Professional Documents
Culture Documents
CONTRACT USED IN
CONSTRUCTION INDUSTRY
Type of Contract
Management
contract Cost-Reimbursement
contract
the price to
be paid is fixed
scope of work
indicated on drawings
No additional
variation or omission
no bill of quantities
is provided
This type useful when project work is not too large, can be precisely
described and few alteration occur during construction
LUMP SUM CONTRACT
• The contractor has more incentive to reduce his cost to increase the profit.
• For example, STA Bhd offer the contractor to do bridge painting work and pavement marking.
This project can use lump sump contract because the project is not to large and can be
described.
• This contract is ideal when the project scope is well defined at the design stage because there is
limited flexibility for modifying the design during construction period.
a. Bill of quantities contract b. Schedules of rates
• the target estimate may be adjusted for variation in quantity and design and
fluctuations in the cost of labor and material, etc.
• the actual fee paid to the contractor is arrive by increasing or reducing the basic fee
by an agreed percentage of the saving or excess between the actual cost and the
adjustment target estimate.
• In some cases, a bonus or penalty based on the time of completion may be applied.
Cost plus percentage contract
• the contractor is paid the actual cost of the work plus an agreed
percentage to cover overhead, profit etc.
• The sum paid to the contractor will be the actual cost incurred in the
execution of the work plus a fixed lump sum which has been previously
agreed.
• No incentive to the contractor if the work can be completed early.
@nurkamaliahmustaffa2013
COST REIMBURSEMENT CONTRACT
• Divided into three types: Cost + percentage fee contract, Cost + fixed fee contract, Target + cost contract.
• Allowable and reasonable cost incurred by a contractor in the performance of a contract.
• The final cost will be determined when the contract is completed.
• A total cost estimate will determined before contract work commences to allow them to set budget for the
project.
• Only the actual cost of completing the contract are covered.
• Contractor did not receives any additional fee.
• Time, labor and materials are highly uncertain to perform the contract.
• Useful in emergency work because insufficient time to prepare a detailed document tender or drawing before
work is commenced.
• No incentive for the contractor if the project can be completed early.
• Tendering proceed based on outline specification, any previous drawing, and an estimates cost.
• Example : Interstate 5 Skagit River Bridge collapsed into the river. Several innovations led to the successful
handling of the emergency and the restoration of the Skagit River Bridge
Advantages of Disadvantages of
management Management Contract management
contract contract
• Contractor expertise
available to design • Final cost of
team. The management contractor is usually a project not
• Construction can construction company and paid known at outset
commerce before predetermining fees and expenses to: as design
design is complete as • Participate in the project from the overlaps with
work let in package. outset construction.
• Useful where complex • Contribute construction expertise to • If management
contract require many design contractor does
design groups and • Manage the construction not have the
contractor- required
management of the The management contractor does not expertise he may
whole process is normally undertake any of the not be able to
controlled by the construction work, but lets specific contribute to the
management packages of work to other contractors design.
contractor/consultant. usually by competitive tender, and
• Time target more supervises their work.
easily met as later
packages of the work
can be adjusted. This type useful for big project which have a lot of works.
MANAGEMENT CONTRACT
• Project management contractor (PMC) is generally appointed by client at early design process as an
principal.
• PMC is paid predetermining fees and expense to participate in the project from the outset, contribute
construction expertise to design & manage the construction.(they control the whole process)
• Does not normally undertake any of the construction work but specific packages of work to other
contractors usually by competitive tender and supervises their work.
• Time target more easily met as later packages of the work can be adjusted but the final cost uncertainly
until the design complete.
∙ The contractor can use their own in-house designers, consultant to complete the design
∙ Client can also choose their own contractor for specific work (Nominated-sub contractor)
∙ This contract allow a fully integrated team to work together from the beginning.
∙ Example project: Mass Rapid Transit (MRT) & PLUS Expressway- (built operate and transfer)
PAST YEAR QUESTIONS
JUNE 2016
DECEMBER 2016
PAST YEAR QUESTIONS
JULY 2017
JUNE 2018
DECEMBER 2018
PAST YEAR QUESTIONS
JUNE 2019