Professional Documents
Culture Documents
This unit describes the various aspects of preparing, It is the responsibility of the contractor to:
awarding, and managing coating contracts. It also • Provide complete and conforming work.
discusses how owner and contractor personnel work • Complete the project by the agreed-upon date.
together in this process. • Provide a warranty for the work, as specified.
3-1
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
–– Additional requirements for complete and documents to decide if they wish to bid on the job.
usable product. They then prepare bids (also called proposals),
• Develop procedures that will result in complete often in a standard format, in confidence and submit
and conforming product. them in sealed envelopes for the owner to examine
• Verify procedures, and modify plan as required. and compare with the bids received from other
• Execute to the plan contractors. Although the lowest qualified bidder is
• Identify and correct nonconformities. normally awarded the contract other factors may
• Perform Corrective Action (CA) to identify root have a bearing on the decision to award. If the
cause(s) and eliminate nonconformities. lowest bid price is significantly higher or lower than
• Document complete and conforming product. the owner’s estimate, the owner must determine if
• Submit invoice and project closeout certifications there was an estimating error or if there were owner-
that: contractor differences in interpretation of specification
–– Verifies correction of all non- requirements. Well-prepared contracts should have
conformities. a relatively small range of bid estimates. To be sure,
–– Verifies documentation of complete and contractors hungry for work are more likely to bid
conforming product. lower than those who are otherwise busy or who find
the project less than desirable.
It is beneficial when the contractor identifies problems
with the plans and specifications early in the planning The competitive bidding process has been the
process, rather than creates a crisis during production. contracting vehicle of choice for many decades and
When contracts are administered with appropriate will remain a significant force in the future. The
expectations, crises will occur only very rarely, and will theory in competitive contracting is that, by allowing
not normally slow progress. In fact, it is a reasonable contractors to compete in terms of managerial and
expectation that there will be very, very few crises technical skills, the most efficient contractor will
in a properly planned project. This will allow the submit the lowest bid and be awarded the contract.
owner sufficient time to make informed decisions on Sometimes, however, this is not the case:
technical issues, including involvement of the designer
as necessary. • Unqualified contractors submit lower bids, either
because they do not understand the requirements
Types of Contracts or do not intend to produce complete and
conforming products.
There are two basic types of construction contracts:
• Qualified contractors take additional risks to bid
competitive bid and direct selection and many
low on work using unverified processes.
variations of each. The term bid also means tender.
3-2
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
• Qualifying each succeeding step. for design and construction. The contracting team is
• Identifying both conforming and nonconforming selected based on such factors as capabilities and
products. experience, as well as bid price.
Penalty Clauses
Design-build is a variation of direct selection in which
the owner executes a single contract with one entity Penalty clauses are often included in coating
(designer-builder) to provide both architectural/ contracts when late completion of a project would
engineering services and construction services. It is create problems, such as loss of revenue or delay
also known as a design-construct and single source other important activities. Typically, penalty clauses
or single responsibility method of contracting. The require the contractor to pay a fixed amount of money
owner or owner’s consultant establishes the physical per day (or week) for each day (or week) by which
requirements, and the contracting team is responsible the contract exceeds its scheduled completion date.
3-3
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Amounts may vary from $250 per day to $10,000 their own expense, to expose, test, and ultimately
depending on the size and character of the project. remove and replace work that does not meet
The owner, of course, has no trouble collecting these specification requirements. If the controversy
fees, because they are merely deducted from the cannot be readily resolved, it may even become
payment given to the contractor upon completion and necessary for the owner to hire another contractor
acceptance of the project. to make these corrections. Since such adversarial
actions may be quite costly to all, they must be
Performance and Payment Bonds well documented and undertaken only when no
alternative approach works.
Often, particularly in the public sector, an owner will
• Withholding payment. The withholding payment
require a contactor to post a “bond” as a safeguard to
clause is an alternative approach that may be
ensure successful completion of a project. The bond
used as an adversarial action. The grounds for
is a promise, made by a third party (often an insurance
withholding payment, which also must be well
company), to complete a project if a contractor
documented, often include failure to provide the
becomes financially unstable or otherwise fails to
specified quality work.
perform under the contract. There is a cost associated
• Removal of unqualified contractor personnel.
with procuring the bond which, depending on the type
This clause can be used to require the contractor
of work, generally amounts to approximately 1% of
to remove from the project contractor personnel
the total cost of a project. Since bonding companies
who have been shown to be incompetent,
use care to assess a contractor’s capabilities and
careless, or otherwise detrimental to completion
available assets before they obligate themselves, by
of work.
virtue of being able to provide a bond, a contractor
• Requiring personal contractor supervision.
establishes credibility.
This clause directs the contractor to assume
personal supervision of the work. It is used
Enforcement Clauses
when the owner finds that existing supervision is
The partnering relationship described in Unit 1 is inadequate to meet project requirements.
preferred to using contract enforcement clauses to • Halting work. This clause directs the contractor to
obtain satisfactory work. However, it is important halt any item of the work until existing deficiencies
that the owner have the ability to employ enforcement in the work and/or the QMS are satisfactorily
clauses when necessary. While owners must pay corrected.
the contractor for quality work meeting specification • Terminating (defaulting) the contract. This
requirements, they are not under any obligation clause is the most drastic enforcement action
to pay for work that does not conform to contract that can be taken and should be used only as
provisions. Enforcement actions, however, should a last resort. Another contractor is then hired
only be invoked after careful determination that these to complete the work. When specified contract
actions are necessary: conditions have either been met or not met,
depending on the contract language, the owner
• Removal and replacement of low quality
is said to place the contractor into “default”. If
materials. This clause requires contractors, at
3-4
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
the contractor has provided a “bond”, then the according to the agreed unit price. This method is
bonding company would be asked to take the appropriate for both competitive bidding and direct
contractor’s place and complete the project. selection contracts.
Methods of Contract Payment In a variation of the unit price, the contractor may
quote a fixed rate for labor and rental of equipment,
There are several methods of contractor payment and
and may provide the materials at “no cost” or “cost
several variations to each. In all cases, arrangements
plus” rates. These “time and materials contracts” are
for payment should be agreed upon before any work
discussed in Unit 6.
is started.
3-5
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Table 3-1
Time Allocated for Contracting Activities Before Start of Work
Activity Time Allocated
Pre-qualifying contractors * 8 weeks
Preparing specification 6 weeks
Advertising for bids 4 weeks
Pre-bid conference 2 weeks
Receiving bids 2 weeks
Reviewing bids 1 week
Awarding contract 1 week
Pre-construction conference 2 weeks
Coordination meeting 2 weeks
3-6
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
• Submit copies of annual reports and/or a list participating contractors to implement and document
of past projects with the total billable for each more stringent (ISO 9001 Compliant) quality control
• Provide information on procedures for record- SSPC-QP 1, SSPC-QP 3, etc. However, unlike
keeping, contract estimation, and scheduling of ISO 9001 certification, QS-1 provides the facility
• Provide evidence of bonding capability. specific Quality Management System (QMS) model
• State whether the firm has any current or for contractors who have the operational capability
impending legal actions. required by QP 1 plus the ISO 9001 compliant QMS
detailed in QS 1.
Contractor Certification Program) certification. SSPC of quality control for their projects may request that
has established qualification programs for coating contractors already qualified to standards such
particular type of coating work: present evidence that their quality systems meet the
requirements of QS 1.
• QP 1 Standard Procedure for Evaluating
Qualifications of Painting Contractors (Field
The PCCP certification process requires about 4 to
Application to Complex Structures)
6 weeks, when all steps proceed smoothly. These
• QP 2 Field Removal of Hazardous Coatings
steps are:
• QP 3 Standard Procedure for Evaluating
• Contractor submits application and required
Qualifications of Shop Painting Applicators
documentation.
• QP 6 Standard Procedure for Evaluating
• SSPC reviews and accepts application and
Contractors who Apply Thermal Spray (Metallizing)
submittals.
for Corrosion Protection to Steel and Concrete
• Auditor evaluates contractor headquarters, field,
Surfaces
and/or shop operations.
• QP 8 Standard Method of Evaluating Contracting
• Auditor conducts exit interview.
Firms that Install Polymer Coatings and Surfacings
• SSPC reviews audit findings to determine
on Concrete and other Cementitious Substrates
conformance with standard.
3-7
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Preparing the Specification the work details. The bidders may ask for additional
information about the project and the specification
Preparing coating project specifications was discussed
requirements.
in detail in Unit 2.
3-8
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
3-9
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
References
1. U.S. Army Corps of Engineers, Control #784, Construction Quality Management for Contractors, August
2004.
2. UFGS-01450N, Construction Quality Control, August 2004.
3. Drisko, Richard W. and Jenkins, James F., “Preparing a Specification for a Coating Project,” Chapter 10.4.
SSPC Painting Manual, Volume 1, Good Painting Practices, pp 521-529, Pittsburgh, PA, 2002.
3-10
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Bond
A promise of performance made by a responsible third-party guaranteeing completion of a contract. Usually offered
by an insurance company but can be in the form of a cash deposit or the pledge of other forms of security.
Contract
Written agreement between parties, usually between an owner and a contractor, to produce a specified end
product for a certain amount of value received. This is the fundamental principle of contracting.
Enforcement Clause
Portion of contract compelling specific action.
Incentive Clause
Portion of contract rewarding contractor for special action.
Lump-Sum Payment
Method of contract payment in which a single, total payment is made to the contractor upon completion of the
work.
PCCP
SSPC’s Painting Contractor Certification Program. (QP1, QP2, QP3, QP6, QP8)
3-11
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Penalty Clause
Portion of contract specifying negative consequences to a contractor for failure to meet specification
requirements.
Retainage
Or “Retained Money.” Portion of payments withheld from contractor until a time when all specified contract
requirements have been met.
Staged Money
Portion of total payment made to contractor upon completion of a given step on time during a project.
3-12
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Unit 3 Workshops
The contractor’s production forces keep applying less than the specified thickness of lining on the interior of a
fuel tank and show no indication of taking any corrective actions. Discuss various approaches available under
the contract to the owner to obtain the specified thickness.
You, as the owner’s representative for a water company, are responsible for preparing and securing a contract
for lining the interiors of four potable water storage tanks. The work is to be done in the winter when water
requirements are lowest, and it is important to complete the work as quickly as possible to obtain the minimum
down time for each tank. Discuss what type of a contract and what type of clauses, and method of payment
would you use to accomplish your goals.
The owner has required the contractor to clean and paint some areas not included in the specification. How
shall the contractor proceed to receive payment for this extra work?
3-13
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
3-14
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
a. Lump sum.
b. Unit price.
c. Cost plus fixed fee.
d. Cost plus percent.
a. Lump sum.
b. Unit price.
c. Cost plus fixed fee.
3-15
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
12. When is the unit price method of payment most commonly used?
a. All bidders can gain a complete understanding of the owner’s expectations at the same
time.
b. All bidders can negotiate their bids at the same time.
c. All bidders can select the same method of bid preparation.
d. All bidders can present their proposed project work plans at the same time.
3-16
Unit 3 Preparing, Awarding, and Managing Coating Contracts
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Topics
PLANNING AND SPECIFYING
INDUSTRIAL COATINGS PROJECTS
• Basics of contracting
(For Owners and Contractors)
• Types of contracts
• Special contract clauses
Unit 3 • Methods of contract payment
Preparing, Awarding, and • Owner contracting actions
Managing Coating Contracts • Preparing the specification
• This unit describes the various aspects • After completing this unit, students will
of preparing, awarding, and managing be able to:
coating contracts. It also discusses how − Describe the different types of contracts
owner and contractor personnel work and contract payments.
together in this process. − Recognize the basic steps in the
contracting process.
Owner Responsibility
Contract
in Contracting
• A written agreement, usually between • Fully identify desired product and estimate
an owner and a contractor, to produce a its cost.
specified end product. • Procure the necessary funding.
• Prepare specification precisely describing
the scope of work, technical requirements,
and level of quality expected.
• Take actions to select contractor, evaluate
proposals, and award a contract.
C2 Planning and Specifying Industrial Coatings Projects
3-17
Unit 3 Preparing, Awarding, and
Managing Coatting
Unit 3 Preparing, Awarding, and Managing Coating Contracts
Contracts
Owner Responsibilities in
Contractor Contract Responsibilities
Contracting (cont’d.)
• Manage the contract to support the • Provide complete and conforming work.
contractor in completing it. • Complete the project by the agreed-
• Take appropriate actions to ensure upon date.
contract completion. • Provide a warranty for the work, as
• Accept satisfactorily completed work and specified.
make payment for it.
Minimum Requirements to
Contractor QMS Requirements
Fulfill These Tasks
• Contractor must: • When QMS is required, contractors must:
− Review contract for discrepancies, omissions, − Plan and prepare to produce complete and
etc. conforming product.
− Perform complete project planning. − Identify contract discrepancies for resolution
− Develop procedures to ensure project is early in planning process.
complete and conforming. − Develop procedures that will result in complete
− Verify those procedures before starting work, or and conforming product.
in the beginning stages of work. − Verify procedures and modify plan as required.
− Inspect verify, and document work throughout − Execute to the plan.
the project.
Contractor QMS
Basic Contracts
Requirements (Cont’d.)
• When QMS is required, contractors also • Competitive bid
must: • Direct selection (negotiated)
− Identify and correct nonconformities.
− Document complete and conforming
product.
− Submit invoice and project closeout
certifications verifying correction of all
nonconformities and documentation of
complete and conforming product.
C2 Planning and Specifying Industrial Coatings Projects
3-18
Unit 3 Preparing, Awarding, and Managing Coating Contracts
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Enforcement Clauses:
Enforcement Clauses
Removal or Replacement
• A tool only invoked after careful • Contractors, at their own expense, are
determination: required to expose, test, and ultimately
− Removal or replacement of materials remove or replace work that does not
− Withholding payment meet specification requirements
− Removal of unqualified personnel • Owner may have to hire another
− Requiring personal contractor supervision contractor to accomplish this but only
− Halting work when no other alternative works.
− Terminating work
C2 Planning and Specifying Industrial Coatings Projects
C2 Planning and Specifying Industrial Coatings Projects
3-19
Unit 3 Preparing, Awarding, and Managing Coatting Contracts
Unit 3 Preparing, Awarding, and Managing Coating Contracts
Enforcement Clauses:
Methods of Contract Payment
Terminating (Defaulting) Contract
C2 Planning and Specifying Industrial Coatings Projects
3-20
Unit3 3Preparing,
Unit Preparing,Awarding,
Awarding, and
and Managing
Managing Coatting
Coating Contracts
Contracts
C2 Planning and Specifying Industrial Coatings Projects
3-21
Unit 3 Preparing, Awarding, and
Managing Coatting Unit 3 Preparing, Awarding, and Managing Coating Contracts
Contracts
Means of Verifying
SSPC PCCP Certifications
Financial Stability
• Copies of annual reports and/or list of • QP 1 Painting Contractors (Field Application
to Complex Structures)
past projects and their billings.
• QP 2 Standard Procedure for Evaluating the
• Procedures for record-keeping, cost Qualifications of Painting Contractors to
estimation, and scheduling of work. Remove Hazardous Paint
• Evidence of bonding capability. • QP 3 Shop Painting Applicators
• Information on any current or impending • QP 6 Contractors Metallizing Steel and
legal actions. Concrete Surfaces
• QP 8 Contractors Installing Polymer
Surfacings to Cementitious Surfaces
C2 Planning and Specifying Industrial Coatings Projects
3-22
Unit33Preparing,
Unit Preparing, Awarding,
Awarding, and
and Managing
ManagingCoatting
CoatingContracts
Contracts
• A contract is a written agreement, usually • The pre-bid conference ensures all bidders
between an owner and a contractor, to receive the same information.
produce a specified end product. • The pre-construction conference and
• Competitive bid and direct-selection are the coordination meeting clarify the specification
two basic types of contracts. and contract clauses for the bid winner. This
• Contracts may include incentive, penalty, and also allows the owner to review the
enforcement clauses. contractor’s work plan, QMS plan, and safety
• Lump sum, unit price, cost plus fixed fee or plan and request modifications when
percentage, staged payments, and retained necessary.
money are all contract payment methods.
C2 Planning and Specifying Industrial Coatings Projects
3-23