafted agreements result in more disputes, delays, and the costs and frustrations of litigation.
Standard forms of contract provide for a written contract, evolved and improved over decades and often tested
internationally, for the clearest possible terms of exactly what is agreed to, especially as it concerns risk.
Note: Use of standard forms of contract often a requirement e.g. via Construction Industry Development Board
(CIDB), National Treasury’s Standard for Infrastructure Procurement and Delivery Management.
Provisions usually catered for in Standard Forms of
Engineering and Construction Contracts
Standard forms of contract, apart from dealing with rights and duties of
parties to the contract, commonly make provision for matters such as:
• Changes, to works/ services/ goods requirements and when
particular events occur or circumstances arise, after the formation of
a contract;
• Risk allocation for each party and how the contractor is
compensated for risk events for which the contractor is not carrying
the risk;
• Procedures to address, inter alia:
• assessments of amounts due
• defects, acceleration, completion etc.
• determining impact on time and cost
• termination
• resolution of disputes
• Roles of those besides the parties e.g. an agent of the employer.
Providers of standard forms of contract
South African:
SAICE (GCC)
the South African Institution of Civil Engineering (SAICE) develops, publishes and
maintains the GCC (General Conditions of Contract for Construction Works).
JBCC
Joint Building Contracts Committee
Note: There are also at times other
forms of standard contracts, monopoly
CIDB supplier contracts and circumstances
requiring ‘bespoke’ contracts (e.g. self-
Construction Industry Development Board build agreements with customers),
which may be applicable / suitable.
NEC3 ‘books’ containing conditions of contract
‘the black book’ is used where
Works construction works is NOT simple or of
low risk, low cost and short duration (e.g.
for main package of new terminal at
conditions of contract
international airport)
Services
conditions of contract Engineering &
Construction Contract
( ECC )
Supply
conditions of contract
Professional Services Engineering & Construction
Contract Subcontract Supply Contract
( PSC ) ( ECS ) ( SC )
Professional Services Supply Short
Short Contract Contract
( PSSC ) ( SSC )
CORE CLAUSES
1 General Similar for other
2 The Contractor’s main responsibilities NEC3 conditions of
3 Time contract.
4 Testing and Defects
5 Payment
6 Compensation events
7 Title
8 Risks and insurance
9 Termination
DISPUTE RESOLUTION
Option W1 – Used by Eskom
OPTION Y
NOT used by Eskom (related to United Kingdom requirements)
Cost Reimbursable Contracts (or Cost Plus) Time and Material (T&M) Contracts (Unit Price Contracts) Fixed Price Contracts
Cost Plus Costs Plus Fixed Price - Economic
Percentage of Costs Plus Fixed Costs Plus Award Incentive Fee Fixed Price Incentive Price Adjustment Firm Fixed Price
Costs (CPPC) Fee (CPFF) Fee (CPAF) (CPIF) Cost Contract (CR) Cost-sharing Contract (CS) Firm (FPI) (FPEPA) (FFP)
Cost Plus --- Cost --- Rates & Target Cost --- Bill of Quantities --- Lump Sum
EPCM EPC
(Engineering, Procurement & Construction Management) (Engineer, Procure, Construct/’Turnkey’)
Option X2
Changes in the law
Yes Yes Yes Yes
Option X3
Multiple currencies
Yes Option A & B Yes Option A & G Yes Option A Yes
Option X4
Parent company guarantee Yes Yes Yes Yes
Option X5
Sectional Completion Yes Yes Option G N/A N/A
Option X6
Bonus for early Completion Yes Yes Option G N/A N/A
Option X7
Delay damages
Yes Yes N/A Yes
Option X8
Collateral warranty agreements
N/A Yes N/A N/A
Option X9
Transfer of Rights
N/A Yes N/A N/A
Option X10
Employer’s Agent
N/A Yes N/A N/A
NEC3 Secondary Option Clauses
Any and many of the secondary options may be selected:
Option X12
Partnering
Yes Yes Yes Yes
Option X13
Performance bond
Yes Yes Yes Yes
Option X14
Advanced payment t o Yes N/A N/A Yes
Contractor/Supplier
Option X15
Limitation of Contractor’s Yes N/A N/A N/A
liability for his design to
reasonable skill and care
Option X16
Retention Yes, not for Option F N/A N/A N/A
Option X17
Low performance
Yes N/A Yes Yes
[service/performance] damages
Option X18
Limitation of liability
Yes Yes Yes N/A
Option X19
Task Order
N/A N/A Yes N/A
Option X20
Key Performance Indicators
Yes, not with Option Yes, not with Option Yes, not with Yes, not with Option
X12 X12 Option X12 X12
Typical Relationships with NEC3 (ECC)
Project
Manager
Communication
Legend:
Contract
Contractual
communication
requirements
Other Supervisor
NEC documents via Eskom Intranet and in Hyperwave
(for use and population, NOT editing)
Includes
Includes notifications, Eskom’s
certificates etc. standard Z Clauses
NEC conditions of contract
(sometimes for use as learners, NOT copying or editing)