Professional Documents
Culture Documents
Lecture 2
Learning Objectives
4
Fixed-Price Contracts
• CCDC 2 – 2008 Stipulated Price Contract
• Standard prime contract between Owner and prime
Contractor to perform the required work for a single, pre
determined fixed price or lump sum, regardless of the
Contractor’s actual costs.
• CCDC 2MA – 2016 Master Agreement and Work Authorization
• CCDC 2MA is developed to meet the needs of Owners with an
on-going construction or maintenance program: to enter into
specific work arrangements quickly and easily, without having
to review and re-negotiate general terms and conditions for
each work order.
• The Master Agreement is a contract form between Owner and
Contractor that is applicable for a defined period of time and
is intended to establish contractual terms and conditions
(excluding scope, time and cost) for multiple projects during
that time period.
• Each project will be ordered by means of Work
Authorizations, that define the project specific requirements
like scope, price, time.
6
Cost Plus Fee: Advantage/DisAdvantages
• Potential advantages for owners:
• Costs may be lower than fixed price because of favorable risk allocation on
contractors.
• Protections under best efforts/fiduciary duties, as well as contractor duties of
good faith and fair dealings.
• Potential disadvantages for owners:
• Uncertain final project cost.
• Insufficient incentives for the contractor to control or reduce costs.
• Higher administrative costs on owner.
Figure 14.3
17
Design-Build vs. Fixed Priced
Figure 14.3
18
Project Delivery: Design-Build
• Increasingly popular delivery method.
• Owner provides performance specifications to Design-
Builder.
• Different relationship between owner and designer.
• Owner’s interests and “bridging.”
• Actual delivery method versus labeled delivery
method.
23
Project Delivery:
Teaming Agreements
• Contract between a prime and another firm that agrees to act as a
potential subcontractor for the purposes of a bid on a federal
contract.
• Context: Primarily, federal government contracts.
• Issue: Agreements to agree versus agreements to negotiate in good
faith.
30
Claims and Disputes
Lecture 2B
Claims and Disputes
• Construction projects are increasingly competitive and
complex, and delivered in a risky and sometimes
adversarial environment.
• Many construction projects face considerable claims and
disputes, along with increasing difficulty in resolving such
disputes in an effective, timely and economic manner.
• Valuable resources are diverted towards the preparation
of claims, settlement of disputes and participation in
arbitration or litigation.
• The net result is time wasted in a non-value-added effort.
Claims and Disputes
• A claim can be defined as a request for additional
financial compensation and/or a request for a time
extension.
• Most claims are resolved at the project level by negotiation
between the parties themselves.
• A claim that cannot, or is not, resolved by negotiation at
the project level becomes a dispute.
• Unresolved claims can be adjudicated through adversarial
techniques such as arbitration or litigation, or by using less
adversarial methods such as mediation.
Typical Causes of Claims and Disputes
• The first major contributor to claims and disputes is the hesitancy to
spend effort clarifying the scope and terms of work during initial
project phases resulting in changes to design, scope, and schedule
during construction.
• The second major contributor is the unclear communication of
contract intentions causing misunderstandings regarding the risks and
responsibilities assigned to the contracting parties.
Typical Causes of Claims and Disputes
• Typical causes of claims and disputes • Inadequate bid information;
that counsel and clients need to • Underestimation, mismanagement
consider include: and/or bad workmanship by
• Lack of project planning and contractors;
inadequate design; • Misunderstanding of contract
• Design changes, errors, omissions, intentions, terms, and conditions or
and extras; contract interpretation;
• Lack of coordination between project • Various kinds of project delays some
teams/contractors; of which are compensable, some of
• Changed soil/site conditions /ground which are non-compensable;
conditions; • Late permits;
• The combination of a fixed-price • Weather conditions; and
contract and fast-tracking; • Unforeseen events such as the
• Insufficient bid preparation time; current Covid-19 pandemic.
Claims and Disputes
• A good understanding of contract and negligence law helps
professionals not only in analyzing and resolving disputes but also in
avoiding disputes in the first place.
• In some situations, claims and disputes are unavoidable.
• A party can become insolvent or bankrupt and be unable to pay.
• The professions of architecture and engineering, are by their very
nature risky.
• The risks of accident, failure, financial loss, and unforeseen results
are always present.
Tort Claims in Construction
• Common tort claims in construction include:
• Negligence
• Misrepresentation
• Interference with contract or prospective advantage
• Premises liability
• Liability for hirer of independent contractor;
• Products liability
D = Defendant; P = Plaintiff.
© 2015 Cengage Learning Engineering. All Rights Reserved. 39
Elements of Negligence: Standard of Conduct
• Is a defined set of rules, principles, values, employee expectations,
behaviors, and relationships that a business considers important and
believes necessary for its success.
• Architects and engineers are held to standards for their profession, higher
than for society as a whole.
• In determining the standard of conduct, balance the magnitude of the
risk with the utility of the conduct and the burden of eliminating the
risk.
• In comparison; A code of ethics is broader, providing a set of
principles that affect employee mindset and decision-making.
• A code of conduct offers principles defining the ethics of a business,
but it also contains specific rules for employee actions and behavior.